Chemical Engineering Exam  >  Chemical Engineering Questions  >  What will be the surface area of the basin fo... Start Learning for Free
 What will be the surface area of the basin for a flow of 2*106 litre per day having a surface loading rate 10,000 litre/day/m2
  • a)
    100
  • b)
    200
  • c)
    300
  • d)
    400
Correct answer is option 'B'. Can you explain this answer?
Verified Answer
What will be the surface area of the basin for a flow of 2*106 litre p...
Explanation: Surface area of basin= flow of water/surface loading rate = 2000000/10000=200m2.
View all questions of this test
Most Upvoted Answer
What will be the surface area of the basin for a flow of 2*106 litre p...
Calculation of Surface Area of Basin

Given:
Flow rate = 2*106 litre per day
Surface loading rate = 10,000 litre/day/m2

We know that the formula for surface loading rate is:

Surface loading rate = Flow rate / Surface area

Rearranging the formula, we get:

Surface area = Flow rate / Surface loading rate

Substituting the given values, we get:

Surface area = 2*106 / 10,000

Surface area = 200 m2

Therefore, the surface area of the basin will be 200 m2.

Explanation

- Given data is the flow rate of water and the surface loading rate of the basin.
- We need to calculate the surface area of the basin that can handle this flow rate and surface loading rate.
- The formula for surface loading rate is Flow rate / Surface area.
- Using this formula, we can calculate the surface area of the basin required to handle the given flow rate and surface loading rate.
- Substituting the given values in the formula, we get the surface area of the basin as 200 m2.
- Therefore, the correct answer is option 'B'.
Explore Courses for Chemical Engineering exam

Similar Chemical Engineering Doubts

What will be the surface area of the basin for a flow of 2*106 litre per day having a surface loading rate 10,000 litre/day/m2?a)100b)200c)300d)400Correct answer is option 'B'. Can you explain this answer?
Question Description
What will be the surface area of the basin for a flow of 2*106 litre per day having a surface loading rate 10,000 litre/day/m2?a)100b)200c)300d)400Correct answer is option 'B'. Can you explain this answer? for Chemical Engineering 2024 is part of Chemical Engineering preparation. The Question and answers have been prepared according to the Chemical Engineering exam syllabus. Information about What will be the surface area of the basin for a flow of 2*106 litre per day having a surface loading rate 10,000 litre/day/m2?a)100b)200c)300d)400Correct answer is option 'B'. Can you explain this answer? covers all topics & solutions for Chemical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for What will be the surface area of the basin for a flow of 2*106 litre per day having a surface loading rate 10,000 litre/day/m2?a)100b)200c)300d)400Correct answer is option 'B'. Can you explain this answer?.
Solutions for What will be the surface area of the basin for a flow of 2*106 litre per day having a surface loading rate 10,000 litre/day/m2?a)100b)200c)300d)400Correct answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Chemical Engineering. Download more important topics, notes, lectures and mock test series for Chemical Engineering Exam by signing up for free.
Here you can find the meaning of What will be the surface area of the basin for a flow of 2*106 litre per day having a surface loading rate 10,000 litre/day/m2?a)100b)200c)300d)400Correct answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of What will be the surface area of the basin for a flow of 2*106 litre per day having a surface loading rate 10,000 litre/day/m2?a)100b)200c)300d)400Correct answer is option 'B'. Can you explain this answer?, a detailed solution for What will be the surface area of the basin for a flow of 2*106 litre per day having a surface loading rate 10,000 litre/day/m2?a)100b)200c)300d)400Correct answer is option 'B'. Can you explain this answer? has been provided alongside types of What will be the surface area of the basin for a flow of 2*106 litre per day having a surface loading rate 10,000 litre/day/m2?a)100b)200c)300d)400Correct answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice What will be the surface area of the basin for a flow of 2*106 litre per day having a surface loading rate 10,000 litre/day/m2?a)100b)200c)300d)400Correct answer is option 'B'. Can you explain this answer? tests, examples and also practice Chemical Engineering tests.
Explore Courses for Chemical Engineering exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev