In cost time optimization of a project, the project can be crashed by expediting
  • a)
    all activities on the critical path
  • b)
    critical activities having minimum cost slope
  • c)
    activities on sub critical path
  • d)
    all activities of the network
Correct answer is option 'B'. Can you explain this answer?
Most Upvoted Answer
In cost time optimization of a project, the project can be crashed by ...
Crashing a project

Crashing a project refers to the process of expediting or accelerating activities in order to complete the project in a shorter duration. This is typically done by reducing the time required for critical activities in the project's critical path. The critical path is the sequence of activities that determines the project's overall duration.

Cost-time optimization

Cost-time optimization involves finding the most efficient way to complete a project while minimizing costs. By crashing the project, the aim is to reduce its duration without significantly increasing the overall cost. This is achieved by identifying critical activities with the minimum cost slope.

Identifying critical activities with minimum cost slope

The cost slope of an activity represents the additional cost required to shorten its duration. By analyzing the cost slope of each critical activity, it is possible to identify those with the lowest cost slope. These activities are the most suitable candidates for crashing as they offer the greatest reduction in project duration for the least additional cost.

Activities on the critical path

Activities on the critical path have zero float, meaning any delay in their completion will directly impact the project's overall duration. Crashing these activities can significantly reduce the project's completion time as they are the most time-sensitive tasks. By focusing on these critical activities, it is possible to achieve the desired time optimization without affecting non-critical tasks.

Activities on sub-critical paths and all activities of the network

Activities on sub-critical paths have some float, indicating that a delay in their completion does not directly impact the project's overall duration. Crashing these activities may not provide a significant reduction in project duration as they are not time-sensitive. Similarly, crashing all activities of the network, including non-critical ones, may not result in the desired time optimization and can lead to unnecessary additional costs.

Conclusion

In cost-time optimization of a project, the most effective approach is to crash critical activities with the minimum cost slope. This strategy allows for the greatest reduction in project duration while minimizing the additional costs. By focusing on the critical path and identifying the most suitable activities for crashing, project managers can achieve time optimization without unnecessary expenses.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

In cost time optimization of a project, the project can be crashed by expeditinga)all activities on the critical pathb)critical activities having minimum cost slopec)activities on sub critical pathd)all activities of the networkCorrect answer is option 'B'. Can you explain this answer?
Question Description
In cost time optimization of a project, the project can be crashed by expeditinga)all activities on the critical pathb)critical activities having minimum cost slopec)activities on sub critical pathd)all activities of the networkCorrect answer is option 'B'. Can you explain this answer? for Civil Engineering (CE) 2025 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about In cost time optimization of a project, the project can be crashed by expeditinga)all activities on the critical pathb)critical activities having minimum cost slopec)activities on sub critical pathd)all activities of the networkCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for In cost time optimization of a project, the project can be crashed by expeditinga)all activities on the critical pathb)critical activities having minimum cost slopec)activities on sub critical pathd)all activities of the networkCorrect answer is option 'B'. Can you explain this answer?.
Solutions for In cost time optimization of a project, the project can be crashed by expeditinga)all activities on the critical pathb)critical activities having minimum cost slopec)activities on sub critical pathd)all activities of the networkCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of In cost time optimization of a project, the project can be crashed by expeditinga)all activities on the critical pathb)critical activities having minimum cost slopec)activities on sub critical pathd)all activities of the networkCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of In cost time optimization of a project, the project can be crashed by expeditinga)all activities on the critical pathb)critical activities having minimum cost slopec)activities on sub critical pathd)all activities of the networkCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for In cost time optimization of a project, the project can be crashed by expeditinga)all activities on the critical pathb)critical activities having minimum cost slopec)activities on sub critical pathd)all activities of the networkCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of In cost time optimization of a project, the project can be crashed by expeditinga)all activities on the critical pathb)critical activities having minimum cost slopec)activities on sub critical pathd)all activities of the networkCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice In cost time optimization of a project, the project can be crashed by expeditinga)all activities on the critical pathb)critical activities having minimum cost slopec)activities on sub critical pathd)all activities of the networkCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev