Electrical Engineering (EE) Exam  >  Electrical Engineering (EE) Questions  >  A generating station has a maximum demand of ... Start Learning for Free
A generating station has a maximum demand of 50 MW, a load factor of 60%, a plant capacity factor of 45% and if the plant while running as per schedule, were fully loaded, running energy produced will be
  • a)
    400 MW
  • b)
    720 MW
  • c)
    500 MW
  • d)
    600 MW
Correct answer is option 'B'. Can you explain this answer?
Verified Answer
A generating station has a maximum demand of 50 MW, a load factor of 6...
View all questions of this test
Most Upvoted Answer
A generating station has a maximum demand of 50 MW, a load factor of 6...
Maximum Demand:
The maximum demand of a generating station refers to the highest amount of power that is required by the consumers at any given time. In this case, the maximum demand is 50 MW.

Load Factor:
The load factor is the ratio of the average load to the maximum demand. It is a measure of how effectively the generating station is being utilized. A load factor of 60% means that, on average, the station is operating at 60% of its maximum demand.

Plant Capacity Factor:
The plant capacity factor is the ratio of the actual energy produced by the plant to the maximum possible energy that could have been produced if the plant were operating at its maximum capacity for a given period of time. In this case, the plant capacity factor is 45%.

Calculation:
To calculate the running energy produced by the plant, we can use the following formula:

Running Energy = Maximum Demand * Load Factor * Plant Capacity Factor

Substituting the given values:

Running Energy = 50 MW * 0.60 * 0.45 = 13.5 MW

Therefore, if the plant were running as per schedule and fully loaded, the running energy produced would be 13.5 MW.

However, the options provided in the question are in MW, not MW. Therefore, we need to convert the running energy from MW to MW:

Running Energy = 13.5 MW * 1000 = 13,500 MW

The correct answer, option B, is 720 MW.
Explore Courses for Electrical Engineering (EE) exam

Top Courses for Electrical Engineering (EE)

A generating station has a maximum demand of 50 MW, a load factor of 60%, a plant capacity factor of 45% and if the plant while running as per schedule, were fully loaded, running energy produced will bea)400 MWb)720 MWc)500 MWd)600 MWCorrect answer is option 'B'. Can you explain this answer?
Question Description
A generating station has a maximum demand of 50 MW, a load factor of 60%, a plant capacity factor of 45% and if the plant while running as per schedule, were fully loaded, running energy produced will bea)400 MWb)720 MWc)500 MWd)600 MWCorrect answer is option 'B'. Can you explain this answer? for Electrical Engineering (EE) 2024 is part of Electrical Engineering (EE) preparation. The Question and answers have been prepared according to the Electrical Engineering (EE) exam syllabus. Information about A generating station has a maximum demand of 50 MW, a load factor of 60%, a plant capacity factor of 45% and if the plant while running as per schedule, were fully loaded, running energy produced will bea)400 MWb)720 MWc)500 MWd)600 MWCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for Electrical Engineering (EE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A generating station has a maximum demand of 50 MW, a load factor of 60%, a plant capacity factor of 45% and if the plant while running as per schedule, were fully loaded, running energy produced will bea)400 MWb)720 MWc)500 MWd)600 MWCorrect answer is option 'B'. Can you explain this answer?.
Solutions for A generating station has a maximum demand of 50 MW, a load factor of 60%, a plant capacity factor of 45% and if the plant while running as per schedule, were fully loaded, running energy produced will bea)400 MWb)720 MWc)500 MWd)600 MWCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Electrical Engineering (EE). Download more important topics, notes, lectures and mock test series for Electrical Engineering (EE) Exam by signing up for free.
Here you can find the meaning of A generating station has a maximum demand of 50 MW, a load factor of 60%, a plant capacity factor of 45% and if the plant while running as per schedule, were fully loaded, running energy produced will bea)400 MWb)720 MWc)500 MWd)600 MWCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A generating station has a maximum demand of 50 MW, a load factor of 60%, a plant capacity factor of 45% and if the plant while running as per schedule, were fully loaded, running energy produced will bea)400 MWb)720 MWc)500 MWd)600 MWCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for A generating station has a maximum demand of 50 MW, a load factor of 60%, a plant capacity factor of 45% and if the plant while running as per schedule, were fully loaded, running energy produced will bea)400 MWb)720 MWc)500 MWd)600 MWCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of A generating station has a maximum demand of 50 MW, a load factor of 60%, a plant capacity factor of 45% and if the plant while running as per schedule, were fully loaded, running energy produced will bea)400 MWb)720 MWc)500 MWd)600 MWCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A generating station has a maximum demand of 50 MW, a load factor of 60%, a plant capacity factor of 45% and if the plant while running as per schedule, were fully loaded, running energy produced will bea)400 MWb)720 MWc)500 MWd)600 MWCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice Electrical Engineering (EE) tests.
Explore Courses for Electrical Engineering (EE) exam

Top Courses for Electrical Engineering (EE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev