Ram and Shyam work on a job together for four days and complete 60% of it.Ram takes leave then and Shyam works for eight more days to complete the job.How long would Ram take to complete the entire job alone?
  • a)
    6 days
  • b)
    8 days
  • c)
    10 days
  • d)
    11 days
Correct answer is option 'C'. Can you explain this answer?
Most Upvoted Answer
Ram and Shyam work on a job together for four days and complete 60% of...
Given information:
- Ram and Shyam work on a job together for four days and complete 60% of it.
- Ram takes leave then and Shyam works for eight more days to complete the job.
We need to find the time taken by Ram to complete the entire job alone.

Solution:
Let's assume that the entire job requires 100 units of work.
- Ram and Shyam work together for four days and complete 60% of the job, which means they complete 60 units of work.
- This leaves 40 units of work to be done.
- Ram takes leave, so Shyam has to complete the remaining 40 units of work alone.
- Shyam works for eight more days to complete the job, which means he completes 40 units of work in eight days.
- Therefore, Shyam can complete 5 units of work in one day (40/8 = 5).
- Ram and Shyam together can complete (60 units in 4 days) = 15 units of work in one day.
- Since Shyam can complete 5 units of work in one day, Ram can complete (15-5) = 10 units of work in one day.
- Therefore, Ram can complete the entire job alone in (100/10) = 10 days.

Hence, the correct answer is option C, 10 days.
Free Test
Community Answer
Ram and Shyam work on a job together for four days and complete 60% of...
Answer
Explore Courses for UPSC exam

Similar UPSC Doubts

Top Courses for UPSC

Ram and Shyam work on a job together for four days and complete 60% of it.Ram takes leave then and Shyam works for eight more days to complete the job.How long would Ram take to complete the entire job alone?a)6 daysb)8 daysc)10 daysd)11 daysCorrect answer is option 'C'. Can you explain this answer?
Question Description
Ram and Shyam work on a job together for four days and complete 60% of it.Ram takes leave then and Shyam works for eight more days to complete the job.How long would Ram take to complete the entire job alone?a)6 daysb)8 daysc)10 daysd)11 daysCorrect answer is option 'C'. Can you explain this answer? for UPSC 2024 is part of UPSC preparation. The Question and answers have been prepared according to the UPSC exam syllabus. Information about Ram and Shyam work on a job together for four days and complete 60% of it.Ram takes leave then and Shyam works for eight more days to complete the job.How long would Ram take to complete the entire job alone?a)6 daysb)8 daysc)10 daysd)11 daysCorrect answer is option 'C'. Can you explain this answer? covers all topics & solutions for UPSC 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Ram and Shyam work on a job together for four days and complete 60% of it.Ram takes leave then and Shyam works for eight more days to complete the job.How long would Ram take to complete the entire job alone?a)6 daysb)8 daysc)10 daysd)11 daysCorrect answer is option 'C'. Can you explain this answer?.
Solutions for Ram and Shyam work on a job together for four days and complete 60% of it.Ram takes leave then and Shyam works for eight more days to complete the job.How long would Ram take to complete the entire job alone?a)6 daysb)8 daysc)10 daysd)11 daysCorrect answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for UPSC. Download more important topics, notes, lectures and mock test series for UPSC Exam by signing up for free.
Here you can find the meaning of Ram and Shyam work on a job together for four days and complete 60% of it.Ram takes leave then and Shyam works for eight more days to complete the job.How long would Ram take to complete the entire job alone?a)6 daysb)8 daysc)10 daysd)11 daysCorrect answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Ram and Shyam work on a job together for four days and complete 60% of it.Ram takes leave then and Shyam works for eight more days to complete the job.How long would Ram take to complete the entire job alone?a)6 daysb)8 daysc)10 daysd)11 daysCorrect answer is option 'C'. Can you explain this answer?, a detailed solution for Ram and Shyam work on a job together for four days and complete 60% of it.Ram takes leave then and Shyam works for eight more days to complete the job.How long would Ram take to complete the entire job alone?a)6 daysb)8 daysc)10 daysd)11 daysCorrect answer is option 'C'. Can you explain this answer? has been provided alongside types of Ram and Shyam work on a job together for four days and complete 60% of it.Ram takes leave then and Shyam works for eight more days to complete the job.How long would Ram take to complete the entire job alone?a)6 daysb)8 daysc)10 daysd)11 daysCorrect answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Ram and Shyam work on a job together for four days and complete 60% of it.Ram takes leave then and Shyam works for eight more days to complete the job.How long would Ram take to complete the entire job alone?a)6 daysb)8 daysc)10 daysd)11 daysCorrect answer is option 'C'. Can you explain this answer? tests, examples and also practice UPSC tests.
Explore Courses for UPSC exam

Top Courses for UPSC

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev