The Optimistic Time (O), Most likely Time (M) and Pessimistic Time (P) (in days) of the activities in the critical path are given below in the format O-M-P.
The expected completion time (in days) of the project is _________
    Correct answer is between '37,38'. Can you explain this answer?
    Verified Answer
    The Optimistic Time (O), Most likely Time (M) and Pessimistic Time (P)...
    Expected completion time of the project = 10.33 + 8.16 + 7.16 + 12.16
    = 37.81 days
    View all questions of this test
    Explore Courses for Civil Engineering (CE) exam

    Top Courses for Civil Engineering (CE)

    The Optimistic Time (O), Most likely Time (M) and Pessimistic Time (P) (in days) of the activities in the critical path are given below in the format O-M-P.The expected completion time (in days) of the project is _________Correct answer is between '37,38'. Can you explain this answer?
    Question Description
    The Optimistic Time (O), Most likely Time (M) and Pessimistic Time (P) (in days) of the activities in the critical path are given below in the format O-M-P.The expected completion time (in days) of the project is _________Correct answer is between '37,38'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about The Optimistic Time (O), Most likely Time (M) and Pessimistic Time (P) (in days) of the activities in the critical path are given below in the format O-M-P.The expected completion time (in days) of the project is _________Correct answer is between '37,38'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The Optimistic Time (O), Most likely Time (M) and Pessimistic Time (P) (in days) of the activities in the critical path are given below in the format O-M-P.The expected completion time (in days) of the project is _________Correct answer is between '37,38'. Can you explain this answer?.
    Solutions for The Optimistic Time (O), Most likely Time (M) and Pessimistic Time (P) (in days) of the activities in the critical path are given below in the format O-M-P.The expected completion time (in days) of the project is _________Correct answer is between '37,38'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
    Here you can find the meaning of The Optimistic Time (O), Most likely Time (M) and Pessimistic Time (P) (in days) of the activities in the critical path are given below in the format O-M-P.The expected completion time (in days) of the project is _________Correct answer is between '37,38'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The Optimistic Time (O), Most likely Time (M) and Pessimistic Time (P) (in days) of the activities in the critical path are given below in the format O-M-P.The expected completion time (in days) of the project is _________Correct answer is between '37,38'. Can you explain this answer?, a detailed solution for The Optimistic Time (O), Most likely Time (M) and Pessimistic Time (P) (in days) of the activities in the critical path are given below in the format O-M-P.The expected completion time (in days) of the project is _________Correct answer is between '37,38'. Can you explain this answer? has been provided alongside types of The Optimistic Time (O), Most likely Time (M) and Pessimistic Time (P) (in days) of the activities in the critical path are given below in the format O-M-P.The expected completion time (in days) of the project is _________Correct answer is between '37,38'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The Optimistic Time (O), Most likely Time (M) and Pessimistic Time (P) (in days) of the activities in the critical path are given below in the format O-M-P.The expected completion time (in days) of the project is _________Correct answer is between '37,38'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
    Explore Courses for Civil Engineering (CE) exam

    Top Courses for Civil Engineering (CE)

    Explore Courses
    Signup for Free!
    Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
    10M+ students study on EduRev