A contractor undertook a certain job to be completed in 55 days and employed 48 men to do it. In 11 days, only 1/6 of the work was completed. How many extra men should he employ in order to complete the work in the allotted time?
  • a)
    8
  • b)
    12
  • c)
    16
  • d)
    18
Correct answer is option 'B'. Can you explain this answer?
Most Upvoted Answer
A contractor undertook a certain job to be completed in 55 days and e...
In 11 days, only 1/6 of the work was done. It is evident that the remaining 5/6 of the work will be finished within 55 days.
But, he wants to finish the remaining work in 55 - 11 = 44 days.
In 55 days, the remaining work can be finished by 48 men.
⇒ In 44 days, the work can be finished by 48 x(55/44)men = 60 men
So, he should employ (60 - 48) = 12 more men.
Free Test
Community Answer
A contractor undertook a certain job to be completed in 55 days and e...
To solve this problem, we can use the concept of man-days.

Given:
- The job is to be completed in 55 days.
- 48 men were initially employed.
- In 11 days, only 1/6 of the work was completed.

Let's assume that the total work required for the job is represented by W.

Work done in 11 days:
In 11 days, only 1/6 of the work was completed.
So, the work done in 11 days = (1/6) * W = W/6

Work remaining after 11 days:
Work remaining = Total work - Work done in 11 days = W - W/6 = (5W/6)

Time remaining:
Since the job is to be completed in 55 days and 11 days have already passed, the time remaining is 55 - 11 = 44 days.

Man-days required to complete the remaining work:
Man-days required = (Work remaining) * (Time remaining)
= (5W/6) * 44

Man-days available with 48 men in 44 days:
Man-days available = (Number of men) * (Time remaining)
= 48 * 44

To calculate the number of extra men required, we need to find the difference between the required man-days and the available man-days.

Difference = Man-days required - Man-days available
= (5W/6) * 44 - (48 * 44)
= (5W - 48 * 6) * 44/6

To complete the work in the allotted time, the contractor needs to employ extra men. The number of extra men required can be calculated by dividing the difference by the number of man-days a single man can contribute in a day.

Number of extra men required = Difference / (Man-days contributed by a single man in a day)

Let's assume that each man contributes M man-days in a day.

Number of extra men required = Difference / M

Since we want to find the number of extra men required, we can rearrange the equation as:

M = Difference / (Number of extra men required)

Simplifying, we get:

Number of extra men required = Difference / M = Difference / (Difference / (Number of extra men required))

Simplifying further, we get:

Number of extra men required = Difference * (Number of extra men required) / Difference

The difference cancels out, and we are left with:

Number of extra men required = Number of extra men required

Therefore, any number of extra men would be required to complete the work in the allotted time.
Explore Courses for Electrical Engineering (EE) exam

Top Courses for Electrical Engineering (EE)

A contractor undertook a certain job to be completed in 55 days and employed 48 men to do it. In 11 days, only 1/6 of the work was completed. How many extra men should he employ in order to complete the work in the allotted time?a)8b)12c)16d)18Correct answer is option 'B'. Can you explain this answer?
Question Description
A contractor undertook a certain job to be completed in 55 days and employed 48 men to do it. In 11 days, only 1/6 of the work was completed. How many extra men should he employ in order to complete the work in the allotted time?a)8b)12c)16d)18Correct answer is option 'B'. Can you explain this answer? for Electrical Engineering (EE) 2024 is part of Electrical Engineering (EE) preparation. The Question and answers have been prepared according to the Electrical Engineering (EE) exam syllabus. Information about A contractor undertook a certain job to be completed in 55 days and employed 48 men to do it. In 11 days, only 1/6 of the work was completed. How many extra men should he employ in order to complete the work in the allotted time?a)8b)12c)16d)18Correct answer is option 'B'. Can you explain this answer? covers all topics & solutions for Electrical Engineering (EE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A contractor undertook a certain job to be completed in 55 days and employed 48 men to do it. In 11 days, only 1/6 of the work was completed. How many extra men should he employ in order to complete the work in the allotted time?a)8b)12c)16d)18Correct answer is option 'B'. Can you explain this answer?.
Solutions for A contractor undertook a certain job to be completed in 55 days and employed 48 men to do it. In 11 days, only 1/6 of the work was completed. How many extra men should he employ in order to complete the work in the allotted time?a)8b)12c)16d)18Correct answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Electrical Engineering (EE). Download more important topics, notes, lectures and mock test series for Electrical Engineering (EE) Exam by signing up for free.
Here you can find the meaning of A contractor undertook a certain job to be completed in 55 days and employed 48 men to do it. In 11 days, only 1/6 of the work was completed. How many extra men should he employ in order to complete the work in the allotted time?a)8b)12c)16d)18Correct answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A contractor undertook a certain job to be completed in 55 days and employed 48 men to do it. In 11 days, only 1/6 of the work was completed. How many extra men should he employ in order to complete the work in the allotted time?a)8b)12c)16d)18Correct answer is option 'B'. Can you explain this answer?, a detailed solution for A contractor undertook a certain job to be completed in 55 days and employed 48 men to do it. In 11 days, only 1/6 of the work was completed. How many extra men should he employ in order to complete the work in the allotted time?a)8b)12c)16d)18Correct answer is option 'B'. Can you explain this answer? has been provided alongside types of A contractor undertook a certain job to be completed in 55 days and employed 48 men to do it. In 11 days, only 1/6 of the work was completed. How many extra men should he employ in order to complete the work in the allotted time?a)8b)12c)16d)18Correct answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A contractor undertook a certain job to be completed in 55 days and employed 48 men to do it. In 11 days, only 1/6 of the work was completed. How many extra men should he employ in order to complete the work in the allotted time?a)8b)12c)16d)18Correct answer is option 'B'. Can you explain this answer? tests, examples and also practice Electrical Engineering (EE) tests.
Explore Courses for Electrical Engineering (EE) exam

Top Courses for Electrical Engineering (EE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev