The radar graph shown below shows the number of days to be taken by different workers A, B, C, and D to complete a particular task individually and the number of wages to be earned by them per day when they work.
Q. A and B work together for 1 day. Then they both leave and C and D work together for 1 day. This pattern continues until the entire work is completed. So, in how many days, total work will be completed?
  • a)
    6 days
  • b)
    6 x 3/10 days
  • c)
    7 x 3/10 days
  • d)
    6 x 1/10 days
Correct answer is option 'B'. Can you explain this answer?
Most Upvoted Answer
The radar graph shown below shows the number of days to be taken by d...
From the data given in the radar graph,
The number of days taken by A to complete a work is 15 days.
The number of days taken by B to complete a work is 10 days.
The number of days taken by C to complete a work is 15 days.
The number of days taken by D to complete a work is 12 days.
Let the total work be the LCM of days = 60 units
The efficiency of A is 60/15 = 4
The efficiency of B is 60/10 = 6
The efficiency of C is 60/15 = 4
The efficiency of D is 60/12 = 5
A and B together one day work is 4 + 6 = 10 units
C and D together one day works is 4 + 5 = 9 units
Work done in two days is 10 + 9 = 19 units
In 6 days, 19 × 3 = 57 units
The remaining units done in 3/10 days.
Hence, the correct answer is 6 x 3/10 days.
The concepts used in this question are
Attention CLAT Students!
To make sure you are not studying endlessly, EduRev has designed CLAT study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in CLAT.
Explore Courses for CLAT exam

Similar CLAT Doubts

Top Courses for CLAT

The radar graph shown below shows the number of days to be taken by different workers A, B, C, and D to complete a particular task individually and the number of wages to be earned by them per day when they work.Q. A and B work together for 1 day. Then they both leave and C and D work together for 1 day. This pattern continues until the entire work is completed. So, in how many days, total work will be completed?a)6 daysb)6 x 3/10 daysc)7 x 3/10 daysd)6 x 1/10 daysCorrect answer is option 'B'. Can you explain this answer?
Question Description
The radar graph shown below shows the number of days to be taken by different workers A, B, C, and D to complete a particular task individually and the number of wages to be earned by them per day when they work.Q. A and B work together for 1 day. Then they both leave and C and D work together for 1 day. This pattern continues until the entire work is completed. So, in how many days, total work will be completed?a)6 daysb)6 x 3/10 daysc)7 x 3/10 daysd)6 x 1/10 daysCorrect answer is option 'B'. Can you explain this answer? for CLAT 2024 is part of CLAT preparation. The Question and answers have been prepared according to the CLAT exam syllabus. Information about The radar graph shown below shows the number of days to be taken by different workers A, B, C, and D to complete a particular task individually and the number of wages to be earned by them per day when they work.Q. A and B work together for 1 day. Then they both leave and C and D work together for 1 day. This pattern continues until the entire work is completed. So, in how many days, total work will be completed?a)6 daysb)6 x 3/10 daysc)7 x 3/10 daysd)6 x 1/10 daysCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for CLAT 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The radar graph shown below shows the number of days to be taken by different workers A, B, C, and D to complete a particular task individually and the number of wages to be earned by them per day when they work.Q. A and B work together for 1 day. Then they both leave and C and D work together for 1 day. This pattern continues until the entire work is completed. So, in how many days, total work will be completed?a)6 daysb)6 x 3/10 daysc)7 x 3/10 daysd)6 x 1/10 daysCorrect answer is option 'B'. Can you explain this answer?.
Solutions for The radar graph shown below shows the number of days to be taken by different workers A, B, C, and D to complete a particular task individually and the number of wages to be earned by them per day when they work.Q. A and B work together for 1 day. Then they both leave and C and D work together for 1 day. This pattern continues until the entire work is completed. So, in how many days, total work will be completed?a)6 daysb)6 x 3/10 daysc)7 x 3/10 daysd)6 x 1/10 daysCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for CLAT. Download more important topics, notes, lectures and mock test series for CLAT Exam by signing up for free.
Here you can find the meaning of The radar graph shown below shows the number of days to be taken by different workers A, B, C, and D to complete a particular task individually and the number of wages to be earned by them per day when they work.Q. A and B work together for 1 day. Then they both leave and C and D work together for 1 day. This pattern continues until the entire work is completed. So, in how many days, total work will be completed?a)6 daysb)6 x 3/10 daysc)7 x 3/10 daysd)6 x 1/10 daysCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The radar graph shown below shows the number of days to be taken by different workers A, B, C, and D to complete a particular task individually and the number of wages to be earned by them per day when they work.Q. A and B work together for 1 day. Then they both leave and C and D work together for 1 day. This pattern continues until the entire work is completed. So, in how many days, total work will be completed?a)6 daysb)6 x 3/10 daysc)7 x 3/10 daysd)6 x 1/10 daysCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for The radar graph shown below shows the number of days to be taken by different workers A, B, C, and D to complete a particular task individually and the number of wages to be earned by them per day when they work.Q. A and B work together for 1 day. Then they both leave and C and D work together for 1 day. This pattern continues until the entire work is completed. So, in how many days, total work will be completed?a)6 daysb)6 x 3/10 daysc)7 x 3/10 daysd)6 x 1/10 daysCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of The radar graph shown below shows the number of days to be taken by different workers A, B, C, and D to complete a particular task individually and the number of wages to be earned by them per day when they work.Q. A and B work together for 1 day. Then they both leave and C and D work together for 1 day. This pattern continues until the entire work is completed. So, in how many days, total work will be completed?a)6 daysb)6 x 3/10 daysc)7 x 3/10 daysd)6 x 1/10 daysCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The radar graph shown below shows the number of days to be taken by different workers A, B, C, and D to complete a particular task individually and the number of wages to be earned by them per day when they work.Q. A and B work together for 1 day. Then they both leave and C and D work together for 1 day. This pattern continues until the entire work is completed. So, in how many days, total work will be completed?a)6 daysb)6 x 3/10 daysc)7 x 3/10 daysd)6 x 1/10 daysCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice CLAT tests.
Explore Courses for CLAT exam

Top Courses for CLAT

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev