Setting up of which of the following projects will require mandatory Environmental Impact Assessment?
Thermal Power Station
  • Crude Oil Refineries
  • Special Waste Incineration
    Select the correct answer using the code given below.
    • a)
      1 only
    • b)
      1 and 3 only
    • c)
      2 and 3 only
    • d)
      1, 2 and 3
    Correct answer is option 'D'. Can you explain this answer?
    Most Upvoted Answer
    Setting up of which of the following projects will require mandatory ...
    • Environmental Impact Assessment has been defined as an activity that has been designed to identify, predict and interpret the impact of an action on human health, including the well being of ecosystems on which the survival of human beings depends.
    • EIA was introduced in India in 1978. EIA covers the following projects:
      • Mandatory EIA: Major projects that are mandatorily subjected to EIA before execution include crude oil refineries, thermal power stations, chemical installations, trading ports, special waste incineration, installations for the disposal of radioactive wastes, motorways and major roads, waste treatment or landfill, iron and steel industry, heavy mining, etc.
      • Discretionary EIA: Some projects are subjected to discretionary environmental assessment in case they are likely to have significant environmental effects. Such projects include poultry units, metal processing, mineral extracting, glass making, food manufacturing, holiday resorts, tanneries, paper industry etc.
    Hence option (d) is the correct answer.
    Explore Courses for UPSC exam

    Top Courses for UPSC

    Setting up of which of the following projects will require mandatory Environmental Impact Assessment? Thermal Power Station Crude Oil Refineries Special Waste Incineration Select the correct answer using the code given below.a)1 onlyb)1 and 3 onlyc)2 and 3 onlyd)1, 2 and 3Correct answer is option 'D'. Can you explain this answer?
    Question Description
    Setting up of which of the following projects will require mandatory Environmental Impact Assessment? Thermal Power Station Crude Oil Refineries Special Waste Incineration Select the correct answer using the code given below.a)1 onlyb)1 and 3 onlyc)2 and 3 onlyd)1, 2 and 3Correct answer is option 'D'. Can you explain this answer? for UPSC 2024 is part of UPSC preparation. The Question and answers have been prepared according to the UPSC exam syllabus. Information about Setting up of which of the following projects will require mandatory Environmental Impact Assessment? Thermal Power Station Crude Oil Refineries Special Waste Incineration Select the correct answer using the code given below.a)1 onlyb)1 and 3 onlyc)2 and 3 onlyd)1, 2 and 3Correct answer is option 'D'. Can you explain this answer? covers all topics & solutions for UPSC 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Setting up of which of the following projects will require mandatory Environmental Impact Assessment? Thermal Power Station Crude Oil Refineries Special Waste Incineration Select the correct answer using the code given below.a)1 onlyb)1 and 3 onlyc)2 and 3 onlyd)1, 2 and 3Correct answer is option 'D'. Can you explain this answer?.
    Solutions for Setting up of which of the following projects will require mandatory Environmental Impact Assessment? Thermal Power Station Crude Oil Refineries Special Waste Incineration Select the correct answer using the code given below.a)1 onlyb)1 and 3 onlyc)2 and 3 onlyd)1, 2 and 3Correct answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for UPSC. Download more important topics, notes, lectures and mock test series for UPSC Exam by signing up for free.
    Here you can find the meaning of Setting up of which of the following projects will require mandatory Environmental Impact Assessment? Thermal Power Station Crude Oil Refineries Special Waste Incineration Select the correct answer using the code given below.a)1 onlyb)1 and 3 onlyc)2 and 3 onlyd)1, 2 and 3Correct answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Setting up of which of the following projects will require mandatory Environmental Impact Assessment? Thermal Power Station Crude Oil Refineries Special Waste Incineration Select the correct answer using the code given below.a)1 onlyb)1 and 3 onlyc)2 and 3 onlyd)1, 2 and 3Correct answer is option 'D'. Can you explain this answer?, a detailed solution for Setting up of which of the following projects will require mandatory Environmental Impact Assessment? Thermal Power Station Crude Oil Refineries Special Waste Incineration Select the correct answer using the code given below.a)1 onlyb)1 and 3 onlyc)2 and 3 onlyd)1, 2 and 3Correct answer is option 'D'. Can you explain this answer? has been provided alongside types of Setting up of which of the following projects will require mandatory Environmental Impact Assessment? Thermal Power Station Crude Oil Refineries Special Waste Incineration Select the correct answer using the code given below.a)1 onlyb)1 and 3 onlyc)2 and 3 onlyd)1, 2 and 3Correct answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Setting up of which of the following projects will require mandatory Environmental Impact Assessment? Thermal Power Station Crude Oil Refineries Special Waste Incineration Select the correct answer using the code given below.a)1 onlyb)1 and 3 onlyc)2 and 3 onlyd)1, 2 and 3Correct answer is option 'D'. Can you explain this answer? tests, examples and also practice UPSC tests.
    Explore Courses for UPSC exam

    Top Courses for UPSC

    Explore Courses
    Signup for Free!
    Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
    10M+ students study on EduRev