A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows rs.200 for 1st day rs.250 for second day we.300 for third day and so on if the contractor pays rs. 27750 as penalty find the no. of days for which the construction work is delayed?
Most Upvoted Answer
A contract on construction job specifies a penalty for delay of comple...
Understanding the Penalty Structure
The penalty for delay in completion of the construction job increases with each passing day. The structure is as follows:
- Rs. 200 for the 1st day
- Rs. 250 for the 2nd day
- Rs. 300 for the 3rd day
- Rs. 350 for the 4th day
- And so on...
This penalty increases by Rs. 50 for each successive day.
Finding the Total Penalty Paid
The total penalty paid by the contractor is Rs. 27,750. We can express the penalty for each day mathematically. The penalty for the nth day can be represented as:
- Penalty on day n = Rs. (200 + 50(n - 1))
To find the total penalty for 'd' days, we need to sum the penalties from day 1 to day d.
Calculating the Total Payment
The total penalty can be calculated using the sum formula for arithmetic series:
- Total penalty = (Number of days) / 2 x (First term + Last term)
Where:
- First term (day 1) = Rs. 200
- Last term (day d) = Rs. (200 + 50(d - 1))
Thus,
- Total penalty = d/2 x (200 + (200 + 50(d - 1)))
Setting this equal to Rs. 27,750, we can simplify and solve for 'd'.
Solving the Equation
From the equation:
- 27,750 = d/2 x (400 + 50(d - 1))
This simplifies to:
- 27,750 = d/2 x (50d + 350)
By multiplying through by 2 and rearranging terms, we can find the value of 'd'.
Final Calculation
After performing the necessary calculations, we find that:
- The number of days delayed (d) = 30 days
Thus, the construction work was delayed for 30 days, resulting in a total penalty of Rs. 27,750.
Community Answer
A contract on construction job specifies a penalty for delay of comple...
Sn=n/2[2a+(n-1) d 27750=n/2[2*200+(n-1)50 Solve it answer will come 30 days
Explore Courses for Class 10 exam

Top Courses for Class 10

A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows rs.200 for 1st day rs.250 for second day we.300 for third day and so on if the contractor pays rs. 27750 as penalty find the no. of days for which the construction work is delayed?
Question Description
A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows rs.200 for 1st day rs.250 for second day we.300 for third day and so on if the contractor pays rs. 27750 as penalty find the no. of days for which the construction work is delayed? for Class 10 2025 is part of Class 10 preparation. The Question and answers have been prepared according to the Class 10 exam syllabus. Information about A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows rs.200 for 1st day rs.250 for second day we.300 for third day and so on if the contractor pays rs. 27750 as penalty find the no. of days for which the construction work is delayed? covers all topics & solutions for Class 10 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows rs.200 for 1st day rs.250 for second day we.300 for third day and so on if the contractor pays rs. 27750 as penalty find the no. of days for which the construction work is delayed?.
Solutions for A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows rs.200 for 1st day rs.250 for second day we.300 for third day and so on if the contractor pays rs. 27750 as penalty find the no. of days for which the construction work is delayed? in English & in Hindi are available as part of our courses for Class 10. Download more important topics, notes, lectures and mock test series for Class 10 Exam by signing up for free.
Here you can find the meaning of A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows rs.200 for 1st day rs.250 for second day we.300 for third day and so on if the contractor pays rs. 27750 as penalty find the no. of days for which the construction work is delayed? defined & explained in the simplest way possible. Besides giving the explanation of A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows rs.200 for 1st day rs.250 for second day we.300 for third day and so on if the contractor pays rs. 27750 as penalty find the no. of days for which the construction work is delayed?, a detailed solution for A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows rs.200 for 1st day rs.250 for second day we.300 for third day and so on if the contractor pays rs. 27750 as penalty find the no. of days for which the construction work is delayed? has been provided alongside types of A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows rs.200 for 1st day rs.250 for second day we.300 for third day and so on if the contractor pays rs. 27750 as penalty find the no. of days for which the construction work is delayed? theory, EduRev gives you an ample number of questions to practice A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows rs.200 for 1st day rs.250 for second day we.300 for third day and so on if the contractor pays rs. 27750 as penalty find the no. of days for which the construction work is delayed? tests, examples and also practice Class 10 tests.
Explore Courses for Class 10 exam

Top Courses for Class 10

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev