Question Description
40 men could have finished the whole project in 28 days but due to the inclusion of a few more men, work got done in 3/4 of the time. Find out how many more men were included (in whole numbers). Related: Practice Questions: Ratio & Proportion? for UPSC 2025 is part of UPSC preparation. The Question and answers have been prepared
according to
the UPSC exam syllabus. Information about 40 men could have finished the whole project in 28 days but due to the inclusion of a few more men, work got done in 3/4 of the time. Find out how many more men were included (in whole numbers). Related: Practice Questions: Ratio & Proportion? covers all topics & solutions for UPSC 2025 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for 40 men could have finished the whole project in 28 days but due to the inclusion of a few more men, work got done in 3/4 of the time. Find out how many more men were included (in whole numbers). Related: Practice Questions: Ratio & Proportion?.
Solutions for 40 men could have finished the whole project in 28 days but due to the inclusion of a few more men, work got done in 3/4 of the time. Find out how many more men were included (in whole numbers). Related: Practice Questions: Ratio & Proportion? in English & in Hindi are available as part of our courses for UPSC.
Download more important topics, notes, lectures and mock test series for UPSC Exam by signing up for free.
Here you can find the meaning of 40 men could have finished the whole project in 28 days but due to the inclusion of a few more men, work got done in 3/4 of the time. Find out how many more men were included (in whole numbers). Related: Practice Questions: Ratio & Proportion? defined & explained in the simplest way possible. Besides giving the explanation of
40 men could have finished the whole project in 28 days but due to the inclusion of a few more men, work got done in 3/4 of the time. Find out how many more men were included (in whole numbers). Related: Practice Questions: Ratio & Proportion?, a detailed solution for 40 men could have finished the whole project in 28 days but due to the inclusion of a few more men, work got done in 3/4 of the time. Find out how many more men were included (in whole numbers). Related: Practice Questions: Ratio & Proportion? has been provided alongside types of 40 men could have finished the whole project in 28 days but due to the inclusion of a few more men, work got done in 3/4 of the time. Find out how many more men were included (in whole numbers). Related: Practice Questions: Ratio & Proportion? theory, EduRev gives you an
ample number of questions to practice 40 men could have finished the whole project in 28 days but due to the inclusion of a few more men, work got done in 3/4 of the time. Find out how many more men were included (in whole numbers). Related: Practice Questions: Ratio & Proportion? tests, examples and also practice UPSC tests.