Mechanical Engineering Exam  >  Mechanical Engineering Questions  >  Earliest finish time can be regarded asa) EST... Start Learning for Free
Earliest finish time can be regarded as
  • a)
    EST + duration of activity
  • b)
    EST − duration of activity
  • c)
    LFT + duration of activity
  • d)
    LFT − duration of activity
Correct answer is option 'A'. Can you explain this answer?
Most Upvoted Answer
Earliest finish time can be regarded asa) EST + duration of activityb)...
Answer:

The earliest finish time (EFT) is an important concept in project management and scheduling. It represents the earliest possible time at which an activity can be completed, taking into account the duration of the activity and the dependencies it has with other activities in the project.

The correct option for the earliest finish time is "A" - EST (duration of activity). Let's understand why this is the case:

Explanation:

To calculate the earliest finish time (EFT) for an activity, we need to consider the following factors:

1. EST (Earliest Start Time): This is the earliest possible time at which an activity can start, taking into account the dependencies it has with other activities. It is calculated by considering the maximum of the earliest finish times of all the activities that precede it.

2. Duration of Activity: This is the time required to complete the activity. It is usually estimated based on the nature of the task and the available resources.

To calculate the earliest finish time (EFT), we add the earliest start time (EST) and the duration of the activity.

EFT = EST + Duration of Activity

Therefore, option "A" - EST (duration of activity) is the correct answer. The earliest finish time can be regarded as the earliest start time plus the duration of the activity.

The earliest finish time is an important parameter in project scheduling as it helps in determining the critical path and identifying activities that need to be completed on time to ensure the project's overall schedule is not delayed. By calculating the earliest finish time for each activity in the project, project managers can create an optimized schedule and allocate resources efficiently.

It is important to note that the other options provided in the question are not correct:

- Option "B" - EST minus the duration of activity is incorrect because subtracting the duration of activity from the earliest start time would give us the earliest start time of the preceding activity, not the earliest finish time of the current activity.

- Option "C" - LFT (latest finish time) multiplied by the duration of activity is incorrect because the latest finish time is the latest possible time at which an activity can be completed, not the earliest finish time.

- Option "D" - LFT minus the duration of activity is incorrect because subtracting the duration of activity from the latest finish time would give us the latest start time, not the earliest finish time.

In conclusion, the earliest finish time can be regarded as the earliest start time plus the duration of the activity (EST + Duration of Activity).
Attention Mechanical Engineering Students!
To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Earliest finish time can be regarded asa) EST + duration of activityb) EST − duration of activityc) LFT + duration of activityd) LFT − duration of activityCorrect answer is option 'A'. Can you explain this answer?
Question Description
Earliest finish time can be regarded asa) EST + duration of activityb) EST − duration of activityc) LFT + duration of activityd) LFT − duration of activityCorrect answer is option 'A'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about Earliest finish time can be regarded asa) EST + duration of activityb) EST − duration of activityc) LFT + duration of activityd) LFT − duration of activityCorrect answer is option 'A'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Earliest finish time can be regarded asa) EST + duration of activityb) EST − duration of activityc) LFT + duration of activityd) LFT − duration of activityCorrect answer is option 'A'. Can you explain this answer?.
Solutions for Earliest finish time can be regarded asa) EST + duration of activityb) EST − duration of activityc) LFT + duration of activityd) LFT − duration of activityCorrect answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of Earliest finish time can be regarded asa) EST + duration of activityb) EST − duration of activityc) LFT + duration of activityd) LFT − duration of activityCorrect answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Earliest finish time can be regarded asa) EST + duration of activityb) EST − duration of activityc) LFT + duration of activityd) LFT − duration of activityCorrect answer is option 'A'. Can you explain this answer?, a detailed solution for Earliest finish time can be regarded asa) EST + duration of activityb) EST − duration of activityc) LFT + duration of activityd) LFT − duration of activityCorrect answer is option 'A'. Can you explain this answer? has been provided alongside types of Earliest finish time can be regarded asa) EST + duration of activityb) EST − duration of activityc) LFT + duration of activityd) LFT − duration of activityCorrect answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Earliest finish time can be regarded asa) EST + duration of activityb) EST − duration of activityc) LFT + duration of activityd) LFT − duration of activityCorrect answer is option 'A'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev