CAT Exam  >  CAT Questions  >  A and B start working on a project. After 10 ... Start Learning for Free
A and B start working on a project. After 10 days B is replaced by C who can complete the project alone in 20 days. If A and B together can complete the project in 30 days, then find the day on which the project will be completed after C replaces B, if the efficiency of B is twice that of A.
  • a)
    15th day
  • b)
    11th day
  • c)
    9th day
  • d)
    7th day 
Correct answer is option 'B'. Can you explain this answer?
Verified Answer
A and B start working on a project. After 10 days B is replaced by C w...
Let the number of days required by B alone to complete the project be x
The number of days required by A alone to complete it = 2x
1/x + l/2x = 1/30
⇒ x = 45
The part of work done in 10 days =1/3
Work done by A and C in 1 day = (1/90) + (1/20) = (11/180)
∴ The number of days taken by A and C = (2/3) / (11/180) = 120/11 = (10*12) / 11 days.
Hence, option 2.
This question is part of UPSC exam. View all CAT courses
Most Upvoted Answer
A and B start working on a project. After 10 days B is replaced by C w...
Let's assume that the total work in the project is represented by 'W'.

Efficiency of A:
Let the efficiency of A be 'x'. So, A can complete 1/xth of the work in 1 day.

Efficiency of B:
Given that the efficiency of B is twice that of A. So, the efficiency of B is '2x'. Hence, B can complete 1/(2x)th of the work in 1 day.

Efficiency of A and B together:
When A and B work together, their combined efficiency is the sum of their individual efficiencies. Hence, their combined efficiency is 'x + 2x = 3x'. Therefore, A and B together can complete 1/(3x)th of the work in 1 day.

Efficiency of C:
Given that C can complete the project alone in 20 days. So, the efficiency of C is 1/20th of the total work per day.

Let's calculate the work done by A, B, and A+B in 10 days:
Work done by A in 10 days = (1/x) * 10 = 10/x
Work done by B in 10 days = (1/(2x)) * 10 = 10/(2x) = 5/x
Work done by A and B together in 10 days = (1/(3x)) * 10 = 10/(3x)

Remaining work after 10 days:
Total work - Work done by A, B, and A+B in 10 days = W - (10/x + 5/x + 10/(3x)) = W - (25/x + 10/(3x)) = W - (75 + 10)/(3x) = W - 85/(3x)

Now, C replaces B and starts working alone. Let's calculate the number of days C will take to complete the remaining work after 10 days:
Given that C can complete 1/20th of the work in 1 day. So, C will complete the remaining work in (W - 85/(3x)) * 20 days.

To find the day on which the project will be completed after C replaces B, we need to find the value of (W - 85/(3x)) * 20.

Let's simplify the expression:
(W - 85/(3x)) * 20 = (20W - (85/3x) * 20) = 20W - (1700/3x)

Since we are looking for the day on which the project will be completed, we need to find the integer value of (W - 85/(3x)) * 20.

Let's analyze the given options:

a) 15th day: (W - 85/(3x)) * 20 = 20W - (1700/3x) = 20W - (113.33/x)
b) 11th day: (W - 85/(3x)) * 20 = 20W - (1700/3x) = 20W - (1700/3x)
c) 9th day: (W - 85/(3x)) * 20 = 20W - (1700/3x) = 20W - (212.5/x)
d) 7th day
Community Answer
A and B start working on a project. After 10 days B is replaced by C w...
A takes twice the time b takes to complete the work.
B takes 45 days. and A takes 90 days.
both A and B worked for 10 days that is equal to 1/3 rd of the work. hence 2/3rd work is remaining. both A and C will finish this work in 11 days
Attention CAT Students!
To make sure you are not studying endlessly, EduRev has designed CAT study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in CAT.
Explore Courses for CAT exam

Similar CAT Doubts

Top Courses for CAT

A and B start working on a project. After 10 days B is replaced by C who can complete the project alone in 20 days. If A and B together can complete the project in 30 days, then find the day on which the project will be completed after C replaces B, if the efficiency of B is twice that of A.a)15th dayb)11th dayc)9th dayd)7th dayCorrect answer is option 'B'. Can you explain this answer?
Question Description
A and B start working on a project. After 10 days B is replaced by C who can complete the project alone in 20 days. If A and B together can complete the project in 30 days, then find the day on which the project will be completed after C replaces B, if the efficiency of B is twice that of A.a)15th dayb)11th dayc)9th dayd)7th dayCorrect answer is option 'B'. Can you explain this answer? for CAT 2024 is part of CAT preparation. The Question and answers have been prepared according to the CAT exam syllabus. Information about A and B start working on a project. After 10 days B is replaced by C who can complete the project alone in 20 days. If A and B together can complete the project in 30 days, then find the day on which the project will be completed after C replaces B, if the efficiency of B is twice that of A.a)15th dayb)11th dayc)9th dayd)7th dayCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for CAT 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A and B start working on a project. After 10 days B is replaced by C who can complete the project alone in 20 days. If A and B together can complete the project in 30 days, then find the day on which the project will be completed after C replaces B, if the efficiency of B is twice that of A.a)15th dayb)11th dayc)9th dayd)7th dayCorrect answer is option 'B'. Can you explain this answer?.
Solutions for A and B start working on a project. After 10 days B is replaced by C who can complete the project alone in 20 days. If A and B together can complete the project in 30 days, then find the day on which the project will be completed after C replaces B, if the efficiency of B is twice that of A.a)15th dayb)11th dayc)9th dayd)7th dayCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for CAT. Download more important topics, notes, lectures and mock test series for CAT Exam by signing up for free.
Here you can find the meaning of A and B start working on a project. After 10 days B is replaced by C who can complete the project alone in 20 days. If A and B together can complete the project in 30 days, then find the day on which the project will be completed after C replaces B, if the efficiency of B is twice that of A.a)15th dayb)11th dayc)9th dayd)7th dayCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A and B start working on a project. After 10 days B is replaced by C who can complete the project alone in 20 days. If A and B together can complete the project in 30 days, then find the day on which the project will be completed after C replaces B, if the efficiency of B is twice that of A.a)15th dayb)11th dayc)9th dayd)7th dayCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for A and B start working on a project. After 10 days B is replaced by C who can complete the project alone in 20 days. If A and B together can complete the project in 30 days, then find the day on which the project will be completed after C replaces B, if the efficiency of B is twice that of A.a)15th dayb)11th dayc)9th dayd)7th dayCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of A and B start working on a project. After 10 days B is replaced by C who can complete the project alone in 20 days. If A and B together can complete the project in 30 days, then find the day on which the project will be completed after C replaces B, if the efficiency of B is twice that of A.a)15th dayb)11th dayc)9th dayd)7th dayCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A and B start working on a project. After 10 days B is replaced by C who can complete the project alone in 20 days. If A and B together can complete the project in 30 days, then find the day on which the project will be completed after C replaces B, if the efficiency of B is twice that of A.a)15th dayb)11th dayc)9th dayd)7th dayCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice CAT tests.
Explore Courses for CAT exam

Top Courses for CAT

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev