DIRECTIONSfor the question:Solve the following question and write the ...
►Total work = 30 * 12 = 360 men days. Work done by 12 men in 12 days = 144 mandays.
►Work left = 360 - 144 = 216 mandays. Now as they have increased their efficiency by 50 % so now they will be doing the work of 9 men.
►Assuming that they will complete the work in X days.
►Then X * 9 = 216 mandays. X = 24 days.
Hence 6 more days will be taken.
View all questions of this test
DIRECTIONSfor the question:Solve the following question and write the ...
Given Information:
- 12 men are employed to complete a job in 30 days.
- After 12 days, 6 men leave.
To Find:
- How many more days over and above the schedule will be required to complete the job if the remaining men increase their working rate by 50%?
Solution:
Step 1: Calculate the work done by 12 men in 12 days:
- Let's assume that the total work required to complete the job is represented by "W".
- Since 12 men are employed to complete the job in 30 days, the work done by 12 men in one day is "W/30".
- Therefore, the work done by 12 men in 12 days is (W/30) * 12 = W/2.
Step 2: Calculate the work remaining after 12 days:
- Since the work done by 12 men in 12 days is W/2, the work remaining after 12 days is W - (W/2) = W/2.
Step 3: Calculate the number of men remaining:
- After 12 days, 6 men leave, so the number of men remaining is 12 - 6 = 6.
Step 4: Calculate the increased working rate:
- The remaining men increase their working rate by 50%, which means they will work 1.5 times faster than before.
Step 5: Calculate the new work done by the remaining men in one day:
- Since the remaining men are working 1.5 times faster, the work done by the remaining men in one day is (W/30) * 1.5 = W/20.
Step 6: Calculate the time required to complete the remaining work:
- Since the work remaining after 12 days is W/2 and the new work done by the remaining men in one day is W/20, the time required to complete the remaining work is (W/2) / (W/20) = 10 days.
Step 7: Calculate the total time required:
- The total time required to complete the job is the sum of the time taken for the initial 12 days and the time taken to complete the remaining work.
- Therefore, the total time required is 12 + 10 = 22 days.
Step 8: Calculate the extra days over the schedule:
- The schedule was to complete the job in 30 days, but it took 22 days to complete.
- Therefore, the extra days over the schedule are 30 - 22 = 8 days.
Conclusion:
- The remaining men, working at an increased rate, will require 10 more days to complete the job.
- Therefore, the total number of days over and above the schedule will be 22 - 12 = 10 days.
To make sure you are not studying endlessly, EduRev has designed CAT study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in CAT.