CAT Exam  >  CAT Questions  >  Three men and eight machines can finish a job... Start Learning for Free
Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 days, then how many men can finish the job in 13 days?
(2019)
  • a)
    13
  • b)
    14
  • c)
    15
  • d)
    16
Correct answer is option 'A'. Can you explain this answer?
Most Upvoted Answer
Three men and eight machines can finish a job in half the time taken b...
Let one machine completes 1 unit of work per day.
Since, two machines can finish the job in 13 days
∴ Amount of work = 2 × 1 × 13 = 26 units.
Also, let a man completes M units of work per day.
From the given conditions 3M + 8 × 1 = 2(8M + 3 × 1) ⇒ M = 2 / 13 units
Let it require ‘x’ number of men to complete the work in 13 days.
xM × 13 = 26 units ⇒
hence, required number of men = 13.
Free Test
Community Answer
Three men and eight machines can finish a job in half the time taken b...
Given information:
- Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job.
- Two machines can finish the job in 13 days.

To find:
- How many men can finish the job in 13 days.

Let's assume that the job requires x days for three men and eight machines to complete it.
According to the given information, the job will take half the time taken by three machines and eight men to finish the same job. So, the time taken by three machines and eight men to finish the job is 2x days.

It is also given that two machines can finish the job in 13 days. So, we can say that two machines can complete the job in 1/13th of the time taken by three machines and eight men.

Using the concept of work done, we can set up the following equation:
(3 men + 8 machines) * x = (3 machines + 8 men) * 2x
Simplifying the equation, we get:
3x + 8x = 6x + 16x
11x = 22x

Dividing both sides by 22x, we get:
11 = 22

This equation is not possible, which means our initial assumption is incorrect. Therefore, we need to find another approach to solve the problem.

Let's assume that the job requires y days for three machines and eight men to complete it.
According to the given information, the job will take half the time taken by three men and eight machines to finish the same job. So, the time taken by three men and eight machines to finish the job is 2y days.

Using the concept of work done, we can set up the following equation:
(3 men + 8 machines) * 2y = (3 machines + 8 men) * y
Simplifying the equation, we get:
6y + 16y = 3y + 8y
22y = 11y

Dividing both sides by 11y, we get:
22 = 11

This equation is also not possible, which means our assumption is incorrect again.

Let's try another approach:
Let's assume that the job requires z days for three men to complete it.
According to the given information, three men can finish the job in half the time taken by three machines and eight men. So, the time taken by three machines and eight men to finish the job is 2z days.

Using the concept of work done, we can set up the following equation:
3 men * z = (3 machines + 8 men) * 2z
Simplifying the equation, we get:
3z = 22z

Dividing both sides by 22z, we get:
3/22 = 1/z

Therefore, we can conclude that the job can be completed by 3/22 of a man in one day.

To find how many men can finish the job in 13 days, we can set up the following equation:
(3/22) * x = 13
Simplifying the equation, we get:
x = (13 * 22) / 3
x = 286/3
x ≈ 95.33

Since we cannot have a fraction of a man, we can round up the value to the nearest
Explore Courses for CAT exam

Similar CAT Doubts

Top Courses for CAT

Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 days, then how many men can finish the job in 13 days?(2019)a)13b)14c)15d)16Correct answer is option 'A'. Can you explain this answer?
Question Description
Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 days, then how many men can finish the job in 13 days?(2019)a)13b)14c)15d)16Correct answer is option 'A'. Can you explain this answer? for CAT 2025 is part of CAT preparation. The Question and answers have been prepared according to the CAT exam syllabus. Information about Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 days, then how many men can finish the job in 13 days?(2019)a)13b)14c)15d)16Correct answer is option 'A'. Can you explain this answer? covers all topics & solutions for CAT 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 days, then how many men can finish the job in 13 days?(2019)a)13b)14c)15d)16Correct answer is option 'A'. Can you explain this answer?.
Solutions for Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 days, then how many men can finish the job in 13 days?(2019)a)13b)14c)15d)16Correct answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for CAT. Download more important topics, notes, lectures and mock test series for CAT Exam by signing up for free.
Here you can find the meaning of Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 days, then how many men can finish the job in 13 days?(2019)a)13b)14c)15d)16Correct answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 days, then how many men can finish the job in 13 days?(2019)a)13b)14c)15d)16Correct answer is option 'A'. Can you explain this answer?, a detailed solution for Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 days, then how many men can finish the job in 13 days?(2019)a)13b)14c)15d)16Correct answer is option 'A'. Can you explain this answer? has been provided alongside types of Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 days, then how many men can finish the job in 13 days?(2019)a)13b)14c)15d)16Correct answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 days, then how many men can finish the job in 13 days?(2019)a)13b)14c)15d)16Correct answer is option 'A'. Can you explain this answer? tests, examples and also practice CAT tests.
Explore Courses for CAT exam

Top Courses for CAT

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev