A takes 20 days to complete a piece of work. B takes 10 days to complete the same piece of work. C takes 30 days to complete the same work. A starts the work and B joins him after 5 days. C joins them 4 days later. Find the time taken by the three of them to complete the work after C joins them.
  • a)
    9/11 days
  • b)
    ¾ days
  • c)
    1 day
  • d)
    24 hours
Correct answer is option 'A'. Can you explain this answer?
Most Upvoted Answer
A takes 20 days to complete a piece of work. B takes 10 days to compl...
Understanding Work Rates
To solve the problem, we first determine the work rates of A, B, and C.
- A completes the work in 20 days, so A's work rate is 1/20 of the work per day.
- B completes the work in 10 days, so B's work rate is 1/10 of the work per day.
- C completes the work in 30 days, so C's work rate is 1/30 of the work per day.
Calculating Work Done by A in 5 Days
- A works alone for the first 5 days.
- Work done by A in 5 days = 5 * (1/20) = 5/20 = 1/4 of the work.
Work Remaining After 5 Days
- Total work is 1, so work remaining = 1 - 1/4 = 3/4 of the work.
C Joining After 9 Days
- B joins A after 5 days, so they work together for the next 4 days.
- Combined work rate of A and B = (1/20 + 1/10) = (1/20 + 2/20) = 3/20.
Work Done by A and B in 4 Days
- Work done by A and B in 4 days = 4 * (3/20) = 12/20 = 3/5 of the work.
Calculating Total Work Done Before C Joins
- Work completed by A and B together = 1/4 + 3/5.
- To add these fractions, convert them to a common denominator (20):
- 1/4 = 5/20, 3/5 = 12/20.
- Total work done = 5/20 + 12/20 = 17/20.
Remaining Work After 9 Days
- Work remaining = 1 - 17/20 = 3/20 of the work.
Work Rate of A, B, and C Together
- Combined work rate of A, B, and C = (1/20 + 1/10 + 1/30).
- Finding a common denominator (60):
- 1/20 = 3/60, 1/10 = 6/60, 1/30 = 2/60.
- Combined rate = 3/60 + 6/60 + 2/60 = 11/60.
Time Taken to Complete Remaining Work
- Time = Remaining work / Combined work rate = (3/20) / (11/60) = (3/20) * (60/11) = 9/11 days.
Thus, the time taken by A, B, and C to complete the work after C joins them is 9/11 days.
Free Test
Community Answer
A takes 20 days to complete a piece of work. B takes 10 days to compl...
Let the total work be 600 units.
A’s one-day work = 30 units
B’s one-day work = 60 units
C’s one-day work = 20 units
Work done by A in the first 5 days = 5 * 30 = 150 units
Work done by A and B in the next 5 days = 4 * (30 + 60) = 360 units
Work remaining = 600 - (150 + 360) = 90 units
(A+B+C)’s one-day work = 30+60+20 = 110 units
So, time taken to complete 90 units of work = 90/110 days = 9/11 days
Explore Courses for CAT exam

Similar CAT Doubts

Top Courses for CAT

A takes 20 days to complete a piece of work. B takes 10 days to complete the same piece of work. C takes 30 days to complete the same work. A starts the work and B joins him after 5 days. C joins them 4 days later. Find the time taken by the three of them to complete the work after C joins them.a)9/11 daysb)¾ daysc)1 dayd)24 hoursCorrect answer is option 'A'. Can you explain this answer?
Question Description
A takes 20 days to complete a piece of work. B takes 10 days to complete the same piece of work. C takes 30 days to complete the same work. A starts the work and B joins him after 5 days. C joins them 4 days later. Find the time taken by the three of them to complete the work after C joins them.a)9/11 daysb)¾ daysc)1 dayd)24 hoursCorrect answer is option 'A'. Can you explain this answer? for CAT 2025 is part of CAT preparation. The Question and answers have been prepared according to the CAT exam syllabus. Information about A takes 20 days to complete a piece of work. B takes 10 days to complete the same piece of work. C takes 30 days to complete the same work. A starts the work and B joins him after 5 days. C joins them 4 days later. Find the time taken by the three of them to complete the work after C joins them.a)9/11 daysb)¾ daysc)1 dayd)24 hoursCorrect answer is option 'A'. Can you explain this answer? covers all topics & solutions for CAT 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A takes 20 days to complete a piece of work. B takes 10 days to complete the same piece of work. C takes 30 days to complete the same work. A starts the work and B joins him after 5 days. C joins them 4 days later. Find the time taken by the three of them to complete the work after C joins them.a)9/11 daysb)¾ daysc)1 dayd)24 hoursCorrect answer is option 'A'. Can you explain this answer?.
Solutions for A takes 20 days to complete a piece of work. B takes 10 days to complete the same piece of work. C takes 30 days to complete the same work. A starts the work and B joins him after 5 days. C joins them 4 days later. Find the time taken by the three of them to complete the work after C joins them.a)9/11 daysb)¾ daysc)1 dayd)24 hoursCorrect answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for CAT. Download more important topics, notes, lectures and mock test series for CAT Exam by signing up for free.
Here you can find the meaning of A takes 20 days to complete a piece of work. B takes 10 days to complete the same piece of work. C takes 30 days to complete the same work. A starts the work and B joins him after 5 days. C joins them 4 days later. Find the time taken by the three of them to complete the work after C joins them.a)9/11 daysb)¾ daysc)1 dayd)24 hoursCorrect answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A takes 20 days to complete a piece of work. B takes 10 days to complete the same piece of work. C takes 30 days to complete the same work. A starts the work and B joins him after 5 days. C joins them 4 days later. Find the time taken by the three of them to complete the work after C joins them.a)9/11 daysb)¾ daysc)1 dayd)24 hoursCorrect answer is option 'A'. Can you explain this answer?, a detailed solution for A takes 20 days to complete a piece of work. B takes 10 days to complete the same piece of work. C takes 30 days to complete the same work. A starts the work and B joins him after 5 days. C joins them 4 days later. Find the time taken by the three of them to complete the work after C joins them.a)9/11 daysb)¾ daysc)1 dayd)24 hoursCorrect answer is option 'A'. Can you explain this answer? has been provided alongside types of A takes 20 days to complete a piece of work. B takes 10 days to complete the same piece of work. C takes 30 days to complete the same work. A starts the work and B joins him after 5 days. C joins them 4 days later. Find the time taken by the three of them to complete the work after C joins them.a)9/11 daysb)¾ daysc)1 dayd)24 hoursCorrect answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A takes 20 days to complete a piece of work. B takes 10 days to complete the same piece of work. C takes 30 days to complete the same work. A starts the work and B joins him after 5 days. C joins them 4 days later. Find the time taken by the three of them to complete the work after C joins them.a)9/11 daysb)¾ daysc)1 dayd)24 hoursCorrect answer is option 'A'. Can you explain this answer? tests, examples and also practice CAT tests.
Explore Courses for CAT exam

Top Courses for CAT

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev