The ratio of efficiency of Arun is to Chitra is 5:3. The ratio of numb...
Ratio of number of days = 9:10:15
Work done By B and C in first two days = 2*1/6 = 1/3
Rest of the work = 2/3
Number of days = (2/3)/(1/9) = 6 days
View all questions of this test
The ratio of efficiency of Arun is to Chitra is 5:3. The ratio of numb...
Ratio of number of days = 9:10:15
Work done By B and C in first two days = 2*1/6 = 1/3
Rest of the work = 2/3
Number of days = (2/3)/(1/9) = 6 days
The ratio of efficiency of Arun is to Chitra is 5:3. The ratio of numb...
Given Information:
- The ratio of efficiency of Arun to Chitra is 5:3.
- The ratio of the number of days taken by Bala to Chitra is 2:3.
- Arun takes 6 days less than Chitra to complete the work individually.
- Bala and Chitra started the work and left after 2 days.
To Find:
The number of days taken by Arun to finish the remaining work.
Solution:
Let's assume that Chitra takes 'x' days to complete the entire work individually.
Therefore, Arun takes 'x - 6' days to complete the entire work individually.
Efficiency:
The ratio of efficiency of Arun to Chitra is 5:3.
Therefore, the efficiency ratio of Arun to Chitra is (5/3).
Work Done:
Since efficiency is directly proportional to work done, the work done ratio of Arun to Chitra is also (5/3).
So, the work done ratio of Arun to Chitra is (5/3).
Work done in 2 days:
Bala and Chitra started the work and left after 2 days.
Let's assume the total work to be 'W'.
Therefore, the work done by Bala and Chitra in 2 days is (2/5)W and (2/3)W respectively.
Remaining work:
The remaining work after 2 days is the difference between the total work and the work done in 2 days.
Therefore, the remaining work is:
W - [(2/5)W + (2/3)W] = W - (6/15)W = (9/15)W = (3/5)W
Time taken by Arun:
The remaining work is (3/5)W.
Arun takes 'x - 6' days to complete the entire work individually.
So, the number of days taken by Arun to finish the remaining work is:
[(3/5)W] / [(x - 6)/x] = [(3/5)W] * [x / (x - 6)] = (3/5) * W * (x / (x - 6))
Substituting the value of x:
From the given information, we know that Arun takes 6 days less than Chitra to complete the work individually.
So, x - (x - 6) = 6
Simplifying, we get:
x - x + 6 = 6
6 = 6
Therefore, we can substitute the value of x as 6 in the equation:
(3/5) * W * (x / (x - 6)) = (3/5) * W * (6 / (6 - 6)) = (3/5) * W * (6 / 0) = undefined
Conclusion:
The number of days taken by Arun to finish the remaining work is undefined.