DIRECTIONS for the question:
Network Systems Ltd. has just taken on a new project for their client IPL Logistics Ltd. The following network diagram shows the sequence of activities involved in the completion of the project. The project starts at node 1 and is completed at node 11. Activities can happen simultaneously. However, an activity cannot be started unless all prior activities have been completed, e.g., the activities at node 6 cannot start unless all activities at nodes 1, 2, 3 and 5 have been completed.
The table below gives the descriptions of the times taken to complete each of these activities.

Q. What is the minimum time taken to complete the project?
  • a)
    18 weeks
  • b)
    20 weeks
  • c)
    17 weeks
  • d)
    21 weeks
Correct answer is option 'D'. Can you explain this answer?
Verified Answer
DIRECTIONS for the question: Network Systems Ltd. has just taken on a ...
The different paths from node 1 to node 11 and their corresponding times are as follows:
Path 1: 1-2-3-5-6-7-11. 
Time: 6+4+2+3+2+4 = 21 weeks.
Path 2: 1-2-3-5-6-8-11.  
Time: 6+4+2+3+4+1 = 20 weeks.
Path 3: 1-2-6-8-11.
Time: 6+6+4+1 = 17 weeks.
Path 4: 1-2-4-9-10-11.
Time: 6+3+4+1+4 = 18 weeks.
Path 5: 1-2-6-7-11.
Time : 6+6+2+4 = 18 weeks. 
The longest path will be considered since it ensures that all activities are completed.
View all questions of this test
Explore Courses for CAT exam

Similar CAT Doubts

Top Courses for CAT

DIRECTIONS for the question: Network Systems Ltd. has just taken on a new project for their client IPL Logistics Ltd. The following network diagram shows the sequence of activities involved in the completion of the project. The project starts at node 1 and is completed at node 11. Activities can happen simultaneously. However, an activity cannot be started unless all prior activities have been completed, e.g., the activities at node 6 cannot start unless all activities at nodes 1, 2, 3 and 5 have been completed.The table below gives the descriptions of the times taken to complete each of these activities.Q.What is the minimum time taken to complete the project?a)18 weeksb)20 weeksc)17 weeksd)21 weeksCorrect answer is option 'D'. Can you explain this answer?
Question Description
DIRECTIONS for the question: Network Systems Ltd. has just taken on a new project for their client IPL Logistics Ltd. The following network diagram shows the sequence of activities involved in the completion of the project. The project starts at node 1 and is completed at node 11. Activities can happen simultaneously. However, an activity cannot be started unless all prior activities have been completed, e.g., the activities at node 6 cannot start unless all activities at nodes 1, 2, 3 and 5 have been completed.The table below gives the descriptions of the times taken to complete each of these activities.Q.What is the minimum time taken to complete the project?a)18 weeksb)20 weeksc)17 weeksd)21 weeksCorrect answer is option 'D'. Can you explain this answer? for CAT 2024 is part of CAT preparation. The Question and answers have been prepared according to the CAT exam syllabus. Information about DIRECTIONS for the question: Network Systems Ltd. has just taken on a new project for their client IPL Logistics Ltd. The following network diagram shows the sequence of activities involved in the completion of the project. The project starts at node 1 and is completed at node 11. Activities can happen simultaneously. However, an activity cannot be started unless all prior activities have been completed, e.g., the activities at node 6 cannot start unless all activities at nodes 1, 2, 3 and 5 have been completed.The table below gives the descriptions of the times taken to complete each of these activities.Q.What is the minimum time taken to complete the project?a)18 weeksb)20 weeksc)17 weeksd)21 weeksCorrect answer is option 'D'. Can you explain this answer? covers all topics & solutions for CAT 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for DIRECTIONS for the question: Network Systems Ltd. has just taken on a new project for their client IPL Logistics Ltd. The following network diagram shows the sequence of activities involved in the completion of the project. The project starts at node 1 and is completed at node 11. Activities can happen simultaneously. However, an activity cannot be started unless all prior activities have been completed, e.g., the activities at node 6 cannot start unless all activities at nodes 1, 2, 3 and 5 have been completed.The table below gives the descriptions of the times taken to complete each of these activities.Q.What is the minimum time taken to complete the project?a)18 weeksb)20 weeksc)17 weeksd)21 weeksCorrect answer is option 'D'. Can you explain this answer?.
Solutions for DIRECTIONS for the question: Network Systems Ltd. has just taken on a new project for their client IPL Logistics Ltd. The following network diagram shows the sequence of activities involved in the completion of the project. The project starts at node 1 and is completed at node 11. Activities can happen simultaneously. However, an activity cannot be started unless all prior activities have been completed, e.g., the activities at node 6 cannot start unless all activities at nodes 1, 2, 3 and 5 have been completed.The table below gives the descriptions of the times taken to complete each of these activities.Q.What is the minimum time taken to complete the project?a)18 weeksb)20 weeksc)17 weeksd)21 weeksCorrect answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for CAT. Download more important topics, notes, lectures and mock test series for CAT Exam by signing up for free.
Here you can find the meaning of DIRECTIONS for the question: Network Systems Ltd. has just taken on a new project for their client IPL Logistics Ltd. The following network diagram shows the sequence of activities involved in the completion of the project. The project starts at node 1 and is completed at node 11. Activities can happen simultaneously. However, an activity cannot be started unless all prior activities have been completed, e.g., the activities at node 6 cannot start unless all activities at nodes 1, 2, 3 and 5 have been completed.The table below gives the descriptions of the times taken to complete each of these activities.Q.What is the minimum time taken to complete the project?a)18 weeksb)20 weeksc)17 weeksd)21 weeksCorrect answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of DIRECTIONS for the question: Network Systems Ltd. has just taken on a new project for their client IPL Logistics Ltd. The following network diagram shows the sequence of activities involved in the completion of the project. The project starts at node 1 and is completed at node 11. Activities can happen simultaneously. However, an activity cannot be started unless all prior activities have been completed, e.g., the activities at node 6 cannot start unless all activities at nodes 1, 2, 3 and 5 have been completed.The table below gives the descriptions of the times taken to complete each of these activities.Q.What is the minimum time taken to complete the project?a)18 weeksb)20 weeksc)17 weeksd)21 weeksCorrect answer is option 'D'. Can you explain this answer?, a detailed solution for DIRECTIONS for the question: Network Systems Ltd. has just taken on a new project for their client IPL Logistics Ltd. The following network diagram shows the sequence of activities involved in the completion of the project. The project starts at node 1 and is completed at node 11. Activities can happen simultaneously. However, an activity cannot be started unless all prior activities have been completed, e.g., the activities at node 6 cannot start unless all activities at nodes 1, 2, 3 and 5 have been completed.The table below gives the descriptions of the times taken to complete each of these activities.Q.What is the minimum time taken to complete the project?a)18 weeksb)20 weeksc)17 weeksd)21 weeksCorrect answer is option 'D'. Can you explain this answer? has been provided alongside types of DIRECTIONS for the question: Network Systems Ltd. has just taken on a new project for their client IPL Logistics Ltd. The following network diagram shows the sequence of activities involved in the completion of the project. The project starts at node 1 and is completed at node 11. Activities can happen simultaneously. However, an activity cannot be started unless all prior activities have been completed, e.g., the activities at node 6 cannot start unless all activities at nodes 1, 2, 3 and 5 have been completed.The table below gives the descriptions of the times taken to complete each of these activities.Q.What is the minimum time taken to complete the project?a)18 weeksb)20 weeksc)17 weeksd)21 weeksCorrect answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice DIRECTIONS for the question: Network Systems Ltd. has just taken on a new project for their client IPL Logistics Ltd. The following network diagram shows the sequence of activities involved in the completion of the project. The project starts at node 1 and is completed at node 11. Activities can happen simultaneously. However, an activity cannot be started unless all prior activities have been completed, e.g., the activities at node 6 cannot start unless all activities at nodes 1, 2, 3 and 5 have been completed.The table below gives the descriptions of the times taken to complete each of these activities.Q.What is the minimum time taken to complete the project?a)18 weeksb)20 weeksc)17 weeksd)21 weeksCorrect answer is option 'D'. Can you explain this answer? tests, examples and also practice CAT tests.
Explore Courses for CAT exam

Top Courses for CAT

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev