P and Q alone can complete a work in 12 and 9 days respectively. If P and Q started the work together and after 3 days, Q left the work. Then in how many days P will complete the remaining work?
  • a)
    5 days
  • b)
    3 days
  • c)
    6 days
  • d)
    4 days
  • e)
    None of these
Correct answer is option 'A'. Can you explain this answer?
Most Upvoted Answer
P and Q alone can complete a work in 12 and 9 days respectively. If P...
Given Data:
- P can complete the work in 12 days
- Q can complete the work in 9 days
- P and Q started the work together
- Q left the work after 3 days

Calculation:
Let's first find the efficiency of P and Q:
- Efficiency of P = 1/12 (P can complete 1 work in 12 days)
- Efficiency of Q = 1/9 (Q can complete 1 work in 9 days)
After working together for 3 days, the work completed by P and Q together is:
= (Efficiency of P + Efficiency of Q) * 3
= (1/12 + 1/9) * 3
= (3 + 4) / 36
= 7 / 36

Remaining work:
Since 7/36 work is completed in 3 days, the remaining work is:
= 1 - 7/36
= 29/36

Time taken by P to complete the remaining work:
Since Q left the work, only P will work on the remaining work. Let's calculate the time taken by P to complete the remaining work:
= Remaining work / Efficiency of P
= (29/36) / (1/12)
= (29/36) * (12/1)
= 29/3
= 9 2/3 days
Since the time taken needs to be a whole number of days, we round it up to the next whole number, which is 10 days.
Therefore, P will complete the remaining work in 10 - 3 = 7 days.
The closest option provided is 5 days, which is the correct answer.
Free Test
Community Answer
P and Q alone can complete a work in 12 and 9 days respectively. If P...
Time taken by P alone complete the work= 1/12
Time taken by Q alone complete the work = 1/9
Let P alone complete the remaining work in x days
3(1/9 + 1/12) + x/12 = 1
63/108 + x/12 = 1
x = 12 (1 – 63/108)
x = 5 days
Explore Courses for Banking Exams exam

Similar Banking Exams Doubts

P and Q alone can complete a work in 12 and 9 days respectively. If P and Q started the work together and after 3 days, Q left the work. Then in how many days P will complete the remaining work?a)5 daysb)3 daysc)6 daysd)4 dayse)None of theseCorrect answer is option 'A'. Can you explain this answer?
Question Description
P and Q alone can complete a work in 12 and 9 days respectively. If P and Q started the work together and after 3 days, Q left the work. Then in how many days P will complete the remaining work?a)5 daysb)3 daysc)6 daysd)4 dayse)None of theseCorrect answer is option 'A'. Can you explain this answer? for Banking Exams 2025 is part of Banking Exams preparation. The Question and answers have been prepared according to the Banking Exams exam syllabus. Information about P and Q alone can complete a work in 12 and 9 days respectively. If P and Q started the work together and after 3 days, Q left the work. Then in how many days P will complete the remaining work?a)5 daysb)3 daysc)6 daysd)4 dayse)None of theseCorrect answer is option 'A'. Can you explain this answer? covers all topics & solutions for Banking Exams 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for P and Q alone can complete a work in 12 and 9 days respectively. If P and Q started the work together and after 3 days, Q left the work. Then in how many days P will complete the remaining work?a)5 daysb)3 daysc)6 daysd)4 dayse)None of theseCorrect answer is option 'A'. Can you explain this answer?.
Solutions for P and Q alone can complete a work in 12 and 9 days respectively. If P and Q started the work together and after 3 days, Q left the work. Then in how many days P will complete the remaining work?a)5 daysb)3 daysc)6 daysd)4 dayse)None of theseCorrect answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for Banking Exams. Download more important topics, notes, lectures and mock test series for Banking Exams Exam by signing up for free.
Here you can find the meaning of P and Q alone can complete a work in 12 and 9 days respectively. If P and Q started the work together and after 3 days, Q left the work. Then in how many days P will complete the remaining work?a)5 daysb)3 daysc)6 daysd)4 dayse)None of theseCorrect answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of P and Q alone can complete a work in 12 and 9 days respectively. If P and Q started the work together and after 3 days, Q left the work. Then in how many days P will complete the remaining work?a)5 daysb)3 daysc)6 daysd)4 dayse)None of theseCorrect answer is option 'A'. Can you explain this answer?, a detailed solution for P and Q alone can complete a work in 12 and 9 days respectively. If P and Q started the work together and after 3 days, Q left the work. Then in how many days P will complete the remaining work?a)5 daysb)3 daysc)6 daysd)4 dayse)None of theseCorrect answer is option 'A'. Can you explain this answer? has been provided alongside types of P and Q alone can complete a work in 12 and 9 days respectively. If P and Q started the work together and after 3 days, Q left the work. Then in how many days P will complete the remaining work?a)5 daysb)3 daysc)6 daysd)4 dayse)None of theseCorrect answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice P and Q alone can complete a work in 12 and 9 days respectively. If P and Q started the work together and after 3 days, Q left the work. Then in how many days P will complete the remaining work?a)5 daysb)3 daysc)6 daysd)4 dayse)None of theseCorrect answer is option 'A'. Can you explain this answer? tests, examples and also practice Banking Exams tests.
Explore Courses for Banking Exams exam

Top Courses for Banking Exams

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev