Mechanical Engineering Exam  >  Mechanical Engineering Questions  >   The product structure of product ‘P’ is show... Start Learning for Free
The product structure of product ‘P’ is shown in the figure below. The assembly of 2 units of ‘B’ and 4 units of ‘C’ to produce 1 unit of ‘A’ takes a week.
The ordering time of B, C and D are 2, 1 and 2 weeks. The master production schedule for product ‘P’ is as follows:-
The net requirement of ‘C’ if initial inventories of A, B, C and D are 10, 20, 15 and 40 is _____________
  • a)
    265
  • b)
    265
Correct answer is between ' 265, 265'. Can you explain this answer?
Verified Answer
The product structure of product ‘P’ is shown in the figure below. Th...
Total demand = 80 units
For producing 1 unit of P, 80 units of ‘A’ is required but in inventory 10 units of ‘A’ is there so a total of 70 units of ‘A’ is required.
It means 4 × 70 = 280 units of C is required. But in inventory 15 units of C is there.
Therefore 280 − 15 = 265 units of ‘C’ are required.
View all questions of this test
Explore Courses for Mechanical Engineering exam

Similar Mechanical Engineering Doubts

Top Courses for Mechanical Engineering

The product structure of product ‘P’ is shown in the figure below. The assembly of 2 units of ‘B’ and 4 units of ‘C’ to produce 1 unit of ‘A’ takes a week.The ordering time of B, C and D are 2, 1 and 2 weeks. The master production schedule for product ‘P’ is as follows:-The net requirement of ‘C’ if initial inventories of A, B, C and D are 10, 20, 15 and 40 is _____________a) 265b) 265Correct answer is between ' 265, 265'. Can you explain this answer?
Question Description
The product structure of product ‘P’ is shown in the figure below. The assembly of 2 units of ‘B’ and 4 units of ‘C’ to produce 1 unit of ‘A’ takes a week.The ordering time of B, C and D are 2, 1 and 2 weeks. The master production schedule for product ‘P’ is as follows:-The net requirement of ‘C’ if initial inventories of A, B, C and D are 10, 20, 15 and 40 is _____________a) 265b) 265Correct answer is between ' 265, 265'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about The product structure of product ‘P’ is shown in the figure below. The assembly of 2 units of ‘B’ and 4 units of ‘C’ to produce 1 unit of ‘A’ takes a week.The ordering time of B, C and D are 2, 1 and 2 weeks. The master production schedule for product ‘P’ is as follows:-The net requirement of ‘C’ if initial inventories of A, B, C and D are 10, 20, 15 and 40 is _____________a) 265b) 265Correct answer is between ' 265, 265'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The product structure of product ‘P’ is shown in the figure below. The assembly of 2 units of ‘B’ and 4 units of ‘C’ to produce 1 unit of ‘A’ takes a week.The ordering time of B, C and D are 2, 1 and 2 weeks. The master production schedule for product ‘P’ is as follows:-The net requirement of ‘C’ if initial inventories of A, B, C and D are 10, 20, 15 and 40 is _____________a) 265b) 265Correct answer is between ' 265, 265'. Can you explain this answer?.
Solutions for The product structure of product ‘P’ is shown in the figure below. The assembly of 2 units of ‘B’ and 4 units of ‘C’ to produce 1 unit of ‘A’ takes a week.The ordering time of B, C and D are 2, 1 and 2 weeks. The master production schedule for product ‘P’ is as follows:-The net requirement of ‘C’ if initial inventories of A, B, C and D are 10, 20, 15 and 40 is _____________a) 265b) 265Correct answer is between ' 265, 265'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of The product structure of product ‘P’ is shown in the figure below. The assembly of 2 units of ‘B’ and 4 units of ‘C’ to produce 1 unit of ‘A’ takes a week.The ordering time of B, C and D are 2, 1 and 2 weeks. The master production schedule for product ‘P’ is as follows:-The net requirement of ‘C’ if initial inventories of A, B, C and D are 10, 20, 15 and 40 is _____________a) 265b) 265Correct answer is between ' 265, 265'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The product structure of product ‘P’ is shown in the figure below. The assembly of 2 units of ‘B’ and 4 units of ‘C’ to produce 1 unit of ‘A’ takes a week.The ordering time of B, C and D are 2, 1 and 2 weeks. The master production schedule for product ‘P’ is as follows:-The net requirement of ‘C’ if initial inventories of A, B, C and D are 10, 20, 15 and 40 is _____________a) 265b) 265Correct answer is between ' 265, 265'. Can you explain this answer?, a detailed solution for The product structure of product ‘P’ is shown in the figure below. The assembly of 2 units of ‘B’ and 4 units of ‘C’ to produce 1 unit of ‘A’ takes a week.The ordering time of B, C and D are 2, 1 and 2 weeks. The master production schedule for product ‘P’ is as follows:-The net requirement of ‘C’ if initial inventories of A, B, C and D are 10, 20, 15 and 40 is _____________a) 265b) 265Correct answer is between ' 265, 265'. Can you explain this answer? has been provided alongside types of The product structure of product ‘P’ is shown in the figure below. The assembly of 2 units of ‘B’ and 4 units of ‘C’ to produce 1 unit of ‘A’ takes a week.The ordering time of B, C and D are 2, 1 and 2 weeks. The master production schedule for product ‘P’ is as follows:-The net requirement of ‘C’ if initial inventories of A, B, C and D are 10, 20, 15 and 40 is _____________a) 265b) 265Correct answer is between ' 265, 265'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The product structure of product ‘P’ is shown in the figure below. The assembly of 2 units of ‘B’ and 4 units of ‘C’ to produce 1 unit of ‘A’ takes a week.The ordering time of B, C and D are 2, 1 and 2 weeks. The master production schedule for product ‘P’ is as follows:-The net requirement of ‘C’ if initial inventories of A, B, C and D are 10, 20, 15 and 40 is _____________a) 265b) 265Correct answer is between ' 265, 265'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev