The time required to complete an activity under abnormal or extremely adverse conditions in which everything goes wrong is called
  • a)
    optimistic time
  • b)
    most likely time
  • c)
    pessimistic time
  • d)
    None of the above
Correct answer is option 'C'. Can you explain this answer?
Most Upvoted Answer
The time required to complete an activity under abnormal or extremely ...
Pessimistic time:
  • The estimate of the maximum possible time taken by activity if there is a delay at every stage except natural hazards is called pessimistic time.
  • It is denoted by the letter tp.
Optimistic time: 
  • This is to estimate the minimum possible time in which an activity can be completed in an ideal condition. In other words it the shortest time for the completion of an activity. It is denoted by to.
  • it does not include any type of delay or setback at any stage.
Most likely time: 
  • The most probable estimate of time which an activity may take for its completion under normal conditions. It is denoted by tm.
  • This is the time estimate usually obtained by experienced engineers.
  • It does include normal delay or setback which is a common thing to execute a project.
Expected time or Average time: 
  • The average time taken by activity if it is repeated many times. It is denoted by te.
  • The average time indicates that there is a fifty-fifty chance for its completion within its time schedule.
  • It is determined by the following formula = ​
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

The time required to complete an activity under abnormal or extremely adverse conditions in which everything goes wrong is calleda)optimistic timeb)most likely timec)pessimistic timed)None of the aboveCorrect answer is option 'C'. Can you explain this answer?
Question Description
The time required to complete an activity under abnormal or extremely adverse conditions in which everything goes wrong is calleda)optimistic timeb)most likely timec)pessimistic timed)None of the aboveCorrect answer is option 'C'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about The time required to complete an activity under abnormal or extremely adverse conditions in which everything goes wrong is calleda)optimistic timeb)most likely timec)pessimistic timed)None of the aboveCorrect answer is option 'C'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The time required to complete an activity under abnormal or extremely adverse conditions in which everything goes wrong is calleda)optimistic timeb)most likely timec)pessimistic timed)None of the aboveCorrect answer is option 'C'. Can you explain this answer?.
Solutions for The time required to complete an activity under abnormal or extremely adverse conditions in which everything goes wrong is calleda)optimistic timeb)most likely timec)pessimistic timed)None of the aboveCorrect answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of The time required to complete an activity under abnormal or extremely adverse conditions in which everything goes wrong is calleda)optimistic timeb)most likely timec)pessimistic timed)None of the aboveCorrect answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The time required to complete an activity under abnormal or extremely adverse conditions in which everything goes wrong is calleda)optimistic timeb)most likely timec)pessimistic timed)None of the aboveCorrect answer is option 'C'. Can you explain this answer?, a detailed solution for The time required to complete an activity under abnormal or extremely adverse conditions in which everything goes wrong is calleda)optimistic timeb)most likely timec)pessimistic timed)None of the aboveCorrect answer is option 'C'. Can you explain this answer? has been provided alongside types of The time required to complete an activity under abnormal or extremely adverse conditions in which everything goes wrong is calleda)optimistic timeb)most likely timec)pessimistic timed)None of the aboveCorrect answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The time required to complete an activity under abnormal or extremely adverse conditions in which everything goes wrong is calleda)optimistic timeb)most likely timec)pessimistic timed)None of the aboveCorrect answer is option 'C'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev