Question Description
In a PERT distribution, the optimistic time is 4 days, expected time is 7 days and the pessimistic time is 11 days. The variance of the network is_______.a)8.17b)1.16c)5.44d)1.36Correct answer is option 'D'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared
according to
the Civil Engineering (CE) exam syllabus. Information about In a PERT distribution, the optimistic time is 4 days, expected time is 7 days and the pessimistic time is 11 days. The variance of the network is_______.a)8.17b)1.16c)5.44d)1.36Correct answer is option 'D'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for In a PERT distribution, the optimistic time is 4 days, expected time is 7 days and the pessimistic time is 11 days. The variance of the network is_______.a)8.17b)1.16c)5.44d)1.36Correct answer is option 'D'. Can you explain this answer?.
Solutions for In a PERT distribution, the optimistic time is 4 days, expected time is 7 days and the pessimistic time is 11 days. The variance of the network is_______.a)8.17b)1.16c)5.44d)1.36Correct answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE).
Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of In a PERT distribution, the optimistic time is 4 days, expected time is 7 days and the pessimistic time is 11 days. The variance of the network is_______.a)8.17b)1.16c)5.44d)1.36Correct answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of
In a PERT distribution, the optimistic time is 4 days, expected time is 7 days and the pessimistic time is 11 days. The variance of the network is_______.a)8.17b)1.16c)5.44d)1.36Correct answer is option 'D'. Can you explain this answer?, a detailed solution for In a PERT distribution, the optimistic time is 4 days, expected time is 7 days and the pessimistic time is 11 days. The variance of the network is_______.a)8.17b)1.16c)5.44d)1.36Correct answer is option 'D'. Can you explain this answer? has been provided alongside types of In a PERT distribution, the optimistic time is 4 days, expected time is 7 days and the pessimistic time is 11 days. The variance of the network is_______.a)8.17b)1.16c)5.44d)1.36Correct answer is option 'D'. Can you explain this answer? theory, EduRev gives you an
ample number of questions to practice In a PERT distribution, the optimistic time is 4 days, expected time is 7 days and the pessimistic time is 11 days. The variance of the network is_______.a)8.17b)1.16c)5.44d)1.36Correct answer is option 'D'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.