Electrical Engineering (EE) Exam  >  Electrical Engineering (EE) Questions  >  A piece of work is to be completed in 100days... Start Learning for Free
A piece of work is to be completed in 100days, 11 Men are employed to do the work it is found that after 50 days only 1/3 rd work is completed. Now additionally how many more Men are to be employed to work to finish the work in time?
Most Upvoted Answer
A piece of work is to be completed in 100days, 11 Men are employed to ...
Problem Statement:

A piece of work is to be completed in 100 days. 11 men are employed to do the work. After 50 days, only 1/3rd of the work is completed. How many more men are to be employed to finish the work in time?


Solution:

Given:


  • Number of days to complete the work (D) = 100 days

  • Number of men employed (M) = 11

  • Days completed (d) = 50 days

  • Work completed (W) = 1/3



Step 1: Calculation of total work

Total work (T) = 1 (Assuming the total work to be 1 unit)


Step 2: Calculation of work done

Work done (D) = W*T = 1/3


Step 3: Calculation of remaining work

Remaining work (R) = T - D = 2/3


Step 4: Calculation of work done by 11 men in 50 days

Let the total work done by 11 men in 50 days be M1

Number of men employed (M1) = 11

Number of days (d1) = 50 days

Work done (W1) = 1/3

Using the formula, Work done = (Number of men employed * Number of days * Efficiency)

Efficiency of 11 men (E1) = W1 / (M1 * d1) = (1/3) / (11 * 50) = 1/165

Total work done by 11 men in 50 days (D1) = M1 * d1 * E1 = 11 * 50 * (1/165) = 10/3


Step 5: Calculation of remaining work to be done

Remaining work (R) = 2/3

Work done by 11 men in 50 days (D1) = 10/3

Remaining work (R1) = R - D1 = 2/3 - 10/3 = -8/3 (Negative value indicates that the work is already delayed)


Step 6: Calculation of additional men required to complete the remaining work in time

Let the number of men required to complete the remaining work in time be M2

Number of men employed (M2
Explore Courses for Electrical Engineering (EE) exam

Similar Electrical Engineering (EE) Doubts

Top Courses for Electrical Engineering (EE)

A piece of work is to be completed in 100days, 11 Men are employed to do the work it is found that after 50 days only 1/3 rd work is completed. Now additionally how many more Men are to be employed to work to finish the work in time?
Question Description
A piece of work is to be completed in 100days, 11 Men are employed to do the work it is found that after 50 days only 1/3 rd work is completed. Now additionally how many more Men are to be employed to work to finish the work in time? for Electrical Engineering (EE) 2024 is part of Electrical Engineering (EE) preparation. The Question and answers have been prepared according to the Electrical Engineering (EE) exam syllabus. Information about A piece of work is to be completed in 100days, 11 Men are employed to do the work it is found that after 50 days only 1/3 rd work is completed. Now additionally how many more Men are to be employed to work to finish the work in time? covers all topics & solutions for Electrical Engineering (EE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A piece of work is to be completed in 100days, 11 Men are employed to do the work it is found that after 50 days only 1/3 rd work is completed. Now additionally how many more Men are to be employed to work to finish the work in time?.
Solutions for A piece of work is to be completed in 100days, 11 Men are employed to do the work it is found that after 50 days only 1/3 rd work is completed. Now additionally how many more Men are to be employed to work to finish the work in time? in English & in Hindi are available as part of our courses for Electrical Engineering (EE). Download more important topics, notes, lectures and mock test series for Electrical Engineering (EE) Exam by signing up for free.
Here you can find the meaning of A piece of work is to be completed in 100days, 11 Men are employed to do the work it is found that after 50 days only 1/3 rd work is completed. Now additionally how many more Men are to be employed to work to finish the work in time? defined & explained in the simplest way possible. Besides giving the explanation of A piece of work is to be completed in 100days, 11 Men are employed to do the work it is found that after 50 days only 1/3 rd work is completed. Now additionally how many more Men are to be employed to work to finish the work in time?, a detailed solution for A piece of work is to be completed in 100days, 11 Men are employed to do the work it is found that after 50 days only 1/3 rd work is completed. Now additionally how many more Men are to be employed to work to finish the work in time? has been provided alongside types of A piece of work is to be completed in 100days, 11 Men are employed to do the work it is found that after 50 days only 1/3 rd work is completed. Now additionally how many more Men are to be employed to work to finish the work in time? theory, EduRev gives you an ample number of questions to practice A piece of work is to be completed in 100days, 11 Men are employed to do the work it is found that after 50 days only 1/3 rd work is completed. Now additionally how many more Men are to be employed to work to finish the work in time? tests, examples and also practice Electrical Engineering (EE) tests.
Explore Courses for Electrical Engineering (EE) exam

Top Courses for Electrical Engineering (EE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev