Quant Exam  >  Quant Questions  >  A, B and C can alone complete a work in 10, 1... Start Learning for Free
A, B and C can alone complete a work in 10, 12 and 15 days respectively. All started the work but B left the work 3 days before completion. How much work was then done by A and B together in the total work?
  • a)
    2/3
  • b)
    3/4
  • c)
    1/3
  • d)
    3/5
  • e)
    2/5
Correct answer is option 'A'. Can you explain this answer?
Verified Answer
A, B and C can alone complete a work in 10, 12 and 15 days respectivel...
Let work completed in x days, so A and C worked for all x days, and B for (x-3) days.
So
(1/10 + 1/15)*x + (1/12)*(x-3) = 1
Solve, x = 5 days
In 5 days, A did 5/10 = 1/2 of work
In (5-3) = 2 days, B did 2/12 = 1/6 of work
So total by A and B = (1/2 + 1/6) = 2/3
View all questions of this test
Most Upvoted Answer
A, B and C can alone complete a work in 10, 12 and 15 days respectivel...
Given information:
A can complete the work in 10 days.
B can complete the work in 12 days.
C can complete the work in 15 days.
B left the work 3 days before completion.

To find:
How much work was then done by A and B together in the total work?

Solution:
To solve this problem, we need to understand the concept of work done per day.

Let's assume that the total work to be done is 60 units (considering the LCM of 10, 12, and 15).

Work done by A per day:
A can complete the work in 10 days, so the work done by A per day is 60/10 = 6 units.

Work done by B per day:
B can complete the work in 12 days, so the work done by B per day is 60/12 = 5 units.

Work done by C per day:
C can complete the work in 15 days, so the work done by C per day is 60/15 = 4 units.

Now, let's calculate the total work done by A, B, and C in the given time frame.

Work done by A in the given time:
Since A is working continuously until the completion of the work, the work done by A in the given time is 6 units/day * (10-3) days = 6 * 7 = 42 units.

Work done by B in the given time:
B left the work 3 days before completion, so the work done by B in the given time is 5 units/day * 3 days = 15 units.

Total work done by A and B together:
The total work done by A and B together in the given time is 42 units + 15 units = 57 units.

Calculating the fraction of work done:
To find the fraction of work done by A and B together, we need to divide the total work done by A and B by the total work done.

Fraction of work done by A and B = (57 units) / (60 units) = 19/20 = 0.95

This can be simplified to 2/3.

Therefore, the answer is option 'A' (2/3).
Free Test
Community Answer
A, B and C can alone complete a work in 10, 12 and 15 days respectivel...
Let work completed in x days, so A and C worked for all x days, and B for (x-3) days.
So
(1/10 + 1/15)*x + (1/12)*(x-3) = 1
Solve, x = 5 days
In 5 days, A did 5/10 = 1/2 of work
In (5-3) = 2 days, B did 2/12 = 1/6 of work
So total by A and B = (1/2 + 1/6) = 2/3
Explore Courses for Quant exam
A, B and C can alone complete a work in 10, 12 and 15 days respectively. All started the work but B left the work 3 days before completion. How much work was then done by A and B together in the total work?a)2/3b)3/4c)1/3d)3/5e)2/5Correct answer is option 'A'. Can you explain this answer?
Question Description
A, B and C can alone complete a work in 10, 12 and 15 days respectively. All started the work but B left the work 3 days before completion. How much work was then done by A and B together in the total work?a)2/3b)3/4c)1/3d)3/5e)2/5Correct answer is option 'A'. Can you explain this answer? for Quant 2024 is part of Quant preparation. The Question and answers have been prepared according to the Quant exam syllabus. Information about A, B and C can alone complete a work in 10, 12 and 15 days respectively. All started the work but B left the work 3 days before completion. How much work was then done by A and B together in the total work?a)2/3b)3/4c)1/3d)3/5e)2/5Correct answer is option 'A'. Can you explain this answer? covers all topics & solutions for Quant 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A, B and C can alone complete a work in 10, 12 and 15 days respectively. All started the work but B left the work 3 days before completion. How much work was then done by A and B together in the total work?a)2/3b)3/4c)1/3d)3/5e)2/5Correct answer is option 'A'. Can you explain this answer?.
Solutions for A, B and C can alone complete a work in 10, 12 and 15 days respectively. All started the work but B left the work 3 days before completion. How much work was then done by A and B together in the total work?a)2/3b)3/4c)1/3d)3/5e)2/5Correct answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for Quant. Download more important topics, notes, lectures and mock test series for Quant Exam by signing up for free.
Here you can find the meaning of A, B and C can alone complete a work in 10, 12 and 15 days respectively. All started the work but B left the work 3 days before completion. How much work was then done by A and B together in the total work?a)2/3b)3/4c)1/3d)3/5e)2/5Correct answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A, B and C can alone complete a work in 10, 12 and 15 days respectively. All started the work but B left the work 3 days before completion. How much work was then done by A and B together in the total work?a)2/3b)3/4c)1/3d)3/5e)2/5Correct answer is option 'A'. Can you explain this answer?, a detailed solution for A, B and C can alone complete a work in 10, 12 and 15 days respectively. All started the work but B left the work 3 days before completion. How much work was then done by A and B together in the total work?a)2/3b)3/4c)1/3d)3/5e)2/5Correct answer is option 'A'. Can you explain this answer? has been provided alongside types of A, B and C can alone complete a work in 10, 12 and 15 days respectively. All started the work but B left the work 3 days before completion. How much work was then done by A and B together in the total work?a)2/3b)3/4c)1/3d)3/5e)2/5Correct answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A, B and C can alone complete a work in 10, 12 and 15 days respectively. All started the work but B left the work 3 days before completion. How much work was then done by A and B together in the total work?a)2/3b)3/4c)1/3d)3/5e)2/5Correct answer is option 'A'. Can you explain this answer? tests, examples and also practice Quant tests.
Explore Courses for Quant exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev