CAT Exam  >  CAT Questions  >   A can complete a project in 20 days and B ca... Start Learning for Free
A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed, in how many days will the project be completed?
  • a)
    18 days
  • b)
    27 days
  • c)
    26.66 days
  • d)
    16 days
  • e)
    None of the Above
Correct answer is option 'A'. Can you explain this answer?
Verified Answer
A can complete a project in 20 days and B can complete the same proje...
If A can complete a project in 20 days, then A will complete 1/20 th of the project in a day.
Similarly, B will complete 1/30 th of the project in a day.
Let the total number of days taken to complete the project be x days.
Then, B would have worked for all x days, while A would have worked for (x - 10) days.
Therefore, A would have completed x-10/20 th of the project and B would have completed x/30 th of the project.
i.e., (x-10)/20+ x/30=1
Solving for x, we get x = 18.
View all questions of this test
Explore Courses for CAT exam
A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed, in how many days will the project be completed?a)18 daysb)27 daysc)26.66 daysd)16 dayse)None of the AboveCorrect answer is option 'A'. Can you explain this answer?
Question Description
A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed, in how many days will the project be completed?a)18 daysb)27 daysc)26.66 daysd)16 dayse)None of the AboveCorrect answer is option 'A'. Can you explain this answer? for CAT 2024 is part of CAT preparation. The Question and answers have been prepared according to the CAT exam syllabus. Information about A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed, in how many days will the project be completed?a)18 daysb)27 daysc)26.66 daysd)16 dayse)None of the AboveCorrect answer is option 'A'. Can you explain this answer? covers all topics & solutions for CAT 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed, in how many days will the project be completed?a)18 daysb)27 daysc)26.66 daysd)16 dayse)None of the AboveCorrect answer is option 'A'. Can you explain this answer?.
Solutions for A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed, in how many days will the project be completed?a)18 daysb)27 daysc)26.66 daysd)16 dayse)None of the AboveCorrect answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for CAT. Download more important topics, notes, lectures and mock test series for CAT Exam by signing up for free.
Here you can find the meaning of A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed, in how many days will the project be completed?a)18 daysb)27 daysc)26.66 daysd)16 dayse)None of the AboveCorrect answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed, in how many days will the project be completed?a)18 daysb)27 daysc)26.66 daysd)16 dayse)None of the AboveCorrect answer is option 'A'. Can you explain this answer?, a detailed solution for A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed, in how many days will the project be completed?a)18 daysb)27 daysc)26.66 daysd)16 dayse)None of the AboveCorrect answer is option 'A'. Can you explain this answer? has been provided alongside types of A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed, in how many days will the project be completed?a)18 daysb)27 daysc)26.66 daysd)16 dayse)None of the AboveCorrect answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed, in how many days will the project be completed?a)18 daysb)27 daysc)26.66 daysd)16 dayse)None of the AboveCorrect answer is option 'A'. Can you explain this answer? tests, examples and also practice CAT tests.
Explore Courses for CAT exam

Top Courses for CAT

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev