Question Description
A and B start working on a project. After 10 days B is replaced by C who can complete the project alone in 20 days. If A and B together can complete the project in 30 days, then find the day on which the project will be completed after C replaces B, if the efficiency of B is twice that of A.a)15th dayb)11th dayc)9th dayd)7th dayCorrect answer is option 'B'. Can you explain this answer? for CAT 2024 is part of CAT preparation. The Question and answers have been prepared
according to
the CAT exam syllabus. Information about A and B start working on a project. After 10 days B is replaced by C who can complete the project alone in 20 days. If A and B together can complete the project in 30 days, then find the day on which the project will be completed after C replaces B, if the efficiency of B is twice that of A.a)15th dayb)11th dayc)9th dayd)7th dayCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for CAT 2024 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for A and B start working on a project. After 10 days B is replaced by C who can complete the project alone in 20 days. If A and B together can complete the project in 30 days, then find the day on which the project will be completed after C replaces B, if the efficiency of B is twice that of A.a)15th dayb)11th dayc)9th dayd)7th dayCorrect answer is option 'B'. Can you explain this answer?.
Solutions for A and B start working on a project. After 10 days B is replaced by C who can complete the project alone in 20 days. If A and B together can complete the project in 30 days, then find the day on which the project will be completed after C replaces B, if the efficiency of B is twice that of A.a)15th dayb)11th dayc)9th dayd)7th dayCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for CAT.
Download more important topics, notes, lectures and mock test series for CAT Exam by signing up for free.
Here you can find the meaning of A and B start working on a project. After 10 days B is replaced by C who can complete the project alone in 20 days. If A and B together can complete the project in 30 days, then find the day on which the project will be completed after C replaces B, if the efficiency of B is twice that of A.a)15th dayb)11th dayc)9th dayd)7th dayCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of
A and B start working on a project. After 10 days B is replaced by C who can complete the project alone in 20 days. If A and B together can complete the project in 30 days, then find the day on which the project will be completed after C replaces B, if the efficiency of B is twice that of A.a)15th dayb)11th dayc)9th dayd)7th dayCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for A and B start working on a project. After 10 days B is replaced by C who can complete the project alone in 20 days. If A and B together can complete the project in 30 days, then find the day on which the project will be completed after C replaces B, if the efficiency of B is twice that of A.a)15th dayb)11th dayc)9th dayd)7th dayCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of A and B start working on a project. After 10 days B is replaced by C who can complete the project alone in 20 days. If A and B together can complete the project in 30 days, then find the day on which the project will be completed after C replaces B, if the efficiency of B is twice that of A.a)15th dayb)11th dayc)9th dayd)7th dayCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an
ample number of questions to practice A and B start working on a project. After 10 days B is replaced by C who can complete the project alone in 20 days. If A and B together can complete the project in 30 days, then find the day on which the project will be completed after C replaces B, if the efficiency of B is twice that of A.a)15th dayb)11th dayc)9th dayd)7th dayCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice CAT tests.