Civil Engineering (CE) Exam  >  Civil Engineering (CE) Questions  >  If the scheduled completion time for a partic... Start Learning for Free
If the scheduled completion time for a particular project is 18 weeks and its earliest expected time is 20 weeks, then the slack time for the project is
  • a)
    2 weeks
  • b)
    0
  • c)
    -2 weeks
  • d)
    None of the above
Correct answer is option 'C'. Can you explain this answer?
Verified Answer
If the scheduled completion time for a particular project is 18 weeks ...
Slack = 18 - 20 = -2 weeks
View all questions of this test
Most Upvoted Answer
If the scheduled completion time for a particular project is 18 weeks ...
Explanation:
Slack time is the amount of time a project activity can be delayed without delaying the entire project completion time. It is calculated as the difference between the earliest expected time and the scheduled completion time.

Given, the scheduled completion time for the project is 18 weeks and the earliest expected time is 20 weeks.

Therefore, the slack time for the project can be calculated as follows:

Slack time = Earliest expected time - Scheduled completion time
Slack time = 20 weeks - 18 weeks
Slack time = -2 weeks

This means that the project activity cannot be delayed by more than 2 weeks without affecting the entire project completion time. Therefore, option C, -2 weeks, is the correct answer.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

If the scheduled completion time for a particular project is 18 weeks and its earliest expected time is 20 weeks, then the slack time for the project isa)2 weeksb)0c)-2 weeksd)None of the aboveCorrect answer is option 'C'. Can you explain this answer?
Question Description
If the scheduled completion time for a particular project is 18 weeks and its earliest expected time is 20 weeks, then the slack time for the project isa)2 weeksb)0c)-2 weeksd)None of the aboveCorrect answer is option 'C'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about If the scheduled completion time for a particular project is 18 weeks and its earliest expected time is 20 weeks, then the slack time for the project isa)2 weeksb)0c)-2 weeksd)None of the aboveCorrect answer is option 'C'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for If the scheduled completion time for a particular project is 18 weeks and its earliest expected time is 20 weeks, then the slack time for the project isa)2 weeksb)0c)-2 weeksd)None of the aboveCorrect answer is option 'C'. Can you explain this answer?.
Solutions for If the scheduled completion time for a particular project is 18 weeks and its earliest expected time is 20 weeks, then the slack time for the project isa)2 weeksb)0c)-2 weeksd)None of the aboveCorrect answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of If the scheduled completion time for a particular project is 18 weeks and its earliest expected time is 20 weeks, then the slack time for the project isa)2 weeksb)0c)-2 weeksd)None of the aboveCorrect answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of If the scheduled completion time for a particular project is 18 weeks and its earliest expected time is 20 weeks, then the slack time for the project isa)2 weeksb)0c)-2 weeksd)None of the aboveCorrect answer is option 'C'. Can you explain this answer?, a detailed solution for If the scheduled completion time for a particular project is 18 weeks and its earliest expected time is 20 weeks, then the slack time for the project isa)2 weeksb)0c)-2 weeksd)None of the aboveCorrect answer is option 'C'. Can you explain this answer? has been provided alongside types of If the scheduled completion time for a particular project is 18 weeks and its earliest expected time is 20 weeks, then the slack time for the project isa)2 weeksb)0c)-2 weeksd)None of the aboveCorrect answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice If the scheduled completion time for a particular project is 18 weeks and its earliest expected time is 20 weeks, then the slack time for the project isa)2 weeksb)0c)-2 weeksd)None of the aboveCorrect answer is option 'C'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev