The network of a small construction project awarded to a contractor is shown in the following figure. The normal duration, crash duration, normal cost, and crash cost of all the activities are shown in the table. The indirect cost incurred by the contractor is INR 5000 per day.
If the project is targeted for completion in 16 days, the total cost (in INR) to be incurred by the contractor would be _____
    Correct answer is '149500'. Can you explain this answer?
    Verified Answer
    The network of a small construction project awarded to a contractor is...

    Path PRTV is critical path and corres-ponding normal duration is 18 days.
    For 18 days:
    Direct cost = 66000
    Indirect cost = 18 × 5000 = 90000
    Total project cost = 156000
    1st stage crashing :
    Crash activity R by 1 day.
    New project duration = 17 days.
    T.P.C = 156000 + 1 × 750 – 1 × 5000 = 151750

    2nd stage crashing :
    Crash activity Q & R simultaneously by 1 day. New project duration = 16 days.
    T.P.C = 151750 + 1 × (750 + 2000) – 5000 = 149500
    View all questions of this test
    Explore Courses for Civil Engineering (CE) exam

    Similar Civil Engineering (CE) Doubts

    Top Courses for Civil Engineering (CE)

    The network of a small construction project awarded to a contractor is shown in the following figure. The normal duration, crash duration, normal cost, and crash cost of all the activities are shown in the table. The indirect cost incurred by the contractor is INR 5000 per day.If the project is targeted for completion in 16 days, the total cost (in INR) to be incurred by the contractor would be _____Correct answer is '149500'. Can you explain this answer?
    Question Description
    The network of a small construction project awarded to a contractor is shown in the following figure. The normal duration, crash duration, normal cost, and crash cost of all the activities are shown in the table. The indirect cost incurred by the contractor is INR 5000 per day.If the project is targeted for completion in 16 days, the total cost (in INR) to be incurred by the contractor would be _____Correct answer is '149500'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about The network of a small construction project awarded to a contractor is shown in the following figure. The normal duration, crash duration, normal cost, and crash cost of all the activities are shown in the table. The indirect cost incurred by the contractor is INR 5000 per day.If the project is targeted for completion in 16 days, the total cost (in INR) to be incurred by the contractor would be _____Correct answer is '149500'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The network of a small construction project awarded to a contractor is shown in the following figure. The normal duration, crash duration, normal cost, and crash cost of all the activities are shown in the table. The indirect cost incurred by the contractor is INR 5000 per day.If the project is targeted for completion in 16 days, the total cost (in INR) to be incurred by the contractor would be _____Correct answer is '149500'. Can you explain this answer?.
    Solutions for The network of a small construction project awarded to a contractor is shown in the following figure. The normal duration, crash duration, normal cost, and crash cost of all the activities are shown in the table. The indirect cost incurred by the contractor is INR 5000 per day.If the project is targeted for completion in 16 days, the total cost (in INR) to be incurred by the contractor would be _____Correct answer is '149500'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
    Here you can find the meaning of The network of a small construction project awarded to a contractor is shown in the following figure. The normal duration, crash duration, normal cost, and crash cost of all the activities are shown in the table. The indirect cost incurred by the contractor is INR 5000 per day.If the project is targeted for completion in 16 days, the total cost (in INR) to be incurred by the contractor would be _____Correct answer is '149500'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The network of a small construction project awarded to a contractor is shown in the following figure. The normal duration, crash duration, normal cost, and crash cost of all the activities are shown in the table. The indirect cost incurred by the contractor is INR 5000 per day.If the project is targeted for completion in 16 days, the total cost (in INR) to be incurred by the contractor would be _____Correct answer is '149500'. Can you explain this answer?, a detailed solution for The network of a small construction project awarded to a contractor is shown in the following figure. The normal duration, crash duration, normal cost, and crash cost of all the activities are shown in the table. The indirect cost incurred by the contractor is INR 5000 per day.If the project is targeted for completion in 16 days, the total cost (in INR) to be incurred by the contractor would be _____Correct answer is '149500'. Can you explain this answer? has been provided alongside types of The network of a small construction project awarded to a contractor is shown in the following figure. The normal duration, crash duration, normal cost, and crash cost of all the activities are shown in the table. The indirect cost incurred by the contractor is INR 5000 per day.If the project is targeted for completion in 16 days, the total cost (in INR) to be incurred by the contractor would be _____Correct answer is '149500'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The network of a small construction project awarded to a contractor is shown in the following figure. The normal duration, crash duration, normal cost, and crash cost of all the activities are shown in the table. The indirect cost incurred by the contractor is INR 5000 per day.If the project is targeted for completion in 16 days, the total cost (in INR) to be incurred by the contractor would be _____Correct answer is '149500'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
    Explore Courses for Civil Engineering (CE) exam

    Top Courses for Civil Engineering (CE)

    Explore Courses
    Signup for Free!
    Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
    10M+ students study on EduRev