Question Description
15 men could finish a piece of work in 210 days. But at the end of 100 days, 15 additional menare employed. In how many more days will the work be complete?a)80 daysb)60 daysc)55 daysd)50 days? for UPSC 2024 is part of UPSC preparation. The Question and answers have been prepared
according to
the UPSC exam syllabus. Information about 15 men could finish a piece of work in 210 days. But at the end of 100 days, 15 additional menare employed. In how many more days will the work be complete?a)80 daysb)60 daysc)55 daysd)50 days? covers all topics & solutions for UPSC 2024 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for 15 men could finish a piece of work in 210 days. But at the end of 100 days, 15 additional menare employed. In how many more days will the work be complete?a)80 daysb)60 daysc)55 daysd)50 days?.
Solutions for 15 men could finish a piece of work in 210 days. But at the end of 100 days, 15 additional menare employed. In how many more days will the work be complete?a)80 daysb)60 daysc)55 daysd)50 days? in English & in Hindi are available as part of our courses for UPSC.
Download more important topics, notes, lectures and mock test series for UPSC Exam by signing up for free.
Here you can find the meaning of 15 men could finish a piece of work in 210 days. But at the end of 100 days, 15 additional menare employed. In how many more days will the work be complete?a)80 daysb)60 daysc)55 daysd)50 days? defined & explained in the simplest way possible. Besides giving the explanation of
15 men could finish a piece of work in 210 days. But at the end of 100 days, 15 additional menare employed. In how many more days will the work be complete?a)80 daysb)60 daysc)55 daysd)50 days?, a detailed solution for 15 men could finish a piece of work in 210 days. But at the end of 100 days, 15 additional menare employed. In how many more days will the work be complete?a)80 daysb)60 daysc)55 daysd)50 days? has been provided alongside types of 15 men could finish a piece of work in 210 days. But at the end of 100 days, 15 additional menare employed. In how many more days will the work be complete?a)80 daysb)60 daysc)55 daysd)50 days? theory, EduRev gives you an
ample number of questions to practice 15 men could finish a piece of work in 210 days. But at the end of 100 days, 15 additional menare employed. In how many more days will the work be complete?a)80 daysb)60 daysc)55 daysd)50 days? tests, examples and also practice UPSC tests.