Quant Exam  >  Quant Questions  >  P takes 6 days less than Q to finish the work... Start Learning for Free
P takes 6 days less than Q to finish the work individually. If P and Q working together complete the work in 4 days, then how many days are required by Q to complete the work alone ?
  • a)
    7 days
  • b)
    10 days
  • c)
    5 days
  • d)
    12 days
  • e)
    None of these
Correct answer is option 'D'. Can you explain this answer?
Verified Answer
P takes 6 days less than Q to finish the work individually. If P and Q...
= 1/6 + 1/12
= 2+1/12 =3/12 = 1/4
View all questions of this test
Most Upvoted Answer
P takes 6 days less than Q to finish the work individually. If P and Q...
A takes 6 days less than B to do a work. If both A and B working together can do it in 4 days, how many days will B take to finish it?

Let the time taken by B to complete the work be x days.

in these type of questions , we should convert the work done into 1 day.

So , According to the question

1/x + 1/x-6 = 1/4

=> x-6+x / x(x-6) = 1/4

=> 2x-6 / x^2-6x = 1/4

=> 8x-24 = x^2-6x

=> x^2-14x+24 = 0

=> (x^2-12x)+(-2x+24) = 0

=> (x-12) (x-2) = 0

=> x = 12 , 2

if the time taken by B to complete the work is 2 days then the time taken by A to complete the work will be -4 days which is not possible.

=> time taken by B to complete the work is 12 days
Free Test
Community Answer
P takes 6 days less than Q to finish the work individually. If P and Q...
Let's assume that Q takes x days to complete the work alone.

Given that P takes 6 days less than Q to finish the work individually, we can say that P takes (x - 6) days to complete the work alone.

Now, let's calculate the individual work rates of P and Q.

The work rate of P is 1/(x - 6) (since P completes the work in (x - 6) days) and the work rate of Q is 1/x (since Q completes the work in x days).

When P and Q work together, their work rates are additive.

So, the work rate when P and Q work together is (1/(x - 6)) + (1/x) = 1/4 (since they complete the work in 4 days when working together).

To solve this equation, we can find a common denominator by multiplying both sides by (x(x - 6)).

(x(x - 6))/(x - 6) + (x(x - 6))/x = (x(x - 6))/4

Simplifying this equation, we get:

x + (x - 6) = (x(x - 6))/4

2x - 6 = (x^2 - 6x)/4

Multiplying both sides by 4 to eliminate the denominator, we get:

8x - 24 = x^2 - 6x

Rearranging this equation, we get:

x^2 - 14x + 24 = 0

This is a quadratic equation. We can either factorize it or use the quadratic formula to find the values of x.

By solving this equation, we find that the values of x are 12 and 2.

Since Q cannot take 2 days (as P takes 6 days less than Q), the value of x is 12.

Therefore, Q takes 12 days to complete the work alone.

Hence, the correct answer is option D) 12 days.
Explore Courses for Quant exam

Similar Quant Doubts

P takes 6 days less than Q to finish the work individually. If P and Q working together complete the work in 4 days, then how many days are required by Q to complete the work alone ?a)7 daysb)10 daysc)5 daysd)12 dayse)None of theseCorrect answer is option 'D'. Can you explain this answer?
Question Description
P takes 6 days less than Q to finish the work individually. If P and Q working together complete the work in 4 days, then how many days are required by Q to complete the work alone ?a)7 daysb)10 daysc)5 daysd)12 dayse)None of theseCorrect answer is option 'D'. Can you explain this answer? for Quant 2024 is part of Quant preparation. The Question and answers have been prepared according to the Quant exam syllabus. Information about P takes 6 days less than Q to finish the work individually. If P and Q working together complete the work in 4 days, then how many days are required by Q to complete the work alone ?a)7 daysb)10 daysc)5 daysd)12 dayse)None of theseCorrect answer is option 'D'. Can you explain this answer? covers all topics & solutions for Quant 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for P takes 6 days less than Q to finish the work individually. If P and Q working together complete the work in 4 days, then how many days are required by Q to complete the work alone ?a)7 daysb)10 daysc)5 daysd)12 dayse)None of theseCorrect answer is option 'D'. Can you explain this answer?.
Solutions for P takes 6 days less than Q to finish the work individually. If P and Q working together complete the work in 4 days, then how many days are required by Q to complete the work alone ?a)7 daysb)10 daysc)5 daysd)12 dayse)None of theseCorrect answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Quant. Download more important topics, notes, lectures and mock test series for Quant Exam by signing up for free.
Here you can find the meaning of P takes 6 days less than Q to finish the work individually. If P and Q working together complete the work in 4 days, then how many days are required by Q to complete the work alone ?a)7 daysb)10 daysc)5 daysd)12 dayse)None of theseCorrect answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of P takes 6 days less than Q to finish the work individually. If P and Q working together complete the work in 4 days, then how many days are required by Q to complete the work alone ?a)7 daysb)10 daysc)5 daysd)12 dayse)None of theseCorrect answer is option 'D'. Can you explain this answer?, a detailed solution for P takes 6 days less than Q to finish the work individually. If P and Q working together complete the work in 4 days, then how many days are required by Q to complete the work alone ?a)7 daysb)10 daysc)5 daysd)12 dayse)None of theseCorrect answer is option 'D'. Can you explain this answer? has been provided alongside types of P takes 6 days less than Q to finish the work individually. If P and Q working together complete the work in 4 days, then how many days are required by Q to complete the work alone ?a)7 daysb)10 daysc)5 daysd)12 dayse)None of theseCorrect answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice P takes 6 days less than Q to finish the work individually. If P and Q working together complete the work in 4 days, then how many days are required by Q to complete the work alone ?a)7 daysb)10 daysc)5 daysd)12 dayse)None of theseCorrect answer is option 'D'. Can you explain this answer? tests, examples and also practice Quant tests.
Explore Courses for Quant exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev