A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows rs.200 for 1st day rs.250 for second day we.300 for third day and so on if the contractor pays rs. 27750 as penalty find the no. of days for which the construction work is delayed?
Most Upvoted Answer
A contract on construction job specifies a penalty for delay of comple...
Sn=n/2[2a+(n-1) d 27750=n/2[2*200+(n-1)50 Solve it answer will come 30 days
Explore Courses for Class 10 exam

Top Courses for Class 10

A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows rs.200 for 1st day rs.250 for second day we.300 for third day and so on if the contractor pays rs. 27750 as penalty find the no. of days for which the construction work is delayed?
Question Description
A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows rs.200 for 1st day rs.250 for second day we.300 for third day and so on if the contractor pays rs. 27750 as penalty find the no. of days for which the construction work is delayed? for Class 10 2025 is part of Class 10 preparation. The Question and answers have been prepared according to the Class 10 exam syllabus. Information about A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows rs.200 for 1st day rs.250 for second day we.300 for third day and so on if the contractor pays rs. 27750 as penalty find the no. of days for which the construction work is delayed? covers all topics & solutions for Class 10 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows rs.200 for 1st day rs.250 for second day we.300 for third day and so on if the contractor pays rs. 27750 as penalty find the no. of days for which the construction work is delayed?.
Solutions for A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows rs.200 for 1st day rs.250 for second day we.300 for third day and so on if the contractor pays rs. 27750 as penalty find the no. of days for which the construction work is delayed? in English & in Hindi are available as part of our courses for Class 10. Download more important topics, notes, lectures and mock test series for Class 10 Exam by signing up for free.
Here you can find the meaning of A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows rs.200 for 1st day rs.250 for second day we.300 for third day and so on if the contractor pays rs. 27750 as penalty find the no. of days for which the construction work is delayed? defined & explained in the simplest way possible. Besides giving the explanation of A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows rs.200 for 1st day rs.250 for second day we.300 for third day and so on if the contractor pays rs. 27750 as penalty find the no. of days for which the construction work is delayed?, a detailed solution for A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows rs.200 for 1st day rs.250 for second day we.300 for third day and so on if the contractor pays rs. 27750 as penalty find the no. of days for which the construction work is delayed? has been provided alongside types of A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows rs.200 for 1st day rs.250 for second day we.300 for third day and so on if the contractor pays rs. 27750 as penalty find the no. of days for which the construction work is delayed? theory, EduRev gives you an ample number of questions to practice A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows rs.200 for 1st day rs.250 for second day we.300 for third day and so on if the contractor pays rs. 27750 as penalty find the no. of days for which the construction work is delayed? tests, examples and also practice Class 10 tests.
Explore Courses for Class 10 exam

Top Courses for Class 10

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev