UPSC Exam  >  UPSC Questions  >  With reference to the Project P 75 (I), consi... Start Learning for Free
With reference to the Project P 75 (I), consider the following statements:
1. This project envisages indigenous construction of six conventional submarines equipped with the state-of-the-art Air Independent Propulsion system at an estimated cost of Rs 43,000 crore.
2. This is the first project processed under the Strategic Partnership model.
Which of the statements given above is/are correct?
  • a)
    1 only
  • b)
    2 only
  • c)
    Both 1 and 2
  • d)
    Neither 1 nor 2
Correct answer is option 'C'. Can you explain this answer?
Most Upvoted Answer
With reference to the Project P 75 (I), consider the following stateme...
The Defence Acquisition Council (DAC) under the Chairmanship of Raksha Mantri Shri Rajnath Singh on June 04, 2021, has approved the issuance of a Request For Proposal (RFP) for construction of six Conventional Submarines under Project P 75 (I) under the Strategic Partnership (SP) Model.
  • This project envisages indigenous construction of six conventional submarines equipped with the state-of-the-art Air Independent Propulsion system at an estimated cost of Rs 43,000 crore.
  • This is the first case processed under the Strategic Partnership model. The SP model of the Defence Procurement Procedure (DPP) aims to promote the role of Indian industry in manufacturing and build a domestic defence industrial ecosystem.
  • This would be one of the largest ‘Make in India’ projects.
  • With this approval, India would be enabled to achieve its 30-year submarine construction programme envisioned by the government to acquire national competence in their building and for Indian industry to independently design and construct them.
  • Strategic Partnership (SP) policy was approved by the Defence ministry in May 2017 as a part of the Defence Procurement Procedure (DPP). In July 2018, Defence Acquisition Council (DAC) approved Implementation guidelines for the SP Model.
Hence both statements are correct.
Free Test
Community Answer
With reference to the Project P 75 (I), consider the following stateme...
Statement 1: This project envisages indigenous construction of six conventional submarines equipped with the state-of-the-art Air Independent Propulsion system at an estimated cost of Rs 43,000 crore.

Statement 2: This is the first project processed under the Strategic Partnership model.

Explanation:

The correct answer is option C, which means both statements 1 and 2 are correct.

Explanation of Statement 1:

The Project P 75 (I) refers to the Indian Navy's plan to construct six conventional submarines equipped with the state-of-the-art Air Independent Propulsion (AIP) system. The submarines will be built indigenously, meaning within the country, and the project is estimated to cost Rs 43,000 crore.

The AIP system is a technology that allows submarines to operate underwater for a longer duration without having to surface. This technology enhances the stealth capabilities of the submarines and makes them more effective in combat scenarios.

The construction of these submarines is a significant step towards strengthening the Indian Navy's underwater capabilities. By building them indigenously, the country reduces its dependency on foreign suppliers and enhances its self-reliance in defense manufacturing.

Explanation of Statement 2:

The Project P 75 (I) is the first project to be processed under the Strategic Partnership (SP) model. The SP model is a policy introduced by the Government of India to promote indigenous defense manufacturing and enhance the country's defense capabilities.

Under the SP model, the government aims to select private sector companies as strategic partners for the manufacturing of major defense platforms such as submarines, fighter aircraft, helicopters, and armored vehicles. These strategic partners will collaborate with foreign Original Equipment Manufacturers (OEMs) to transfer technology and build the platforms in India.

The selection of strategic partners is done through a competitive and transparent process, ensuring that the best companies are chosen based on their capabilities, track record, and ability to meet the requirements of the Indian Armed Forces.

The Project P 75 (I) being the first project processed under the SP model signifies the government's commitment to promoting indigenous defense manufacturing and strengthening the country's defense industry.

Conclusion:

In conclusion, both statements 1 and 2 are correct. The Project P 75 (I) involves the indigenous construction of six conventional submarines equipped with the state-of-the-art AIP system at an estimated cost of Rs 43,000 crore. Additionally, it is the first project processed under the Strategic Partnership model, which aims to promote indigenous defense manufacturing and enhance the country's defense capabilities.
Explore Courses for UPSC exam

Similar UPSC Doubts

Top Courses for UPSC

With reference to the Project P 75 (I), consider the following statements:1. This project envisages indigenous construction of six conventional submarines equipped with the state-of-the-art Air Independent Propulsion system at an estimated cost of Rs 43,000 crore.2. This is the first project processed under the Strategic Partnership model.Which of the statements given above is/are correct?a)1 onlyb)2 onlyc)Both 1 and 2d)Neither 1 nor 2Correct answer is option 'C'. Can you explain this answer?
Question Description
With reference to the Project P 75 (I), consider the following statements:1. This project envisages indigenous construction of six conventional submarines equipped with the state-of-the-art Air Independent Propulsion system at an estimated cost of Rs 43,000 crore.2. This is the first project processed under the Strategic Partnership model.Which of the statements given above is/are correct?a)1 onlyb)2 onlyc)Both 1 and 2d)Neither 1 nor 2Correct answer is option 'C'. Can you explain this answer? for UPSC 2024 is part of UPSC preparation. The Question and answers have been prepared according to the UPSC exam syllabus. Information about With reference to the Project P 75 (I), consider the following statements:1. This project envisages indigenous construction of six conventional submarines equipped with the state-of-the-art Air Independent Propulsion system at an estimated cost of Rs 43,000 crore.2. This is the first project processed under the Strategic Partnership model.Which of the statements given above is/are correct?a)1 onlyb)2 onlyc)Both 1 and 2d)Neither 1 nor 2Correct answer is option 'C'. Can you explain this answer? covers all topics & solutions for UPSC 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for With reference to the Project P 75 (I), consider the following statements:1. This project envisages indigenous construction of six conventional submarines equipped with the state-of-the-art Air Independent Propulsion system at an estimated cost of Rs 43,000 crore.2. This is the first project processed under the Strategic Partnership model.Which of the statements given above is/are correct?a)1 onlyb)2 onlyc)Both 1 and 2d)Neither 1 nor 2Correct answer is option 'C'. Can you explain this answer?.
Solutions for With reference to the Project P 75 (I), consider the following statements:1. This project envisages indigenous construction of six conventional submarines equipped with the state-of-the-art Air Independent Propulsion system at an estimated cost of Rs 43,000 crore.2. This is the first project processed under the Strategic Partnership model.Which of the statements given above is/are correct?a)1 onlyb)2 onlyc)Both 1 and 2d)Neither 1 nor 2Correct answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for UPSC. Download more important topics, notes, lectures and mock test series for UPSC Exam by signing up for free.
Here you can find the meaning of With reference to the Project P 75 (I), consider the following statements:1. This project envisages indigenous construction of six conventional submarines equipped with the state-of-the-art Air Independent Propulsion system at an estimated cost of Rs 43,000 crore.2. This is the first project processed under the Strategic Partnership model.Which of the statements given above is/are correct?a)1 onlyb)2 onlyc)Both 1 and 2d)Neither 1 nor 2Correct answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of With reference to the Project P 75 (I), consider the following statements:1. This project envisages indigenous construction of six conventional submarines equipped with the state-of-the-art Air Independent Propulsion system at an estimated cost of Rs 43,000 crore.2. This is the first project processed under the Strategic Partnership model.Which of the statements given above is/are correct?a)1 onlyb)2 onlyc)Both 1 and 2d)Neither 1 nor 2Correct answer is option 'C'. Can you explain this answer?, a detailed solution for With reference to the Project P 75 (I), consider the following statements:1. This project envisages indigenous construction of six conventional submarines equipped with the state-of-the-art Air Independent Propulsion system at an estimated cost of Rs 43,000 crore.2. This is the first project processed under the Strategic Partnership model.Which of the statements given above is/are correct?a)1 onlyb)2 onlyc)Both 1 and 2d)Neither 1 nor 2Correct answer is option 'C'. Can you explain this answer? has been provided alongside types of With reference to the Project P 75 (I), consider the following statements:1. This project envisages indigenous construction of six conventional submarines equipped with the state-of-the-art Air Independent Propulsion system at an estimated cost of Rs 43,000 crore.2. This is the first project processed under the Strategic Partnership model.Which of the statements given above is/are correct?a)1 onlyb)2 onlyc)Both 1 and 2d)Neither 1 nor 2Correct answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice With reference to the Project P 75 (I), consider the following statements:1. This project envisages indigenous construction of six conventional submarines equipped with the state-of-the-art Air Independent Propulsion system at an estimated cost of Rs 43,000 crore.2. This is the first project processed under the Strategic Partnership model.Which of the statements given above is/are correct?a)1 onlyb)2 onlyc)Both 1 and 2d)Neither 1 nor 2Correct answer is option 'C'. Can you explain this answer? tests, examples and also practice UPSC tests.
Explore Courses for UPSC exam

Top Courses for UPSC

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev