The probability distribution taken to represent the completion time in PERT analysis is:
  • a)
    Gamma distribution
  • b)
    Normal distribution
  • c)
    Beta distribution
  • d)
    none of these
Correct answer is option 'B'. Can you explain this answer?
Verified Answer
The probability distribution taken to represent the completion time in...
The distribution curve for the time taken in to complete each activity of a project resembles a beta-distribution curve and the distribution curve for the time taken to complete entire project ( consisting of several activities) in general resembles a normal distribution curve.
View all questions of this test
Most Upvoted Answer
The probability distribution taken to represent the completion time in...
PERT Analysis and Completion Time Probability Distribution

PERT (Program Evaluation and Review Technique) analysis is a project management tool used to determine the expected completion time of a project. It is based on the assumption that the completion time of a project is uncertain and can vary due to various factors such as delays, resource availability, and unforeseen events.

Probability Distribution in PERT Analysis

In PERT analysis, completion time is represented by a probability distribution. The probability distribution is used to determine the expected completion time of the project and the probability of completing the project within a given time frame.

There are three types of probability distributions that are commonly used in PERT analysis:

1. Normal Distribution: The normal distribution is a bell-shaped curve that is symmetrical around the mean. It is used when the completion time is affected by a large number of independent factors that are assumed to be normally distributed.

2. Beta Distribution: The beta distribution is a continuous probability distribution that is used when the completion time is affected by a limited number of independent factors. It is often used when there is uncertainty about the shape of the probability distribution.

3. Gamma Distribution: The gamma distribution is a continuous probability distribution that is used when the completion time is affected by a series of independent factors. It is often used when the distribution is skewed to the right.

Correct Answer

The correct answer to the question is option 'B', which is the normal distribution. The normal distribution is the most commonly used probability distribution in PERT analysis, as it assumes that the completion time is affected by a large number of independent factors that are normally distributed.
Free Test
Community Answer
The probability distribution taken to represent the completion time in...
Beta distribution is my ans... but here normal_distribution is given in answer
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

The probability distribution taken to represent the completion time in PERT analysis is:a)Gamma distributionb)Normal distributionc)Beta distributiond)none of theseCorrect answer is option 'B'. Can you explain this answer?
Question Description
The probability distribution taken to represent the completion time in PERT analysis is:a)Gamma distributionb)Normal distributionc)Beta distributiond)none of theseCorrect answer is option 'B'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about The probability distribution taken to represent the completion time in PERT analysis is:a)Gamma distributionb)Normal distributionc)Beta distributiond)none of theseCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The probability distribution taken to represent the completion time in PERT analysis is:a)Gamma distributionb)Normal distributionc)Beta distributiond)none of theseCorrect answer is option 'B'. Can you explain this answer?.
Solutions for The probability distribution taken to represent the completion time in PERT analysis is:a)Gamma distributionb)Normal distributionc)Beta distributiond)none of theseCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of The probability distribution taken to represent the completion time in PERT analysis is:a)Gamma distributionb)Normal distributionc)Beta distributiond)none of theseCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The probability distribution taken to represent the completion time in PERT analysis is:a)Gamma distributionb)Normal distributionc)Beta distributiond)none of theseCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for The probability distribution taken to represent the completion time in PERT analysis is:a)Gamma distributionb)Normal distributionc)Beta distributiond)none of theseCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of The probability distribution taken to represent the completion time in PERT analysis is:a)Gamma distributionb)Normal distributionc)Beta distributiond)none of theseCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The probability distribution taken to represent the completion time in PERT analysis is:a)Gamma distributionb)Normal distributionc)Beta distributiond)none of theseCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev