54 men can do a work in 12 days. Find the amount of work done by 5 men in 12 days. in percentage?
Most Upvoted Answer
54 men can do a work in 12 days. Find the amount of work done by 5 men...
Understanding the Total Work
To calculate the work done by 5 men in 12 days, we first need to determine the total amount of work done by the original group of men.
- 54 men can complete the work in 12 days.
- Therefore, the total work can be expressed as:
Total Work = Number of Men × Days = 54 men × 12 days
Calculating the Total Work
- Total Work = 54 × 12 = 648 man-days
This means the total work required for the job is 648 man-days.
Work Done by 5 Men in 12 Days
Now, we'll find out how much work 5 men can accomplish in the same time frame of 12 days.
- Work done by 5 men in 12 days = 5 men × 12 days = 60 man-days
Percentage of Total Work Done
To find the percentage of the total work done by 5 men:
- Percentage = (Work done by 5 men / Total Work) × 100
Substituting the values:
- Percentage = (60 man-days / 648 man-days) × 100
Calculating that gives:
- Percentage ≈ 9.26%
Conclusion
In conclusion, the amount of work done by 5 men in 12 days represents approximately 9.26% of the total work. This highlights the efficiency and productivity variations when comparing different group sizes in completing a task.
Attention Class 10 Students!
To make sure you are not studying endlessly, EduRev has designed Class 10 study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Class 10.
Explore Courses for Class 10 exam

Top Courses for Class 10

54 men can do a work in 12 days. Find the amount of work done by 5 men in 12 days. in percentage?
Question Description
54 men can do a work in 12 days. Find the amount of work done by 5 men in 12 days. in percentage? for Class 10 2024 is part of Class 10 preparation. The Question and answers have been prepared according to the Class 10 exam syllabus. Information about 54 men can do a work in 12 days. Find the amount of work done by 5 men in 12 days. in percentage? covers all topics & solutions for Class 10 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for 54 men can do a work in 12 days. Find the amount of work done by 5 men in 12 days. in percentage?.
Solutions for 54 men can do a work in 12 days. Find the amount of work done by 5 men in 12 days. in percentage? in English & in Hindi are available as part of our courses for Class 10. Download more important topics, notes, lectures and mock test series for Class 10 Exam by signing up for free.
Here you can find the meaning of 54 men can do a work in 12 days. Find the amount of work done by 5 men in 12 days. in percentage? defined & explained in the simplest way possible. Besides giving the explanation of 54 men can do a work in 12 days. Find the amount of work done by 5 men in 12 days. in percentage?, a detailed solution for 54 men can do a work in 12 days. Find the amount of work done by 5 men in 12 days. in percentage? has been provided alongside types of 54 men can do a work in 12 days. Find the amount of work done by 5 men in 12 days. in percentage? theory, EduRev gives you an ample number of questions to practice 54 men can do a work in 12 days. Find the amount of work done by 5 men in 12 days. in percentage? tests, examples and also practice Class 10 tests.
Explore Courses for Class 10 exam

Top Courses for Class 10

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev