CLAT Exam  >  CLAT Questions  >   A and B together can complete a work in 3 da... Start Learning for Free
A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in:
  • a)
    5 days
  • b)
    6 days
  • c)
    9 days
  • d)
    10 days
Correct answer is option 'B'. Can you explain this answer?
Verified Answer
A and B together can complete a work in 3 days. They start together b...
(A+B)'s one day's work = 1/3 part
(A+B) works 2 days together = 2/3 part
1/3 part of work is completed by A in two days
Hence, one day's work of A = ⅙
Then, one day's work of
So, B alone can complete the whole work in 6 days.
Hence, the correct option is (B).
View all questions of this test
Most Upvoted Answer
A and B together can complete a work in 3 days. They start together b...
Given Information:
- A and B together can complete a work in 3 days.
- They start together but after 2 days, B left the work.
- The work is completed after two more days.

Objective:
Find the time taken by B alone to complete the work.

Assumption:
Let's assume that A and B work at a constant rate throughout the duration of the work.

Explanation:
To solve this problem, we can use the concept of work done. The work done is calculated by multiplying the rate at which work is done by the time taken to complete the work.

Step 1: Calculate the total work:
Let's assume that the total work to be done is represented by W. Since A and B together can complete the work in 3 days, their combined rate of work is W/3.

Step 2: Calculate the work done in the first 2 days:
Since A and B work together for 2 days, the work done by them in these 2 days is (W/3) * 2 = (2W/3).

Step 3: Calculate the remaining work:
The work remaining to be done after 2 days is the total work minus the work done in the first 2 days. Therefore, the remaining work is W - (2W/3) = (W/3).

Step 4: Calculate the time taken by B to complete the remaining work:
We are given that the remaining work is completed after two more days. Since B is working alone during these two days, we can calculate B's rate of work as (W/3) / 2 = W/6. This means that B can complete the remaining work (W/3) in 2 days.

Step 5: Calculate the time taken by B to complete the entire work:
Since B can complete the remaining work (W/3) in 2 days, we can calculate the time taken by B to complete the entire work (W) as (2 days) * (3/1) = 6 days.

Therefore, the correct answer is option 'B', i.e., B alone could do the work in 6 days.
Attention CLAT Students!
To make sure you are not studying endlessly, EduRev has designed CLAT study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in CLAT.
Explore Courses for CLAT exam

Top Courses for CLAT

A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in:a)5 daysb)6 daysc)9 daysd)10 daysCorrect answer is option 'B'. Can you explain this answer?
Question Description
A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in:a)5 daysb)6 daysc)9 daysd)10 daysCorrect answer is option 'B'. Can you explain this answer? for CLAT 2024 is part of CLAT preparation. The Question and answers have been prepared according to the CLAT exam syllabus. Information about A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in:a)5 daysb)6 daysc)9 daysd)10 daysCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for CLAT 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in:a)5 daysb)6 daysc)9 daysd)10 daysCorrect answer is option 'B'. Can you explain this answer?.
Solutions for A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in:a)5 daysb)6 daysc)9 daysd)10 daysCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for CLAT. Download more important topics, notes, lectures and mock test series for CLAT Exam by signing up for free.
Here you can find the meaning of A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in:a)5 daysb)6 daysc)9 daysd)10 daysCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in:a)5 daysb)6 daysc)9 daysd)10 daysCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in:a)5 daysb)6 daysc)9 daysd)10 daysCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in:a)5 daysb)6 daysc)9 daysd)10 daysCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in:a)5 daysb)6 daysc)9 daysd)10 daysCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice CLAT tests.
Explore Courses for CLAT exam

Top Courses for CLAT

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev