If the optimistic time, most likely time and pessimistic times for activity A are 8,12 and 16 respectively and for activity B are 10,11 and 18 respectively, then
  • a)
    Expected time of activity A is greater than the expected time of activity B
  • b)
    Expected time of activity B is greater then the expected time of activity A
  • c)
    Expected time of both activities A and B are same
  • d)
    None of the above
Correct answer is option 'C'. Can you explain this answer?
Verified Answer
If the optimistic time, most likely time and pessimistic times for act...
te(for A) =
te(for B) =
View all questions of this test
Most Upvoted Answer
If the optimistic time, most likely time and pessimistic times for act...
Explanation:

Expected Time Calculation:
- Expected time = (Optimistic Time + 4 * Most Likely Time + Pessimistic Time) / 6

Calculation for Activity A:
- Expected time for Activity A = (8 + 4*12 + 16) / 6 = 12

Calculation for Activity B:
- Expected time for Activity B = (10 + 4*11 + 18) / 6 = 11.5

Comparison:
- Expected time of Activity A = 12
- Expected time of Activity B = 11.5
Therefore, the expected time of both activities A and B is the same. So, option 'C' is the correct answer.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

If the optimistic time, most likely time and pessimistic times for activity A are 8,12 and 16 respectively and for activity B are 10,11 and 18 respectively, thena)Expected time of activity A is greater than the expected time of activity Bb)Expected time of activity B is greater then the expected time of activity Ac)Expected time of both activities A and B are samed)None of the aboveCorrect answer is option 'C'. Can you explain this answer?
Question Description
If the optimistic time, most likely time and pessimistic times for activity A are 8,12 and 16 respectively and for activity B are 10,11 and 18 respectively, thena)Expected time of activity A is greater than the expected time of activity Bb)Expected time of activity B is greater then the expected time of activity Ac)Expected time of both activities A and B are samed)None of the aboveCorrect answer is option 'C'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about If the optimistic time, most likely time and pessimistic times for activity A are 8,12 and 16 respectively and for activity B are 10,11 and 18 respectively, thena)Expected time of activity A is greater than the expected time of activity Bb)Expected time of activity B is greater then the expected time of activity Ac)Expected time of both activities A and B are samed)None of the aboveCorrect answer is option 'C'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for If the optimistic time, most likely time and pessimistic times for activity A are 8,12 and 16 respectively and for activity B are 10,11 and 18 respectively, thena)Expected time of activity A is greater than the expected time of activity Bb)Expected time of activity B is greater then the expected time of activity Ac)Expected time of both activities A and B are samed)None of the aboveCorrect answer is option 'C'. Can you explain this answer?.
Solutions for If the optimistic time, most likely time and pessimistic times for activity A are 8,12 and 16 respectively and for activity B are 10,11 and 18 respectively, thena)Expected time of activity A is greater than the expected time of activity Bb)Expected time of activity B is greater then the expected time of activity Ac)Expected time of both activities A and B are samed)None of the aboveCorrect answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of If the optimistic time, most likely time and pessimistic times for activity A are 8,12 and 16 respectively and for activity B are 10,11 and 18 respectively, thena)Expected time of activity A is greater than the expected time of activity Bb)Expected time of activity B is greater then the expected time of activity Ac)Expected time of both activities A and B are samed)None of the aboveCorrect answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of If the optimistic time, most likely time and pessimistic times for activity A are 8,12 and 16 respectively and for activity B are 10,11 and 18 respectively, thena)Expected time of activity A is greater than the expected time of activity Bb)Expected time of activity B is greater then the expected time of activity Ac)Expected time of both activities A and B are samed)None of the aboveCorrect answer is option 'C'. Can you explain this answer?, a detailed solution for If the optimistic time, most likely time and pessimistic times for activity A are 8,12 and 16 respectively and for activity B are 10,11 and 18 respectively, thena)Expected time of activity A is greater than the expected time of activity Bb)Expected time of activity B is greater then the expected time of activity Ac)Expected time of both activities A and B are samed)None of the aboveCorrect answer is option 'C'. Can you explain this answer? has been provided alongside types of If the optimistic time, most likely time and pessimistic times for activity A are 8,12 and 16 respectively and for activity B are 10,11 and 18 respectively, thena)Expected time of activity A is greater than the expected time of activity Bb)Expected time of activity B is greater then the expected time of activity Ac)Expected time of both activities A and B are samed)None of the aboveCorrect answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice If the optimistic time, most likely time and pessimistic times for activity A are 8,12 and 16 respectively and for activity B are 10,11 and 18 respectively, thena)Expected time of activity A is greater than the expected time of activity Bb)Expected time of activity B is greater then the expected time of activity Ac)Expected time of both activities A and B are samed)None of the aboveCorrect answer is option 'C'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev