Question Description
100 men were to complete a piece of work in 20 days. After they worked for 10 days, 60 more men were employed to complete the work on time. If additional men were not employed, then how many days behind schedule the work would be finished?a)12b)8c)10d)6e)None of theseCorrect answer is option 'D'. Can you explain this answer? for Quant 2024 is part of Quant preparation. The Question and answers have been prepared
according to
the Quant exam syllabus. Information about 100 men were to complete a piece of work in 20 days. After they worked for 10 days, 60 more men were employed to complete the work on time. If additional men were not employed, then how many days behind schedule the work would be finished?a)12b)8c)10d)6e)None of theseCorrect answer is option 'D'. Can you explain this answer? covers all topics & solutions for Quant 2024 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for 100 men were to complete a piece of work in 20 days. After they worked for 10 days, 60 more men were employed to complete the work on time. If additional men were not employed, then how many days behind schedule the work would be finished?a)12b)8c)10d)6e)None of theseCorrect answer is option 'D'. Can you explain this answer?.
Solutions for 100 men were to complete a piece of work in 20 days. After they worked for 10 days, 60 more men were employed to complete the work on time. If additional men were not employed, then how many days behind schedule the work would be finished?a)12b)8c)10d)6e)None of theseCorrect answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Quant.
Download more important topics, notes, lectures and mock test series for Quant Exam by signing up for free.
Here you can find the meaning of 100 men were to complete a piece of work in 20 days. After they worked for 10 days, 60 more men were employed to complete the work on time. If additional men were not employed, then how many days behind schedule the work would be finished?a)12b)8c)10d)6e)None of theseCorrect answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of
100 men were to complete a piece of work in 20 days. After they worked for 10 days, 60 more men were employed to complete the work on time. If additional men were not employed, then how many days behind schedule the work would be finished?a)12b)8c)10d)6e)None of theseCorrect answer is option 'D'. Can you explain this answer?, a detailed solution for 100 men were to complete a piece of work in 20 days. After they worked for 10 days, 60 more men were employed to complete the work on time. If additional men were not employed, then how many days behind schedule the work would be finished?a)12b)8c)10d)6e)None of theseCorrect answer is option 'D'. Can you explain this answer? has been provided alongside types of 100 men were to complete a piece of work in 20 days. After they worked for 10 days, 60 more men were employed to complete the work on time. If additional men were not employed, then how many days behind schedule the work would be finished?a)12b)8c)10d)6e)None of theseCorrect answer is option 'D'. Can you explain this answer? theory, EduRev gives you an
ample number of questions to practice 100 men were to complete a piece of work in 20 days. After they worked for 10 days, 60 more men were employed to complete the work on time. If additional men were not employed, then how many days behind schedule the work would be finished?a)12b)8c)10d)6e)None of theseCorrect answer is option 'D'. Can you explain this answer? tests, examples and also practice Quant tests.