40 men could have finished the whole project in 28 days but due to the inclusion of a few more men, work got done in 3/4 of the time. Find out how many more men were included (in whole numbers). 
?
Most Upvoted Answer
40 men could have finished the whole project in 28 days but due to the...
Let's start by finding the total work that needs to be done. We know that 40 men can finish the project in 28 days, so we can use the formula:

Men × Days = Work

40 × 28 = Work

Work = 1120

This means that the total work that needs to be done is 1120 units.

Now, we are told that the work got done in 3/4 of the time. This means that the new time taken is:

28 × 3/4 = 21 days

We can use the same formula to find out how many men were working on the project during these 21 days:

Men × Days = Work

Men × 21 = 1120

Men = 1120/21

Men ≈ 53.33

Since we need a whole number of men, we can round up to 54. Therefore, 54 men were working on the project during the last 21 days.

To find out how many more men were included, we can subtract the original 40 men from the final 54 men:

54 – 40 = 14

Therefore, 14 more men were included in the project.
Community Answer
40 men could have finished the whole project in 28 days but due to the...
13
Explore Courses for UPSC exam

Top Courses for UPSC

40 men could have finished the whole project in 28 days but due to the inclusion of a few more men, work got done in 3/4 of the time. Find out how many more men were included (in whole numbers).  Related: Practice Questions: Ratio & Proportion?
Question Description
40 men could have finished the whole project in 28 days but due to the inclusion of a few more men, work got done in 3/4 of the time. Find out how many more men were included (in whole numbers).  Related: Practice Questions: Ratio & Proportion? for UPSC 2025 is part of UPSC preparation. The Question and answers have been prepared according to the UPSC exam syllabus. Information about 40 men could have finished the whole project in 28 days but due to the inclusion of a few more men, work got done in 3/4 of the time. Find out how many more men were included (in whole numbers).  Related: Practice Questions: Ratio & Proportion? covers all topics & solutions for UPSC 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for 40 men could have finished the whole project in 28 days but due to the inclusion of a few more men, work got done in 3/4 of the time. Find out how many more men were included (in whole numbers).  Related: Practice Questions: Ratio & Proportion?.
Solutions for 40 men could have finished the whole project in 28 days but due to the inclusion of a few more men, work got done in 3/4 of the time. Find out how many more men were included (in whole numbers).  Related: Practice Questions: Ratio & Proportion? in English & in Hindi are available as part of our courses for UPSC. Download more important topics, notes, lectures and mock test series for UPSC Exam by signing up for free.
Here you can find the meaning of 40 men could have finished the whole project in 28 days but due to the inclusion of a few more men, work got done in 3/4 of the time. Find out how many more men were included (in whole numbers).  Related: Practice Questions: Ratio & Proportion? defined & explained in the simplest way possible. Besides giving the explanation of 40 men could have finished the whole project in 28 days but due to the inclusion of a few more men, work got done in 3/4 of the time. Find out how many more men were included (in whole numbers).  Related: Practice Questions: Ratio & Proportion?, a detailed solution for 40 men could have finished the whole project in 28 days but due to the inclusion of a few more men, work got done in 3/4 of the time. Find out how many more men were included (in whole numbers).  Related: Practice Questions: Ratio & Proportion? has been provided alongside types of 40 men could have finished the whole project in 28 days but due to the inclusion of a few more men, work got done in 3/4 of the time. Find out how many more men were included (in whole numbers).  Related: Practice Questions: Ratio & Proportion? theory, EduRev gives you an ample number of questions to practice 40 men could have finished the whole project in 28 days but due to the inclusion of a few more men, work got done in 3/4 of the time. Find out how many more men were included (in whole numbers).  Related: Practice Questions: Ratio & Proportion? tests, examples and also practice UPSC tests.
Explore Courses for UPSC exam

Top Courses for UPSC

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev