Question Description
A generating station has a maximum demand of 50 MW, a load factor of 60%, a plant capacity factor of 45% and if the plant while running as per schedule, were fully loaded, running energy produced will bea)400 MWb)720 MWc)500 MWd)600 MWCorrect answer is option 'B'. Can you explain this answer? for Electrical Engineering (EE) 2024 is part of Electrical Engineering (EE) preparation. The Question and answers have been prepared
according to
the Electrical Engineering (EE) exam syllabus. Information about A generating station has a maximum demand of 50 MW, a load factor of 60%, a plant capacity factor of 45% and if the plant while running as per schedule, were fully loaded, running energy produced will bea)400 MWb)720 MWc)500 MWd)600 MWCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for Electrical Engineering (EE) 2024 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for A generating station has a maximum demand of 50 MW, a load factor of 60%, a plant capacity factor of 45% and if the plant while running as per schedule, were fully loaded, running energy produced will bea)400 MWb)720 MWc)500 MWd)600 MWCorrect answer is option 'B'. Can you explain this answer?.
Solutions for A generating station has a maximum demand of 50 MW, a load factor of 60%, a plant capacity factor of 45% and if the plant while running as per schedule, were fully loaded, running energy produced will bea)400 MWb)720 MWc)500 MWd)600 MWCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Electrical Engineering (EE).
Download more important topics, notes, lectures and mock test series for Electrical Engineering (EE) Exam by signing up for free.
Here you can find the meaning of A generating station has a maximum demand of 50 MW, a load factor of 60%, a plant capacity factor of 45% and if the plant while running as per schedule, were fully loaded, running energy produced will bea)400 MWb)720 MWc)500 MWd)600 MWCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of
A generating station has a maximum demand of 50 MW, a load factor of 60%, a plant capacity factor of 45% and if the plant while running as per schedule, were fully loaded, running energy produced will bea)400 MWb)720 MWc)500 MWd)600 MWCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for A generating station has a maximum demand of 50 MW, a load factor of 60%, a plant capacity factor of 45% and if the plant while running as per schedule, were fully loaded, running energy produced will bea)400 MWb)720 MWc)500 MWd)600 MWCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of A generating station has a maximum demand of 50 MW, a load factor of 60%, a plant capacity factor of 45% and if the plant while running as per schedule, were fully loaded, running energy produced will bea)400 MWb)720 MWc)500 MWd)600 MWCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an
ample number of questions to practice A generating station has a maximum demand of 50 MW, a load factor of 60%, a plant capacity factor of 45% and if the plant while running as per schedule, were fully loaded, running energy produced will bea)400 MWb)720 MWc)500 MWd)600 MWCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice Electrical Engineering (EE) tests.