Civil Engineering (CE) Exam  >  Civil Engineering (CE) Questions  >   1. Under reamed piles are precast piles with... Start Learning for Free
1. Under reamed piles are precast piles with one or more under reams in each pile.
2. Under reamed piles are designed as bearing piles.
3. The length of traditional under reamed pile ranges from 3 m to 4 m.
Which of the above statements is/are correct?
  • a)
    Only 1 and 2
  • b)
    Only 2 and 3
  • c)
    Only 1 and 3
  • d)
    1, 2 and 3
Correct answer is option 'B'. Can you explain this answer?
Most Upvoted Answer
1. Under reamed piles are precast piles with one or more under reams ...
Under reamed piles are cast in situ piles which may be installed both in sandy and clayey soils.
Under reamed piles are designed as bearing piles.
The length of traditional under reamed pile ranges from 3 m to 4 m.
As given statements 2 and 3 are correct.
Free Test
Community Answer
1. Under reamed piles are precast piles with one or more under reams ...
Explanation:

Under reamed piles are a type of precast piles used in foundation construction. They have one or more under reams in each pile. These under reams are enlarged bulb-like sections at the base of the pile that increase the bearing capacity of the pile.

Statement 1: Under reamed piles are precast piles with one or more under reams in each pile.

This statement is correct. Under reamed piles are indeed precast piles with under reams in each pile. The under reams are created by using special tools during the casting process.

Statement 2: Under reamed piles are designed as bearing piles.

This statement is also correct. Under reamed piles are primarily designed as bearing piles. The under reams at the base of the pile increase the bearing capacity and improve the load distribution of the pile.

Statement 3: The length of traditional under reamed pile ranges from 3 m to 4 m.

This statement is incorrect. The length of traditional under reamed piles can vary depending on the specific project requirements. They can be shorter or longer than 3 m to 4 m. The length of the pile is determined based on factors such as the soil conditions, the load-bearing capacity required, and the depth of the foundation.

Therefore, the correct statements are:

a) Only 1 and 2
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

1. Under reamed piles are precast piles with one or more under reams in each pile.2. Under reamed piles are designed as bearing piles.3. The length of traditional under reamed pile ranges from 3 m to 4 m.Which of the above statements is/are correct?a)Only 1 and 2b)Only 2 and 3c)Only 1 and 3d)1, 2 and 3Correct answer is option 'B'. Can you explain this answer?
Question Description
1. Under reamed piles are precast piles with one or more under reams in each pile.2. Under reamed piles are designed as bearing piles.3. The length of traditional under reamed pile ranges from 3 m to 4 m.Which of the above statements is/are correct?a)Only 1 and 2b)Only 2 and 3c)Only 1 and 3d)1, 2 and 3Correct answer is option 'B'. Can you explain this answer? for Civil Engineering (CE) 2025 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about 1. Under reamed piles are precast piles with one or more under reams in each pile.2. Under reamed piles are designed as bearing piles.3. The length of traditional under reamed pile ranges from 3 m to 4 m.Which of the above statements is/are correct?a)Only 1 and 2b)Only 2 and 3c)Only 1 and 3d)1, 2 and 3Correct answer is option 'B'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for 1. Under reamed piles are precast piles with one or more under reams in each pile.2. Under reamed piles are designed as bearing piles.3. The length of traditional under reamed pile ranges from 3 m to 4 m.Which of the above statements is/are correct?a)Only 1 and 2b)Only 2 and 3c)Only 1 and 3d)1, 2 and 3Correct answer is option 'B'. Can you explain this answer?.
Solutions for 1. Under reamed piles are precast piles with one or more under reams in each pile.2. Under reamed piles are designed as bearing piles.3. The length of traditional under reamed pile ranges from 3 m to 4 m.Which of the above statements is/are correct?a)Only 1 and 2b)Only 2 and 3c)Only 1 and 3d)1, 2 and 3Correct answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of 1. Under reamed piles are precast piles with one or more under reams in each pile.2. Under reamed piles are designed as bearing piles.3. The length of traditional under reamed pile ranges from 3 m to 4 m.Which of the above statements is/are correct?a)Only 1 and 2b)Only 2 and 3c)Only 1 and 3d)1, 2 and 3Correct answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of 1. Under reamed piles are precast piles with one or more under reams in each pile.2. Under reamed piles are designed as bearing piles.3. The length of traditional under reamed pile ranges from 3 m to 4 m.Which of the above statements is/are correct?a)Only 1 and 2b)Only 2 and 3c)Only 1 and 3d)1, 2 and 3Correct answer is option 'B'. Can you explain this answer?, a detailed solution for 1. Under reamed piles are precast piles with one or more under reams in each pile.2. Under reamed piles are designed as bearing piles.3. The length of traditional under reamed pile ranges from 3 m to 4 m.Which of the above statements is/are correct?a)Only 1 and 2b)Only 2 and 3c)Only 1 and 3d)1, 2 and 3Correct answer is option 'B'. Can you explain this answer? has been provided alongside types of 1. Under reamed piles are precast piles with one or more under reams in each pile.2. Under reamed piles are designed as bearing piles.3. The length of traditional under reamed pile ranges from 3 m to 4 m.Which of the above statements is/are correct?a)Only 1 and 2b)Only 2 and 3c)Only 1 and 3d)1, 2 and 3Correct answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice 1. Under reamed piles are precast piles with one or more under reams in each pile.2. Under reamed piles are designed as bearing piles.3. The length of traditional under reamed pile ranges from 3 m to 4 m.Which of the above statements is/are correct?a)Only 1 and 2b)Only 2 and 3c)Only 1 and 3d)1, 2 and 3Correct answer is option 'B'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev