UPSC Exam  >  UPSC Questions  >  Which of the following could be the reasons f... Start Learning for Free
Which of the following could be the reasons for the failure of infrastructure projects by the public sector enterprises?
  1. Cost overruns.
  2. Ineffective Governance
  3. Lack of inter-ministerial/departmental coordination
  4. Optimum input-output ratio is rarely observed leading to overcapitalisation
Select the correct answer code:
  • a)
    1, 2, 3 
  • b)
    1, 3, 4 
  • c)
    2, 3, 4 
  • d)
    1, 2, 3, 4
Correct answer is option 'D'. Can you explain this answer?
Most Upvoted Answer
Which of the following could be the reasons for the failure of infrast...
The primary reasons for the failure of public sector enterprises is no secret. Cost overruns, inter alia, is one of the major reasons. In some cases, project completion time is exceeded, leading to elevated project cost so much so that either the project itself becomes unviable at the time of its launching or delays its break even point. Besides, optimum input-output ratio is seldom observed in a majority of government infrastructural projects leading to their overcapitalisation. A reluctance to implement labour reforms, a lack of inter-ministerial/departmental coordination, poor decision-making, ineffective governance and excessive government control are other reasons for the failure of public infrastructural assets.
Explore Courses for UPSC exam

Top Courses for UPSC

Which of the following could be the reasons for the failure of infrastructure projects by the public sector enterprises? Cost overruns. Ineffective Governance Lack of inter-ministerial/departmental coordination Optimum input-output ratio is rarely observed leading to overcapitalisationSelect the correct answer code:a)1, 2, 3b)1, 3, 4c)2, 3, 4d)1, 2, 3, 4Correct answer is option 'D'. Can you explain this answer?
Question Description
Which of the following could be the reasons for the failure of infrastructure projects by the public sector enterprises? Cost overruns. Ineffective Governance Lack of inter-ministerial/departmental coordination Optimum input-output ratio is rarely observed leading to overcapitalisationSelect the correct answer code:a)1, 2, 3b)1, 3, 4c)2, 3, 4d)1, 2, 3, 4Correct answer is option 'D'. Can you explain this answer? for UPSC 2024 is part of UPSC preparation. The Question and answers have been prepared according to the UPSC exam syllabus. Information about Which of the following could be the reasons for the failure of infrastructure projects by the public sector enterprises? Cost overruns. Ineffective Governance Lack of inter-ministerial/departmental coordination Optimum input-output ratio is rarely observed leading to overcapitalisationSelect the correct answer code:a)1, 2, 3b)1, 3, 4c)2, 3, 4d)1, 2, 3, 4Correct answer is option 'D'. Can you explain this answer? covers all topics & solutions for UPSC 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Which of the following could be the reasons for the failure of infrastructure projects by the public sector enterprises? Cost overruns. Ineffective Governance Lack of inter-ministerial/departmental coordination Optimum input-output ratio is rarely observed leading to overcapitalisationSelect the correct answer code:a)1, 2, 3b)1, 3, 4c)2, 3, 4d)1, 2, 3, 4Correct answer is option 'D'. Can you explain this answer?.
Solutions for Which of the following could be the reasons for the failure of infrastructure projects by the public sector enterprises? Cost overruns. Ineffective Governance Lack of inter-ministerial/departmental coordination Optimum input-output ratio is rarely observed leading to overcapitalisationSelect the correct answer code:a)1, 2, 3b)1, 3, 4c)2, 3, 4d)1, 2, 3, 4Correct answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for UPSC. Download more important topics, notes, lectures and mock test series for UPSC Exam by signing up for free.
Here you can find the meaning of Which of the following could be the reasons for the failure of infrastructure projects by the public sector enterprises? Cost overruns. Ineffective Governance Lack of inter-ministerial/departmental coordination Optimum input-output ratio is rarely observed leading to overcapitalisationSelect the correct answer code:a)1, 2, 3b)1, 3, 4c)2, 3, 4d)1, 2, 3, 4Correct answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Which of the following could be the reasons for the failure of infrastructure projects by the public sector enterprises? Cost overruns. Ineffective Governance Lack of inter-ministerial/departmental coordination Optimum input-output ratio is rarely observed leading to overcapitalisationSelect the correct answer code:a)1, 2, 3b)1, 3, 4c)2, 3, 4d)1, 2, 3, 4Correct answer is option 'D'. Can you explain this answer?, a detailed solution for Which of the following could be the reasons for the failure of infrastructure projects by the public sector enterprises? Cost overruns. Ineffective Governance Lack of inter-ministerial/departmental coordination Optimum input-output ratio is rarely observed leading to overcapitalisationSelect the correct answer code:a)1, 2, 3b)1, 3, 4c)2, 3, 4d)1, 2, 3, 4Correct answer is option 'D'. Can you explain this answer? has been provided alongside types of Which of the following could be the reasons for the failure of infrastructure projects by the public sector enterprises? Cost overruns. Ineffective Governance Lack of inter-ministerial/departmental coordination Optimum input-output ratio is rarely observed leading to overcapitalisationSelect the correct answer code:a)1, 2, 3b)1, 3, 4c)2, 3, 4d)1, 2, 3, 4Correct answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Which of the following could be the reasons for the failure of infrastructure projects by the public sector enterprises? Cost overruns. Ineffective Governance Lack of inter-ministerial/departmental coordination Optimum input-output ratio is rarely observed leading to overcapitalisationSelect the correct answer code:a)1, 2, 3b)1, 3, 4c)2, 3, 4d)1, 2, 3, 4Correct answer is option 'D'. Can you explain this answer? tests, examples and also practice UPSC tests.
Explore Courses for UPSC exam

Top Courses for UPSC

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev