CAT Exam  >  CAT Questions  >  DIRECTIONSfor the question:Solve the followin... Start Learning for Free
DIRECTIONS for the question: Solve the following question and write the answer (in numerical value).
Twelve men are employed to complete a job in 30 days. After 12 days 6 men leave. How many more days over and above the schedule will be required to complete the job if the remaining men increase their working rate by 50%? (in days)
    Correct answer is '6'. Can you explain this answer?
    Verified Answer
    DIRECTIONSfor the question:Solve the following question and write the ...
    ►Total work = 30 * 12 = 360 men days. Work done by 12 men in 12 days = 144 mandays.
    ►Work left = 360 - 144 = 216 mandays. Now as they have increased their efficiency by 50 % so now they will be doing the work of 9 men.
    ►Assuming that they will complete the work in X days.
    ►Then X * 9 = 216 mandays. X = 24 days.
    Hence 6 more days will be taken.
    View all questions of this test
    Most Upvoted Answer
    DIRECTIONSfor the question:Solve the following question and write the ...
    Given Information:
    - 12 men are employed to complete a job in 30 days.
    - After 12 days, 6 men leave.

    To Find:
    - How many more days over and above the schedule will be required to complete the job if the remaining men increase their working rate by 50%?

    Solution:

    Step 1: Calculate the work done by 12 men in 12 days:
    - Let's assume that the total work required to complete the job is represented by "W".
    - Since 12 men are employed to complete the job in 30 days, the work done by 12 men in one day is "W/30".
    - Therefore, the work done by 12 men in 12 days is (W/30) * 12 = W/2.

    Step 2: Calculate the work remaining after 12 days:
    - Since the work done by 12 men in 12 days is W/2, the work remaining after 12 days is W - (W/2) = W/2.

    Step 3: Calculate the number of men remaining:
    - After 12 days, 6 men leave, so the number of men remaining is 12 - 6 = 6.

    Step 4: Calculate the increased working rate:
    - The remaining men increase their working rate by 50%, which means they will work 1.5 times faster than before.

    Step 5: Calculate the new work done by the remaining men in one day:
    - Since the remaining men are working 1.5 times faster, the work done by the remaining men in one day is (W/30) * 1.5 = W/20.

    Step 6: Calculate the time required to complete the remaining work:
    - Since the work remaining after 12 days is W/2 and the new work done by the remaining men in one day is W/20, the time required to complete the remaining work is (W/2) / (W/20) = 10 days.

    Step 7: Calculate the total time required:
    - The total time required to complete the job is the sum of the time taken for the initial 12 days and the time taken to complete the remaining work.
    - Therefore, the total time required is 12 + 10 = 22 days.

    Step 8: Calculate the extra days over the schedule:
    - The schedule was to complete the job in 30 days, but it took 22 days to complete.
    - Therefore, the extra days over the schedule are 30 - 22 = 8 days.

    Conclusion:
    - The remaining men, working at an increased rate, will require 10 more days to complete the job.
    - Therefore, the total number of days over and above the schedule will be 22 - 12 = 10 days.
    Attention CAT Students!
    To make sure you are not studying endlessly, EduRev has designed CAT study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in CAT.
    Explore Courses for CAT exam

    Similar CAT Doubts

    DIRECTION for the question: Read the following information and choose the best alternative:The year 2004 was a great year for Top-Cloth cotton mill. Manufacturing towels for the export market employing more than 2000 workers, the company had an impressive growth in sales and profits. The Chairman felt that employees were entitled to a share in the profits and it was proposed that the employee mess be air-conditioned. The proposal was discussed in a meeting that was attended by, among other senior officials, the marketing director, the personnel director and the finance director. The proposal was based on the fact that the shop floor of the mill often had temperatures in excess of 40°C with a relative humidity of 99%. The air-conditioned mess would represent managements appreciation of the employees hard work.At the end of 2005, management reviewed the mills performance. Profits were higher, and employee attrition was negligible. Chairman decided that employees deserved additional recognition for their fine work. Since the mess had already been air-conditioned, the chairman wanted to know if the employees appreciated this sort of action. In the course of discussion, the chairman asked the personnel director to send a questionnaire to a sample of fifty employees and obtain their reaction to the air-conditioned mess. The management agreed to decide only after obtaining the feedback from the employees.The personnel director mailed a simple form to fifty employees asked them for the following information: "Please state your reaction to the air-conditioned mess."Of the fifty forms mailed, forty-six were returned. The answers received were as follows:Q.The main conclusion(s) about the personnel director that emerge(s) from this situation is(ar e):A. The personnel director did not have the competence to manage an employee feedback survey, and should have been given the task to a professional consultant.B. The personnel director was responsible for employees reactions.C. The personnel director had failed in his duty of maintaining constant touch with employees.D. The cost of air-conditioning is a waste, since its beneficiaries did not feel any benefit.

    DIRECTION for the question: Read the following information and choose the best alternative:The year 2004 was a great year for Top-Cloth cotton mill. Manufacturing towels for the export market employing more than 2000 workers, the company had an impressive growth in sales and profits. The Chairman felt that employees were entitled to a share in the profits and it was proposed that the employee mess be air-conditioned. The proposal was discussed in a meeting that was attended by, among other senior officials, the marketing director, the personnel director and the finance director. The proposal was based on the fact that the shop floor of the mill often had temperatures in excess of 40°C with a relative humidity of 99%. The air-conditioned mess would represent managements appreciation of the employees hard work.At the end of 2005, management reviewed the mills performance. Profits were higher, and employee attrition was negligible. Chairman decided that employees deserved additional recognition for their fine work. Since the mess had already been air-conditioned, the chairman wanted to know if the employees appreciated this sort of action. In the course of discussion, the chairman asked the personnel director to send a questionnaire to a sample of fifty employees and obtain their reaction to the air-conditioned mess. The management agreed to decide only after obtaining the feedback from the employees.The personnel director mailed a simple form to fifty employees asked them for the following information: "Please state your reaction to the air-conditioned mess."Of the fifty forms mailed, forty-six were returned. The answers received were as follows:Q.This decision-making situation best highlights

    DIRECTION for the question: Read the following information and choose the best alternative:The year 2004 was a great year for Top-Cloth cotton mill. Manufacturing towels for the export market employing more than 2000 workers, the company had an impressive growth in sales and profits. The Chairman felt that employees were entitled to a share in the profits and it was proposed that the employee mess be air-conditioned. The proposal was discussed in a meeting that was attended by, among other senior officials, the marketing director, the personnel director and the finance director. The proposal was based on the fact that the shop floor of the mill often had temperatures in excess of 40°C with a relative humidity of 99%. The air-conditioned mess would represent managements appreciation of the employees hard work.At the end of 2005, management reviewed the mills performance. Profits were higher, and employee attrition was negligible. Chairman decided that employees deserved additional recognition for their fine work. Since the mess had already been air-conditioned, the chairman wanted to know if the employees appreciated this sort of action. In the course of discussion, the chairman asked the personnel director to send a questionnaire to a sample of fifty employees and obtain their reaction to the air-conditioned mess. The management agreed to decide only after obtaining the feedback from the employees.The personnel director mailed a simple form to fifty employees asked them for the following information: "Please state your reaction to the air-conditioned mess."Of the fifty forms mailed, forty-six were returned. The answers received were as follows:Q.Management of Top-Cloth cotton mill considers itself to be socially conscious and its decisions are often re–examined for their social relevance and the impact on society. In view of this consideration, what could have been considered before deciding on profit sharing?A. communicating managements intentions via employee newslettersB. taking employees inputs in designing the cafeterias interiors and installation of air- conditioningC. considering employees views on different ways of sharing excess profitsD. investing in capacity expansion to take care of the booming export marketE. dividing the profits equally among the workers and shareholdersThe options in decreasing order of their impact on society

    DIRECTIONSfor the question:Solve the following question and write the answer (in numerical value).Twelve men are employed to complete a job in 30 days. After 12 days 6 men leave. How many more days over and above the schedule will be required to complete the job if the remaining men increase their working rate by 50%? (in days)Correct answer is '6'. Can you explain this answer?
    Question Description
    DIRECTIONSfor the question:Solve the following question and write the answer (in numerical value).Twelve men are employed to complete a job in 30 days. After 12 days 6 men leave. How many more days over and above the schedule will be required to complete the job if the remaining men increase their working rate by 50%? (in days)Correct answer is '6'. Can you explain this answer? for CAT 2024 is part of CAT preparation. The Question and answers have been prepared according to the CAT exam syllabus. Information about DIRECTIONSfor the question:Solve the following question and write the answer (in numerical value).Twelve men are employed to complete a job in 30 days. After 12 days 6 men leave. How many more days over and above the schedule will be required to complete the job if the remaining men increase their working rate by 50%? (in days)Correct answer is '6'. Can you explain this answer? covers all topics & solutions for CAT 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for DIRECTIONSfor the question:Solve the following question and write the answer (in numerical value).Twelve men are employed to complete a job in 30 days. After 12 days 6 men leave. How many more days over and above the schedule will be required to complete the job if the remaining men increase their working rate by 50%? (in days)Correct answer is '6'. Can you explain this answer?.
    Solutions for DIRECTIONSfor the question:Solve the following question and write the answer (in numerical value).Twelve men are employed to complete a job in 30 days. After 12 days 6 men leave. How many more days over and above the schedule will be required to complete the job if the remaining men increase their working rate by 50%? (in days)Correct answer is '6'. Can you explain this answer? in English & in Hindi are available as part of our courses for CAT. Download more important topics, notes, lectures and mock test series for CAT Exam by signing up for free.
    Here you can find the meaning of DIRECTIONSfor the question:Solve the following question and write the answer (in numerical value).Twelve men are employed to complete a job in 30 days. After 12 days 6 men leave. How many more days over and above the schedule will be required to complete the job if the remaining men increase their working rate by 50%? (in days)Correct answer is '6'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of DIRECTIONSfor the question:Solve the following question and write the answer (in numerical value).Twelve men are employed to complete a job in 30 days. After 12 days 6 men leave. How many more days over and above the schedule will be required to complete the job if the remaining men increase their working rate by 50%? (in days)Correct answer is '6'. Can you explain this answer?, a detailed solution for DIRECTIONSfor the question:Solve the following question and write the answer (in numerical value).Twelve men are employed to complete a job in 30 days. After 12 days 6 men leave. How many more days over and above the schedule will be required to complete the job if the remaining men increase their working rate by 50%? (in days)Correct answer is '6'. Can you explain this answer? has been provided alongside types of DIRECTIONSfor the question:Solve the following question and write the answer (in numerical value).Twelve men are employed to complete a job in 30 days. After 12 days 6 men leave. How many more days over and above the schedule will be required to complete the job if the remaining men increase their working rate by 50%? (in days)Correct answer is '6'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice DIRECTIONSfor the question:Solve the following question and write the answer (in numerical value).Twelve men are employed to complete a job in 30 days. After 12 days 6 men leave. How many more days over and above the schedule will be required to complete the job if the remaining men increase their working rate by 50%? (in days)Correct answer is '6'. Can you explain this answer? tests, examples and also practice CAT tests.
    Explore Courses for CAT exam

    Top Courses for CAT

    Explore Courses
    Signup for Free!
    Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
    10M+ students study on EduRev