In Construction Management, the Critical Path Network helps an engineer
  • a)
    To concentrate his attention on critical activities
  • b)
    To divert the resources from non-critical advanced activities to critical activities
  • c)
    To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
  • d)
    All of the above
Correct answer is option 'D'. Can you explain this answer?
Verified Answer
In Construction Management, the Critical Path Network helps an enginee...
Concept:
  • The critical path is the longest path time-wise which can be determined from the forwarding path method only.
  • The critical path is the longest path through the network and time along this path gives the project duration. The critical path joins those activities which are critical.
  • The activities on the critical path are those activities that have total float equal to zero.
  • The activities that control the project duration are the ones that have zero total floats and form a continuous chain or path starting at the first node and ending with the last node.
So the Critical Path Network helps an engineer:
  • To concentrate his attention on critical activities.
  • To divert the resources from non-critical advanced activities to critical activities.
  • To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project.
So here all of the above options are correct.
View all questions of this test
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

In Construction Management, the Critical Path Network helps an engineera)To concentrate his attention on critical activitiesb)To divert the resources from non-critical advanced activities to critical activitiesc)To be cautious for avoiding any delay in the critical activities to avoid delay of the whole projectd)All of the aboveCorrect answer is option 'D'. Can you explain this answer?
Question Description
In Construction Management, the Critical Path Network helps an engineera)To concentrate his attention on critical activitiesb)To divert the resources from non-critical advanced activities to critical activitiesc)To be cautious for avoiding any delay in the critical activities to avoid delay of the whole projectd)All of the aboveCorrect answer is option 'D'. Can you explain this answer? for Civil Engineering (CE) 2025 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about In Construction Management, the Critical Path Network helps an engineera)To concentrate his attention on critical activitiesb)To divert the resources from non-critical advanced activities to critical activitiesc)To be cautious for avoiding any delay in the critical activities to avoid delay of the whole projectd)All of the aboveCorrect answer is option 'D'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for In Construction Management, the Critical Path Network helps an engineera)To concentrate his attention on critical activitiesb)To divert the resources from non-critical advanced activities to critical activitiesc)To be cautious for avoiding any delay in the critical activities to avoid delay of the whole projectd)All of the aboveCorrect answer is option 'D'. Can you explain this answer?.
Solutions for In Construction Management, the Critical Path Network helps an engineera)To concentrate his attention on critical activitiesb)To divert the resources from non-critical advanced activities to critical activitiesc)To be cautious for avoiding any delay in the critical activities to avoid delay of the whole projectd)All of the aboveCorrect answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of In Construction Management, the Critical Path Network helps an engineera)To concentrate his attention on critical activitiesb)To divert the resources from non-critical advanced activities to critical activitiesc)To be cautious for avoiding any delay in the critical activities to avoid delay of the whole projectd)All of the aboveCorrect answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of In Construction Management, the Critical Path Network helps an engineera)To concentrate his attention on critical activitiesb)To divert the resources from non-critical advanced activities to critical activitiesc)To be cautious for avoiding any delay in the critical activities to avoid delay of the whole projectd)All of the aboveCorrect answer is option 'D'. Can you explain this answer?, a detailed solution for In Construction Management, the Critical Path Network helps an engineera)To concentrate his attention on critical activitiesb)To divert the resources from non-critical advanced activities to critical activitiesc)To be cautious for avoiding any delay in the critical activities to avoid delay of the whole projectd)All of the aboveCorrect answer is option 'D'. Can you explain this answer? has been provided alongside types of In Construction Management, the Critical Path Network helps an engineera)To concentrate his attention on critical activitiesb)To divert the resources from non-critical advanced activities to critical activitiesc)To be cautious for avoiding any delay in the critical activities to avoid delay of the whole projectd)All of the aboveCorrect answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice In Construction Management, the Critical Path Network helps an engineera)To concentrate his attention on critical activitiesb)To divert the resources from non-critical advanced activities to critical activitiesc)To be cautious for avoiding any delay in the critical activities to avoid delay of the whole projectd)All of the aboveCorrect answer is option 'D'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev