Question Description
A contractor undertook a certain job to be completed in 55 days and employed 48 men to do it. In 11 days, only 1/6 of the work was completed. How many extra men should he employ in order to complete the work in the allotted time?a)8b)12c)16d)18Correct answer is option 'B'. Can you explain this answer? for Electrical Engineering (EE) 2024 is part of Electrical Engineering (EE) preparation. The Question and answers have been prepared
according to
the Electrical Engineering (EE) exam syllabus. Information about A contractor undertook a certain job to be completed in 55 days and employed 48 men to do it. In 11 days, only 1/6 of the work was completed. How many extra men should he employ in order to complete the work in the allotted time?a)8b)12c)16d)18Correct answer is option 'B'. Can you explain this answer? covers all topics & solutions for Electrical Engineering (EE) 2024 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for A contractor undertook a certain job to be completed in 55 days and employed 48 men to do it. In 11 days, only 1/6 of the work was completed. How many extra men should he employ in order to complete the work in the allotted time?a)8b)12c)16d)18Correct answer is option 'B'. Can you explain this answer?.
Solutions for A contractor undertook a certain job to be completed in 55 days and employed 48 men to do it. In 11 days, only 1/6 of the work was completed. How many extra men should he employ in order to complete the work in the allotted time?a)8b)12c)16d)18Correct answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Electrical Engineering (EE).
Download more important topics, notes, lectures and mock test series for Electrical Engineering (EE) Exam by signing up for free.
Here you can find the meaning of A contractor undertook a certain job to be completed in 55 days and employed 48 men to do it. In 11 days, only 1/6 of the work was completed. How many extra men should he employ in order to complete the work in the allotted time?a)8b)12c)16d)18Correct answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of
A contractor undertook a certain job to be completed in 55 days and employed 48 men to do it. In 11 days, only 1/6 of the work was completed. How many extra men should he employ in order to complete the work in the allotted time?a)8b)12c)16d)18Correct answer is option 'B'. Can you explain this answer?, a detailed solution for A contractor undertook a certain job to be completed in 55 days and employed 48 men to do it. In 11 days, only 1/6 of the work was completed. How many extra men should he employ in order to complete the work in the allotted time?a)8b)12c)16d)18Correct answer is option 'B'. Can you explain this answer? has been provided alongside types of A contractor undertook a certain job to be completed in 55 days and employed 48 men to do it. In 11 days, only 1/6 of the work was completed. How many extra men should he employ in order to complete the work in the allotted time?a)8b)12c)16d)18Correct answer is option 'B'. Can you explain this answer? theory, EduRev gives you an
ample number of questions to practice A contractor undertook a certain job to be completed in 55 days and employed 48 men to do it. In 11 days, only 1/6 of the work was completed. How many extra men should he employ in order to complete the work in the allotted time?a)8b)12c)16d)18Correct answer is option 'B'. Can you explain this answer? tests, examples and also practice Electrical Engineering (EE) tests.