Question Description
A contract is to be completed in 56 days if 104 persons work, each working at 8 hours a day. After30 days, 2/5 of the work is completed. How many additional persons should be deployed so that thework will be completed in the scheduled time, each person’s now working 9 hours a day.a)160b)150c)24d)56Correct answer is option 'D'. Can you explain this answer? for UPSC 2024 is part of UPSC preparation. The Question and answers have been prepared
according to
the UPSC exam syllabus. Information about A contract is to be completed in 56 days if 104 persons work, each working at 8 hours a day. After30 days, 2/5 of the work is completed. How many additional persons should be deployed so that thework will be completed in the scheduled time, each person’s now working 9 hours a day.a)160b)150c)24d)56Correct answer is option 'D'. Can you explain this answer? covers all topics & solutions for UPSC 2024 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for A contract is to be completed in 56 days if 104 persons work, each working at 8 hours a day. After30 days, 2/5 of the work is completed. How many additional persons should be deployed so that thework will be completed in the scheduled time, each person’s now working 9 hours a day.a)160b)150c)24d)56Correct answer is option 'D'. Can you explain this answer?.
Solutions for A contract is to be completed in 56 days if 104 persons work, each working at 8 hours a day. After30 days, 2/5 of the work is completed. How many additional persons should be deployed so that thework will be completed in the scheduled time, each person’s now working 9 hours a day.a)160b)150c)24d)56Correct answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for UPSC.
Download more important topics, notes, lectures and mock test series for UPSC Exam by signing up for free.
Here you can find the meaning of A contract is to be completed in 56 days if 104 persons work, each working at 8 hours a day. After30 days, 2/5 of the work is completed. How many additional persons should be deployed so that thework will be completed in the scheduled time, each person’s now working 9 hours a day.a)160b)150c)24d)56Correct answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of
A contract is to be completed in 56 days if 104 persons work, each working at 8 hours a day. After30 days, 2/5 of the work is completed. How many additional persons should be deployed so that thework will be completed in the scheduled time, each person’s now working 9 hours a day.a)160b)150c)24d)56Correct answer is option 'D'. Can you explain this answer?, a detailed solution for A contract is to be completed in 56 days if 104 persons work, each working at 8 hours a day. After30 days, 2/5 of the work is completed. How many additional persons should be deployed so that thework will be completed in the scheduled time, each person’s now working 9 hours a day.a)160b)150c)24d)56Correct answer is option 'D'. Can you explain this answer? has been provided alongside types of A contract is to be completed in 56 days if 104 persons work, each working at 8 hours a day. After30 days, 2/5 of the work is completed. How many additional persons should be deployed so that thework will be completed in the scheduled time, each person’s now working 9 hours a day.a)160b)150c)24d)56Correct answer is option 'D'. Can you explain this answer? theory, EduRev gives you an
ample number of questions to practice A contract is to be completed in 56 days if 104 persons work, each working at 8 hours a day. After30 days, 2/5 of the work is completed. How many additional persons should be deployed so that thework will be completed in the scheduled time, each person’s now working 9 hours a day.a)160b)150c)24d)56Correct answer is option 'D'. Can you explain this answer? tests, examples and also practice UPSC tests.