Question Description
A worker has been allowed to complete a work in 12 hours,but he completes the work in 9 hours .labour rate per hour is rs.2.if cost of material is rs.8 and factory overheads are 150% of direct labour, find out factory cost as per following methods:1) Halsey plan2)Rowan pan3) piece rate system? for UPSC 2024 is part of UPSC preparation. The Question and answers have been prepared
according to
the UPSC exam syllabus. Information about A worker has been allowed to complete a work in 12 hours,but he completes the work in 9 hours .labour rate per hour is rs.2.if cost of material is rs.8 and factory overheads are 150% of direct labour, find out factory cost as per following methods:1) Halsey plan2)Rowan pan3) piece rate system? covers all topics & solutions for UPSC 2024 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for A worker has been allowed to complete a work in 12 hours,but he completes the work in 9 hours .labour rate per hour is rs.2.if cost of material is rs.8 and factory overheads are 150% of direct labour, find out factory cost as per following methods:1) Halsey plan2)Rowan pan3) piece rate system?.
Solutions for A worker has been allowed to complete a work in 12 hours,but he completes the work in 9 hours .labour rate per hour is rs.2.if cost of material is rs.8 and factory overheads are 150% of direct labour, find out factory cost as per following methods:1) Halsey plan2)Rowan pan3) piece rate system? in English & in Hindi are available as part of our courses for UPSC.
Download more important topics, notes, lectures and mock test series for UPSC Exam by signing up for free.
Here you can find the meaning of A worker has been allowed to complete a work in 12 hours,but he completes the work in 9 hours .labour rate per hour is rs.2.if cost of material is rs.8 and factory overheads are 150% of direct labour, find out factory cost as per following methods:1) Halsey plan2)Rowan pan3) piece rate system? defined & explained in the simplest way possible. Besides giving the explanation of
A worker has been allowed to complete a work in 12 hours,but he completes the work in 9 hours .labour rate per hour is rs.2.if cost of material is rs.8 and factory overheads are 150% of direct labour, find out factory cost as per following methods:1) Halsey plan2)Rowan pan3) piece rate system?, a detailed solution for A worker has been allowed to complete a work in 12 hours,but he completes the work in 9 hours .labour rate per hour is rs.2.if cost of material is rs.8 and factory overheads are 150% of direct labour, find out factory cost as per following methods:1) Halsey plan2)Rowan pan3) piece rate system? has been provided alongside types of A worker has been allowed to complete a work in 12 hours,but he completes the work in 9 hours .labour rate per hour is rs.2.if cost of material is rs.8 and factory overheads are 150% of direct labour, find out factory cost as per following methods:1) Halsey plan2)Rowan pan3) piece rate system? theory, EduRev gives you an
ample number of questions to practice A worker has been allowed to complete a work in 12 hours,but he completes the work in 9 hours .labour rate per hour is rs.2.if cost of material is rs.8 and factory overheads are 150% of direct labour, find out factory cost as per following methods:1) Halsey plan2)Rowan pan3) piece rate system? tests, examples and also practice UPSC tests.