100 men were to complete a piece of work in 20 days. After they worked for 10 days, 60 more men were employed to complete the work on time. If additional men were not employed, then how many days behind schedule the work would be finished?
  • a)
    12
  • b)
    8
  • c)
    10
  • d)
    6
  • e)
    None of these
Correct answer is option 'D'. Can you explain this answer?
Verified Answer
100 men were to complete a piece of work in 20 days. After they worked...
D) 6
Explanation: Let 100 men complete x work in 10 days after which (100+60) = 160 men complete the remaining (1-x) work in remaining 10 days [Total work to be completed in 20 days] So, M1*D1*W2 = M2*D2*W1 100*10*(1-x) = 160*10*x Solve, x= 5/13 This means that initially employed 100 men can finish 5/13th of work in 10 days, so let they will complete 1 whole work in x days.
M1*D1*W2 = M2*D2*W1
100*10*1 = 100*x*(5/13) Solve, x = 26 This means extra (26-20) = 6 days will be required if additional men are not employed after 10 days.
View all questions of this test
Most Upvoted Answer
100 men were to complete a piece of work in 20 days. After they worked...
Given:
100 men complete a piece of work in 20 days
Work started with 100 men and after 10 days 60 more men were employed

To find:
How many days behind schedule the work would be finished if additional men were not employed

Solution:
Let's assume the total work is equal to 100 units (this is just an assumption for ease of calculation)

Total work = 100 units
100 men complete 100 units of work in 20 days
So, 1 man will complete 1 unit of work in 20 * 100 = 2000 days
100 men will complete 100 units of work in 2000/100 = 20 days

Now, after 10 days, 100 men have completed 10 * 100 = 1000 units of work
Remaining work = 100 - 1000 = -900 units (negative value indicates that the work is already completed)

So, to complete the work on time, 60 more men were employed
Total men now = 100 + 60 = 160
Work remaining = -900 units (as previously calculated)

Now, 160 men will complete 900 units of work in 900/(160*10) = 0.5625 days
So, the work will be completed in a total of 10 + 0.5625 = 10.5625 days

If additional men were not employed, then the work would have been completed in 20 - 10 = 10 days
So, the work will be finished behind schedule by 10.5625 - 10 = 0.5625 days = 6/11 days ≈ 0.5 days

Therefore, the correct option is (D) 6 days.
Free Test
Community Answer
100 men were to complete a piece of work in 20 days. After they worked...
D) 6
Explanation: Let 100 men complete x work in 10 days after which (100+60) = 160 men complete the remaining (1-x) work in remaining 10 days [Total work to be completed in 20 days] So, M1*D1*W2 = M2*D2*W1 100*10*(1-x) = 160*10*x Solve, x= 5/13 This means that initially employed 100 men can finish 5/13th of work in 10 days, so let they will complete 1 whole work in x days.
M1*D1*W2 = M2*D2*W1
100*10*1 = 100*x*(5/13) Solve, x = 26 This means extra (26-20) = 6 days will be required if additional men are not employed after 10 days.
Explore Courses for Quant exam
100 men were to complete a piece of work in 20 days. After they worked for 10 days, 60 more men were employed to complete the work on time. If additional men were not employed, then how many days behind schedule the work would be finished?a)12b)8c)10d)6e)None of theseCorrect answer is option 'D'. Can you explain this answer?
Question Description
100 men were to complete a piece of work in 20 days. After they worked for 10 days, 60 more men were employed to complete the work on time. If additional men were not employed, then how many days behind schedule the work would be finished?a)12b)8c)10d)6e)None of theseCorrect answer is option 'D'. Can you explain this answer? for Quant 2024 is part of Quant preparation. The Question and answers have been prepared according to the Quant exam syllabus. Information about 100 men were to complete a piece of work in 20 days. After they worked for 10 days, 60 more men were employed to complete the work on time. If additional men were not employed, then how many days behind schedule the work would be finished?a)12b)8c)10d)6e)None of theseCorrect answer is option 'D'. Can you explain this answer? covers all topics & solutions for Quant 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for 100 men were to complete a piece of work in 20 days. After they worked for 10 days, 60 more men were employed to complete the work on time. If additional men were not employed, then how many days behind schedule the work would be finished?a)12b)8c)10d)6e)None of theseCorrect answer is option 'D'. Can you explain this answer?.
Solutions for 100 men were to complete a piece of work in 20 days. After they worked for 10 days, 60 more men were employed to complete the work on time. If additional men were not employed, then how many days behind schedule the work would be finished?a)12b)8c)10d)6e)None of theseCorrect answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Quant. Download more important topics, notes, lectures and mock test series for Quant Exam by signing up for free.
Here you can find the meaning of 100 men were to complete a piece of work in 20 days. After they worked for 10 days, 60 more men were employed to complete the work on time. If additional men were not employed, then how many days behind schedule the work would be finished?a)12b)8c)10d)6e)None of theseCorrect answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of 100 men were to complete a piece of work in 20 days. After they worked for 10 days, 60 more men were employed to complete the work on time. If additional men were not employed, then how many days behind schedule the work would be finished?a)12b)8c)10d)6e)None of theseCorrect answer is option 'D'. Can you explain this answer?, a detailed solution for 100 men were to complete a piece of work in 20 days. After they worked for 10 days, 60 more men were employed to complete the work on time. If additional men were not employed, then how many days behind schedule the work would be finished?a)12b)8c)10d)6e)None of theseCorrect answer is option 'D'. Can you explain this answer? has been provided alongside types of 100 men were to complete a piece of work in 20 days. After they worked for 10 days, 60 more men were employed to complete the work on time. If additional men were not employed, then how many days behind schedule the work would be finished?a)12b)8c)10d)6e)None of theseCorrect answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice 100 men were to complete a piece of work in 20 days. After they worked for 10 days, 60 more men were employed to complete the work on time. If additional men were not employed, then how many days behind schedule the work would be finished?a)12b)8c)10d)6e)None of theseCorrect answer is option 'D'. Can you explain this answer? tests, examples and also practice Quant tests.
Explore Courses for Quant exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev