A and B together can do a piece of work in 7(1/5) days, B and C together can do the same piece of work in 10(2/7) days. A, B and C working together can complete the work in 4(1/2) days. In what time B working alone can complete the work?
  • a)
    18 days
  • b)
    24 days
  • c)
    72 days
  • d)
    36 days
  • e)
    48 days
Correct answer is option 'C'. Can you explain this answer?
Most Upvoted Answer
A and B together can do a piece of work in 7(1/5)days, B and C togethe...
GIVEN :
A and B together can do a piece of work in 36/5 days.
B and C together can do a piece of work in 72/7 days.
A, B and C together can do a piece of work in 9/2 days.
CALCULATION :
⇒ One day work of (A + B) = 5/36
⇒ One day work of (B + C) = 7/72
⇒ One day work of (A + B + C) = 2/9
One day work A = One day work of (A + B + C) - One day work work of (B + C)
⇒ 2/9 - 7/72
⇒ 1/8
One day work of C = One day work of (A + B + C) - One day work work of (A + B)
⇒ 2/9 - 5/36
⇒ 1/12
One day work of (A + C) = 1/8 + 1/12 = 5/24
One day work of B = One day work of (A + B + C) - One day work work of (A + C)
⇒ 2/9 - 5/24
⇒ 1/72
∴ B alone can complete the work in 72 days.
Free Test
Community Answer
A and B together can do a piece of work in 7(1/5)days, B and C togethe...
Understanding the Problem
To determine how long B alone would take to complete the work, we start by converting the mixed fractions into improper fractions.
Work Rates of A, B, and C
- A and B together complete the work in 7(1/5) days, which is 36/5 days. Therefore, their combined work rate is 5/36 (work per day).
- B and C together complete the work in 10(2/7) days, which is 72/7 days. Thus, their combined work rate is 7/72 (work per day).
- A, B, and C together complete the work in 4(1/2) days, which is 9/2 days. Hence, their combined work rate is 2/9 (work per day).
Setting Up the Equations
Let the work rates of A, B, and C be a, b, and c respectively. We can set up the following equations based on the rates:
1. a + b = 5/36
2. b + c = 7/72
3. a + b + c = 2/9
Finding Individual Work Rates
From the third equation, we can express c in terms of a and b:
c = (2/9) - (a + b)
Substituting a + b from the first equation:
c = (2/9) - (5/36)
Converting (2/9) to a common denominator (36):
c = (8/36) - (5/36) = 3/36 = 1/12
Now substitute c back into the second equation:
b + (1/12) = 7/72
Converting (1/12) to common denominator (72):
b + (6/72) = 7/72
Thus, b = (7/72) - (6/72) = 1/72.
Calculating Time for B Alone
The time taken by B to complete the work alone is the reciprocal of b:
Time = 1 / (1/72) = 72 days.
Thus, the correct answer is option 'C': 72 days.
Explore Courses for Banking Exams exam

Similar Banking Exams Doubts

A and B together can do a piece of work in 7(1/5)days, B and C together can do the same piece of work in 10(2/7)days. A, B and C working together can complete the work in 4(1/2)days. In what time B working alone can complete the work?a)18 daysb)24 daysc)72 daysd)36 dayse)48 daysCorrect answer is option 'C'. Can you explain this answer?
Question Description
A and B together can do a piece of work in 7(1/5)days, B and C together can do the same piece of work in 10(2/7)days. A, B and C working together can complete the work in 4(1/2)days. In what time B working alone can complete the work?a)18 daysb)24 daysc)72 daysd)36 dayse)48 daysCorrect answer is option 'C'. Can you explain this answer? for Banking Exams 2025 is part of Banking Exams preparation. The Question and answers have been prepared according to the Banking Exams exam syllabus. Information about A and B together can do a piece of work in 7(1/5)days, B and C together can do the same piece of work in 10(2/7)days. A, B and C working together can complete the work in 4(1/2)days. In what time B working alone can complete the work?a)18 daysb)24 daysc)72 daysd)36 dayse)48 daysCorrect answer is option 'C'. Can you explain this answer? covers all topics & solutions for Banking Exams 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A and B together can do a piece of work in 7(1/5)days, B and C together can do the same piece of work in 10(2/7)days. A, B and C working together can complete the work in 4(1/2)days. In what time B working alone can complete the work?a)18 daysb)24 daysc)72 daysd)36 dayse)48 daysCorrect answer is option 'C'. Can you explain this answer?.
Solutions for A and B together can do a piece of work in 7(1/5)days, B and C together can do the same piece of work in 10(2/7)days. A, B and C working together can complete the work in 4(1/2)days. In what time B working alone can complete the work?a)18 daysb)24 daysc)72 daysd)36 dayse)48 daysCorrect answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Banking Exams. Download more important topics, notes, lectures and mock test series for Banking Exams Exam by signing up for free.
Here you can find the meaning of A and B together can do a piece of work in 7(1/5)days, B and C together can do the same piece of work in 10(2/7)days. A, B and C working together can complete the work in 4(1/2)days. In what time B working alone can complete the work?a)18 daysb)24 daysc)72 daysd)36 dayse)48 daysCorrect answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A and B together can do a piece of work in 7(1/5)days, B and C together can do the same piece of work in 10(2/7)days. A, B and C working together can complete the work in 4(1/2)days. In what time B working alone can complete the work?a)18 daysb)24 daysc)72 daysd)36 dayse)48 daysCorrect answer is option 'C'. Can you explain this answer?, a detailed solution for A and B together can do a piece of work in 7(1/5)days, B and C together can do the same piece of work in 10(2/7)days. A, B and C working together can complete the work in 4(1/2)days. In what time B working alone can complete the work?a)18 daysb)24 daysc)72 daysd)36 dayse)48 daysCorrect answer is option 'C'. Can you explain this answer? has been provided alongside types of A and B together can do a piece of work in 7(1/5)days, B and C together can do the same piece of work in 10(2/7)days. A, B and C working together can complete the work in 4(1/2)days. In what time B working alone can complete the work?a)18 daysb)24 daysc)72 daysd)36 dayse)48 daysCorrect answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A and B together can do a piece of work in 7(1/5)days, B and C together can do the same piece of work in 10(2/7)days. A, B and C working together can complete the work in 4(1/2)days. In what time B working alone can complete the work?a)18 daysb)24 daysc)72 daysd)36 dayse)48 daysCorrect answer is option 'C'. Can you explain this answer? tests, examples and also practice Banking Exams tests.
Explore Courses for Banking Exams exam

Top Courses for Banking Exams

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev