Question Description
The network of a small construction project awarded to a contractor is shown in the following figure. The normal duration, crash duration, normal cost, and crash cost of all the activities are shown in the table. The indirect cost incurred by the contractor is INR 5000 per day.If the project is targeted for completion in 16 days, the total cost (in INR) to be incurred by the contractor would be _____Correct answer is '149500'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared
according to
the Civil Engineering (CE) exam syllabus. Information about The network of a small construction project awarded to a contractor is shown in the following figure. The normal duration, crash duration, normal cost, and crash cost of all the activities are shown in the table. The indirect cost incurred by the contractor is INR 5000 per day.If the project is targeted for completion in 16 days, the total cost (in INR) to be incurred by the contractor would be _____Correct answer is '149500'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for The network of a small construction project awarded to a contractor is shown in the following figure. The normal duration, crash duration, normal cost, and crash cost of all the activities are shown in the table. The indirect cost incurred by the contractor is INR 5000 per day.If the project is targeted for completion in 16 days, the total cost (in INR) to be incurred by the contractor would be _____Correct answer is '149500'. Can you explain this answer?.
Solutions for The network of a small construction project awarded to a contractor is shown in the following figure. The normal duration, crash duration, normal cost, and crash cost of all the activities are shown in the table. The indirect cost incurred by the contractor is INR 5000 per day.If the project is targeted for completion in 16 days, the total cost (in INR) to be incurred by the contractor would be _____Correct answer is '149500'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE).
Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of The network of a small construction project awarded to a contractor is shown in the following figure. The normal duration, crash duration, normal cost, and crash cost of all the activities are shown in the table. The indirect cost incurred by the contractor is INR 5000 per day.If the project is targeted for completion in 16 days, the total cost (in INR) to be incurred by the contractor would be _____Correct answer is '149500'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of
The network of a small construction project awarded to a contractor is shown in the following figure. The normal duration, crash duration, normal cost, and crash cost of all the activities are shown in the table. The indirect cost incurred by the contractor is INR 5000 per day.If the project is targeted for completion in 16 days, the total cost (in INR) to be incurred by the contractor would be _____Correct answer is '149500'. Can you explain this answer?, a detailed solution for The network of a small construction project awarded to a contractor is shown in the following figure. The normal duration, crash duration, normal cost, and crash cost of all the activities are shown in the table. The indirect cost incurred by the contractor is INR 5000 per day.If the project is targeted for completion in 16 days, the total cost (in INR) to be incurred by the contractor would be _____Correct answer is '149500'. Can you explain this answer? has been provided alongside types of The network of a small construction project awarded to a contractor is shown in the following figure. The normal duration, crash duration, normal cost, and crash cost of all the activities are shown in the table. The indirect cost incurred by the contractor is INR 5000 per day.If the project is targeted for completion in 16 days, the total cost (in INR) to be incurred by the contractor would be _____Correct answer is '149500'. Can you explain this answer? theory, EduRev gives you an
ample number of questions to practice The network of a small construction project awarded to a contractor is shown in the following figure. The normal duration, crash duration, normal cost, and crash cost of all the activities are shown in the table. The indirect cost incurred by the contractor is INR 5000 per day.If the project is targeted for completion in 16 days, the total cost (in INR) to be incurred by the contractor would be _____Correct answer is '149500'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.