The optimistic, most likely and pessimistic time estimates of activity are 8, 15 and 18 weeks respectively. The Probable range of completion time of the activity will be
  • a)
    5.99 to 22.67 weeks
  • b)
    8.54 to 18.59 weeks
  • c)
    9.32 to 19.34 weeks
  • d)
    10.20 to 20.31 weeks
Correct answer is option 'C'. Can you explain this answer?
Most Upvoted Answer
The optimistic, most likely and pessimistic time estimates of activity...
Calculation of Probable Range
- To calculate the probable range of completion time, we use the formula:
Probable time = (Optimistic + 4*Most Likely + Pessimistic) / 6

Given data:
- Optimistic time = 8 weeks
- Most Likely time = 15 weeks
- Pessimistic time = 18 weeks

Calculation:
Probable time = (8 + 4*15 + 18) / 6
Probable time = (8 + 60 + 18) / 6
Probable time = 86 / 6
Probable time = 14.33 weeks
Therefore, the probable range of completion time of the activity is from 9.32 to 19.34 weeks, which is option 'C'.
Free Test
Community Answer
The optimistic, most likely and pessimistic time estimates of activity...
Concept:
The expected completion time (tE)

Where,
t0 = optimistic time, tL = most likely time
tP = pessimistic time
The probable range is from (te - 3σ) to (te + 3σ)   
σ is Standard Deviation
Solution:
The expected completion time (tE)​

The Probable range of completion time of the activity will be from (t− 3σ) t o(t+ 3σ)
i.e. (14.33 - 3 × 1.67) to (14.33 + 3 × 1.67)
9.32 weeks to 19.34 weeks
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

The optimistic, most likely and pessimistic time estimates of activity are 8, 15 and 18 weeks respectively. The Probable range of completion time of the activity will bea)5.99 to 22.67 weeksb)8.54 to 18.59 weeksc)9.32 to 19.34 weeksd)10.20 to 20.31 weeksCorrect answer is option 'C'. Can you explain this answer?
Question Description
The optimistic, most likely and pessimistic time estimates of activity are 8, 15 and 18 weeks respectively. The Probable range of completion time of the activity will bea)5.99 to 22.67 weeksb)8.54 to 18.59 weeksc)9.32 to 19.34 weeksd)10.20 to 20.31 weeksCorrect answer is option 'C'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about The optimistic, most likely and pessimistic time estimates of activity are 8, 15 and 18 weeks respectively. The Probable range of completion time of the activity will bea)5.99 to 22.67 weeksb)8.54 to 18.59 weeksc)9.32 to 19.34 weeksd)10.20 to 20.31 weeksCorrect answer is option 'C'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The optimistic, most likely and pessimistic time estimates of activity are 8, 15 and 18 weeks respectively. The Probable range of completion time of the activity will bea)5.99 to 22.67 weeksb)8.54 to 18.59 weeksc)9.32 to 19.34 weeksd)10.20 to 20.31 weeksCorrect answer is option 'C'. Can you explain this answer?.
Solutions for The optimistic, most likely and pessimistic time estimates of activity are 8, 15 and 18 weeks respectively. The Probable range of completion time of the activity will bea)5.99 to 22.67 weeksb)8.54 to 18.59 weeksc)9.32 to 19.34 weeksd)10.20 to 20.31 weeksCorrect answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of The optimistic, most likely and pessimistic time estimates of activity are 8, 15 and 18 weeks respectively. The Probable range of completion time of the activity will bea)5.99 to 22.67 weeksb)8.54 to 18.59 weeksc)9.32 to 19.34 weeksd)10.20 to 20.31 weeksCorrect answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The optimistic, most likely and pessimistic time estimates of activity are 8, 15 and 18 weeks respectively. The Probable range of completion time of the activity will bea)5.99 to 22.67 weeksb)8.54 to 18.59 weeksc)9.32 to 19.34 weeksd)10.20 to 20.31 weeksCorrect answer is option 'C'. Can you explain this answer?, a detailed solution for The optimistic, most likely and pessimistic time estimates of activity are 8, 15 and 18 weeks respectively. The Probable range of completion time of the activity will bea)5.99 to 22.67 weeksb)8.54 to 18.59 weeksc)9.32 to 19.34 weeksd)10.20 to 20.31 weeksCorrect answer is option 'C'. Can you explain this answer? has been provided alongside types of The optimistic, most likely and pessimistic time estimates of activity are 8, 15 and 18 weeks respectively. The Probable range of completion time of the activity will bea)5.99 to 22.67 weeksb)8.54 to 18.59 weeksc)9.32 to 19.34 weeksd)10.20 to 20.31 weeksCorrect answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The optimistic, most likely and pessimistic time estimates of activity are 8, 15 and 18 weeks respectively. The Probable range of completion time of the activity will bea)5.99 to 22.67 weeksb)8.54 to 18.59 weeksc)9.32 to 19.34 weeksd)10.20 to 20.31 weeksCorrect answer is option 'C'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev