If optimistic time (O) to paint is 2hr. , most likely time (M) is 3 hr. , pessimistic time to paint is 5 hr. , AThen using PERT the approximate expected time (Te) to paint a room ? ans is 3.2 hrs. Can any one explain?
Most Upvoted Answer
If optimistic time (O) to paint is 2hr. , most likely time (M) is 3 hr...
PERT (Program Evaluation and Review Technique) is a project management tool that is used to estimate the time required to complete a task. It takes into account the optimistic time (O), most likely time (M), and pessimistic time (P) to calculate the expected time (Te) for completing the task.

Given data:
- Optimistic time (O) = 2 hours
- Most likely time (M) = 3 hours
- Pessimistic time (P) = 5 hours

Calculating the expected time (Te):
The formula to calculate the expected time (Te) using PERT is:
Te = (O + 4M + P) / 6

Substituting the given values into the formula:
Te = (2 + 4(3) + 5) / 6
Te = (2 + 12 + 5) / 6
Te = 19 / 6
Te ≈ 3.2 hours

Therefore, the approximate expected time (Te) to paint the room using PERT is 3.2 hours.

Explanation:
1. Optimistic time (O):
The optimistic time (O) is the minimum time required to complete the task. In this case, it is 2 hours. It assumes that everything will go perfectly without any delays or issues.

2. Most likely time (M):
The most likely time (M) is the time that is considered to be the most realistic estimate for completing the task. In this case, it is 3 hours. It takes into account the normal working conditions and assumes that there might be some minor delays or issues.

3. Pessimistic time (P):
The pessimistic time (P) is the maximum time required to complete the task. In this case, it is 5 hours. It considers the worst-case scenario where there might be significant delays, issues, or unforeseen circumstances.

4. Expected time (Te):
The expected time (Te) is calculated using the PERT formula. It gives a weighted average estimate of the time required to complete the task, considering all three time estimates (O, M, P). The formula takes into account the most likely time (M) more heavily than the optimistic time (O) and pessimistic time (P).

Conclusion:
Using the PERT technique, the approximate expected time (Te) to paint the room is calculated to be 3.2 hours. This estimate takes into account the best-case, most likely, and worst-case scenarios to provide a realistic expectation of the time required for the task.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

If optimistic time (O) to paint is 2hr. , most likely time (M) is 3 hr. , pessimistic time to paint is 5 hr. , AThen using PERT the approximate expected time (Te) to paint a room ? ans is 3.2 hrs. Can any one explain?
Question Description
If optimistic time (O) to paint is 2hr. , most likely time (M) is 3 hr. , pessimistic time to paint is 5 hr. , AThen using PERT the approximate expected time (Te) to paint a room ? ans is 3.2 hrs. Can any one explain? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about If optimistic time (O) to paint is 2hr. , most likely time (M) is 3 hr. , pessimistic time to paint is 5 hr. , AThen using PERT the approximate expected time (Te) to paint a room ? ans is 3.2 hrs. Can any one explain? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for If optimistic time (O) to paint is 2hr. , most likely time (M) is 3 hr. , pessimistic time to paint is 5 hr. , AThen using PERT the approximate expected time (Te) to paint a room ? ans is 3.2 hrs. Can any one explain?.
Solutions for If optimistic time (O) to paint is 2hr. , most likely time (M) is 3 hr. , pessimistic time to paint is 5 hr. , AThen using PERT the approximate expected time (Te) to paint a room ? ans is 3.2 hrs. Can any one explain? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of If optimistic time (O) to paint is 2hr. , most likely time (M) is 3 hr. , pessimistic time to paint is 5 hr. , AThen using PERT the approximate expected time (Te) to paint a room ? ans is 3.2 hrs. Can any one explain? defined & explained in the simplest way possible. Besides giving the explanation of If optimistic time (O) to paint is 2hr. , most likely time (M) is 3 hr. , pessimistic time to paint is 5 hr. , AThen using PERT the approximate expected time (Te) to paint a room ? ans is 3.2 hrs. Can any one explain?, a detailed solution for If optimistic time (O) to paint is 2hr. , most likely time (M) is 3 hr. , pessimistic time to paint is 5 hr. , AThen using PERT the approximate expected time (Te) to paint a room ? ans is 3.2 hrs. Can any one explain? has been provided alongside types of If optimistic time (O) to paint is 2hr. , most likely time (M) is 3 hr. , pessimistic time to paint is 5 hr. , AThen using PERT the approximate expected time (Te) to paint a room ? ans is 3.2 hrs. Can any one explain? theory, EduRev gives you an ample number of questions to practice If optimistic time (O) to paint is 2hr. , most likely time (M) is 3 hr. , pessimistic time to paint is 5 hr. , AThen using PERT the approximate expected time (Te) to paint a room ? ans is 3.2 hrs. Can any one explain? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev