Given that the direct fixed cost is Rs.4000. Find the optimal completion time of the project and the cost associated with it, if the overhead cost is Rs.260/day.
  • a)
    30,12310
  • b)
    30,12330
  • c)
    31,12310
  • d)
    32,12320
Correct answer is option 'C'. Can you explain this answer?
Most Upvoted Answer
Given that the direct fixed cost is Rs.4000. Find the optimal complet...
Paths are:
A‐ B‐ E‐ F‐ G‐ I = 3 + 3 + 5 + 6 + 4 + 10 = 31 30
A‐ B‐ E‐ F‐ H = 3 + 3 + 5 + 6 + 10 = 27 26
A‐ C‐ F‐ G‐ I = 3 + 7 + 6 + 4 + 10 = 30
A‐C‐F‐H = 3 + 7 + 6 + 13 = 29
A‐D‐F‐G‐ I = 3 + 9 + 6 + 4 + 10 = 32∗ 31 30
A‐D‐F‐H = 3 + 9 + 6 + 13 = 31 30 29
(i) TC = 4000 + 260 × 32 = 12,320
(ii) Crash activity ‘D’ by 1 day TC = (4000 + 250 × 1) + 260 × 31
= 12,310
(iii) Crash B, D each by 1 day TC = (4000 + 250 × 1 + 30 × 1 + 250× 1) + 260 × 30
= 12,330
Optimal time = 31
Cost = 12310
Free Test
Community Answer
Given that the direct fixed cost is Rs.4000. Find the optimal complet...
Paths are:
A‐ B‐ E‐ F‐ G‐ I = 3 + 3 + 5 + 6 + 4 + 10 = 31 30
A‐ B‐ E‐ F‐ H = 3 + 3 + 5 + 6 + 10 = 27 26
A‐ C‐ F‐ G‐ I = 3 + 7 + 6 + 4 + 10 = 30
A‐C‐F‐H = 3 + 7 + 6 + 13 = 29
A‐D‐F‐G‐ I = 3 + 9 + 6 + 4 + 10 = 32∗ 31 30
A‐D‐F‐H = 3 + 9 + 6 + 13 = 31 30 29
(i) TC = 4000 + 260 × 32 = 12,320
(ii) Crash activity ‘D’ by 1 day TC = (4000 + 250 × 1) + 260 × 31
= 12,310
(iii) Crash B, D each by 1 day TC = (4000 + 250 × 1 + 30 × 1 + 250× 1) + 260 × 30
= 12,330
Optimal time = 31
Cost = 12310
Explore Courses for Mechanical Engineering exam
Question Description
Given that the direct fixed cost is Rs.4000. Find the optimal completion time of the project and the cost associated with it, if the overhead cost is Rs.260/day.a) 30,12310b) 30,12330c) 31,12310d) 32,12320Correct answer is option 'C'. Can you explain this answer? for Mechanical Engineering 2025 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about Given that the direct fixed cost is Rs.4000. Find the optimal completion time of the project and the cost associated with it, if the overhead cost is Rs.260/day.a) 30,12310b) 30,12330c) 31,12310d) 32,12320Correct answer is option 'C'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Given that the direct fixed cost is Rs.4000. Find the optimal completion time of the project and the cost associated with it, if the overhead cost is Rs.260/day.a) 30,12310b) 30,12330c) 31,12310d) 32,12320Correct answer is option 'C'. Can you explain this answer?.
Solutions for Given that the direct fixed cost is Rs.4000. Find the optimal completion time of the project and the cost associated with it, if the overhead cost is Rs.260/day.a) 30,12310b) 30,12330c) 31,12310d) 32,12320Correct answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of Given that the direct fixed cost is Rs.4000. Find the optimal completion time of the project and the cost associated with it, if the overhead cost is Rs.260/day.a) 30,12310b) 30,12330c) 31,12310d) 32,12320Correct answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Given that the direct fixed cost is Rs.4000. Find the optimal completion time of the project and the cost associated with it, if the overhead cost is Rs.260/day.a) 30,12310b) 30,12330c) 31,12310d) 32,12320Correct answer is option 'C'. Can you explain this answer?, a detailed solution for Given that the direct fixed cost is Rs.4000. Find the optimal completion time of the project and the cost associated with it, if the overhead cost is Rs.260/day.a) 30,12310b) 30,12330c) 31,12310d) 32,12320Correct answer is option 'C'. Can you explain this answer? has been provided alongside types of Given that the direct fixed cost is Rs.4000. Find the optimal completion time of the project and the cost associated with it, if the overhead cost is Rs.260/day.a) 30,12310b) 30,12330c) 31,12310d) 32,12320Correct answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Given that the direct fixed cost is Rs.4000. Find the optimal completion time of the project and the cost associated with it, if the overhead cost is Rs.260/day.a) 30,12310b) 30,12330c) 31,12310d) 32,12320Correct answer is option 'C'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam
Signup to solve all Doubts
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev