Civil Engineering (CE) Exam  >  Civil Engineering (CE) Questions  >  Pick up the correct statement from the follow... Start Learning for Free
Pick up the correct statement from the following :
  • a)
    The unit hydrograph of a specified unit duration obtained from the past data can be used to obtain the hydrograph of future storms of like duration
  • b)
    To obtain the ordinates of storm hydrograph, the ordinates of unit hydrograph are multiplied by the multiplying factor
  • c)
    The multiplying factor for storm hydrograph may be obtained by dividing the run off in mm by 25 mm
  • d)
    A tolerance of about 25% of specified duration of unit hydrograph may be accepted without any serious error
  • e)
    All the above.
Correct answer is option 'E'. Can you explain this answer?
Most Upvoted Answer
Pick up the correct statement from the following :a)The unit hydrograp...
Unit Hydrograph and Storm Hydrograph

Unit Hydrograph:
A unit hydrograph is defined as the hydrograph of direct runoff resulting from one unit of excess rainfall that is uniformly distributed over the watershed at a uniform rate for a specified duration. The unit hydrograph of a specified unit duration obtained from the past data can be used to obtain the hydrograph of future storms of like duration. Unit hydrograph is a very important tool for hydrologic analysis and design of hydraulic structures.

Storm Hydrograph:
A storm hydrograph is the hydrograph of direct runoff resulting from a particular storm of known rainfall depth, duration and distribution over a watershed. To obtain the ordinates of storm hydrograph, the ordinates of unit hydrograph are multiplied by the multiplying factor. The multiplying factor for storm hydrograph may be obtained by dividing the runoff in mm by 25 mm. It is important to note that the multiplying factor is based on the assumption that the excess rainfall is uniformly distributed over the watershed and the time of concentration is the same for both the unit hydrograph and the storm hydrograph.

Tolerance of Unit Hydrograph:
A tolerance of about 25% of specified duration of unit hydrograph may be accepted without any serious error. This means that the unit hydrograph of slightly different duration may be used for the design of hydraulic structures without much error. However, caution should be exercised when using a unit hydrograph of significantly different duration.

Conclusion:
In conclusion, the unit hydrograph is an important tool for hydrologic analysis and design of hydraulic structures. It can be used to obtain the hydrograph of future storms of like duration. The storm hydrograph can be obtained by multiplying the ordinates of unit hydrograph by the multiplying factor. A tolerance of about 25% of specified duration of unit hydrograph may be accepted without any serious error.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Pick up the correct statement from the following :a)The unit hydrograph of a specified unit duration obtained from the past data can be used to obtain the hydrograph of future storms of like durationb)To obtain the ordinates of storm hydrograph, the ordinates of unit hydrograph are multiplied by the multiplying factorc)The multiplying factor for storm hydrograph may be obtained by dividing the run off in mm by 25 mmd)A tolerance of about 25% of specified duration of unit hydrograph may be accepted without any serious errore)All the above.Correct answer is option 'E'. Can you explain this answer?
Question Description
Pick up the correct statement from the following :a)The unit hydrograph of a specified unit duration obtained from the past data can be used to obtain the hydrograph of future storms of like durationb)To obtain the ordinates of storm hydrograph, the ordinates of unit hydrograph are multiplied by the multiplying factorc)The multiplying factor for storm hydrograph may be obtained by dividing the run off in mm by 25 mmd)A tolerance of about 25% of specified duration of unit hydrograph may be accepted without any serious errore)All the above.Correct answer is option 'E'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about Pick up the correct statement from the following :a)The unit hydrograph of a specified unit duration obtained from the past data can be used to obtain the hydrograph of future storms of like durationb)To obtain the ordinates of storm hydrograph, the ordinates of unit hydrograph are multiplied by the multiplying factorc)The multiplying factor for storm hydrograph may be obtained by dividing the run off in mm by 25 mmd)A tolerance of about 25% of specified duration of unit hydrograph may be accepted without any serious errore)All the above.Correct answer is option 'E'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Pick up the correct statement from the following :a)The unit hydrograph of a specified unit duration obtained from the past data can be used to obtain the hydrograph of future storms of like durationb)To obtain the ordinates of storm hydrograph, the ordinates of unit hydrograph are multiplied by the multiplying factorc)The multiplying factor for storm hydrograph may be obtained by dividing the run off in mm by 25 mmd)A tolerance of about 25% of specified duration of unit hydrograph may be accepted without any serious errore)All the above.Correct answer is option 'E'. Can you explain this answer?.
Solutions for Pick up the correct statement from the following :a)The unit hydrograph of a specified unit duration obtained from the past data can be used to obtain the hydrograph of future storms of like durationb)To obtain the ordinates of storm hydrograph, the ordinates of unit hydrograph are multiplied by the multiplying factorc)The multiplying factor for storm hydrograph may be obtained by dividing the run off in mm by 25 mmd)A tolerance of about 25% of specified duration of unit hydrograph may be accepted without any serious errore)All the above.Correct answer is option 'E'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of Pick up the correct statement from the following :a)The unit hydrograph of a specified unit duration obtained from the past data can be used to obtain the hydrograph of future storms of like durationb)To obtain the ordinates of storm hydrograph, the ordinates of unit hydrograph are multiplied by the multiplying factorc)The multiplying factor for storm hydrograph may be obtained by dividing the run off in mm by 25 mmd)A tolerance of about 25% of specified duration of unit hydrograph may be accepted without any serious errore)All the above.Correct answer is option 'E'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Pick up the correct statement from the following :a)The unit hydrograph of a specified unit duration obtained from the past data can be used to obtain the hydrograph of future storms of like durationb)To obtain the ordinates of storm hydrograph, the ordinates of unit hydrograph are multiplied by the multiplying factorc)The multiplying factor for storm hydrograph may be obtained by dividing the run off in mm by 25 mmd)A tolerance of about 25% of specified duration of unit hydrograph may be accepted without any serious errore)All the above.Correct answer is option 'E'. Can you explain this answer?, a detailed solution for Pick up the correct statement from the following :a)The unit hydrograph of a specified unit duration obtained from the past data can be used to obtain the hydrograph of future storms of like durationb)To obtain the ordinates of storm hydrograph, the ordinates of unit hydrograph are multiplied by the multiplying factorc)The multiplying factor for storm hydrograph may be obtained by dividing the run off in mm by 25 mmd)A tolerance of about 25% of specified duration of unit hydrograph may be accepted without any serious errore)All the above.Correct answer is option 'E'. Can you explain this answer? has been provided alongside types of Pick up the correct statement from the following :a)The unit hydrograph of a specified unit duration obtained from the past data can be used to obtain the hydrograph of future storms of like durationb)To obtain the ordinates of storm hydrograph, the ordinates of unit hydrograph are multiplied by the multiplying factorc)The multiplying factor for storm hydrograph may be obtained by dividing the run off in mm by 25 mmd)A tolerance of about 25% of specified duration of unit hydrograph may be accepted without any serious errore)All the above.Correct answer is option 'E'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Pick up the correct statement from the following :a)The unit hydrograph of a specified unit duration obtained from the past data can be used to obtain the hydrograph of future storms of like durationb)To obtain the ordinates of storm hydrograph, the ordinates of unit hydrograph are multiplied by the multiplying factorc)The multiplying factor for storm hydrograph may be obtained by dividing the run off in mm by 25 mmd)A tolerance of about 25% of specified duration of unit hydrograph may be accepted without any serious errore)All the above.Correct answer is option 'E'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev