A PERT network has 9 activities on its critical path. The standard dev...
In CPM:
The standard deviation of critical path:
Where, σ
1, σ
2, ...., σ
8, σ
9 are the standard deviation of each activity on the critical path
Calculation:
Given:
σ
1, σ
2, ...., σ
8, σ
9 = 3
∴ the standard deviation of the critical path is 9.
A PERT network has 9 activities on its critical path. The standard dev...
Introduction:
In project management, a PERT (Program Evaluation and Review Technique) network is a tool used to schedule, organize, and manage tasks within a project. It helps in determining the critical path, which is the longest sequence of activities that must be completed in order to finish the project on time.
Given Information:
- The PERT network has 9 activities on its critical path.
- The standard deviation of each activity on the critical path is 3.
Calculating Standard Deviation of the Critical Path:
To calculate the standard deviation of the critical path, we need to understand the concept of variance. Variance is the square of the standard deviation.
Formula:
For a sequence of activities, the variance of the critical path is equal to the sum of the variances of the individual activities on the critical path.
Calculating Variance:
Since the standard deviation of each activity on the critical path is given as 3, we can calculate the variance of each activity by squaring the standard deviation.
Variance = (Standard Deviation)^2 = 3^2 = 9
Summing Up the Variances:
Since the variance is additive, we can sum up the variances of all 9 activities on the critical path to find the variance of the critical path.
Variance of Critical Path = Sum of Variances of Individual Activities
= 9 + 9 + 9 + 9 + 9 + 9 + 9 + 9 + 9
= 81
Calculating Standard Deviation:
To find the standard deviation of the critical path, we need to take the square root of the variance.
Standard Deviation = √Variance = √81 = 9
Conclusion:
Therefore, the standard deviation of the critical path is 9. Hence, the correct answer is option 'B'.