Question Description
150 workers were engaged to finish a piece of work in certain number of days 4 workers left on the second day, 4 more workers left on-third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed. I need the answer with steps well xplained? for Class 10 2024 is part of Class 10 preparation. The Question and answers have been prepared
according to
the Class 10 exam syllabus. Information about 150 workers were engaged to finish a piece of work in certain number of days 4 workers left on the second day, 4 more workers left on-third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed. I need the answer with steps well xplained? covers all topics & solutions for Class 10 2024 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for 150 workers were engaged to finish a piece of work in certain number of days 4 workers left on the second day, 4 more workers left on-third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed. I need the answer with steps well xplained?.
Solutions for 150 workers were engaged to finish a piece of work in certain number of days 4 workers left on the second day, 4 more workers left on-third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed. I need the answer with steps well xplained? in English & in Hindi are available as part of our courses for Class 10.
Download more important topics, notes, lectures and mock test series for Class 10 Exam by signing up for free.
Here you can find the meaning of 150 workers were engaged to finish a piece of work in certain number of days 4 workers left on the second day, 4 more workers left on-third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed. I need the answer with steps well xplained? defined & explained in the simplest way possible. Besides giving the explanation of
150 workers were engaged to finish a piece of work in certain number of days 4 workers left on the second day, 4 more workers left on-third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed. I need the answer with steps well xplained?, a detailed solution for 150 workers were engaged to finish a piece of work in certain number of days 4 workers left on the second day, 4 more workers left on-third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed. I need the answer with steps well xplained? has been provided alongside types of 150 workers were engaged to finish a piece of work in certain number of days 4 workers left on the second day, 4 more workers left on-third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed. I need the answer with steps well xplained? theory, EduRev gives you an
ample number of questions to practice 150 workers were engaged to finish a piece of work in certain number of days 4 workers left on the second day, 4 more workers left on-third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed. I need the answer with steps well xplained? tests, examples and also practice Class 10 tests.