Question Description
P can do a work in 24 days, while Q do it in 36 days. P and Q worked for alternate turns (started with P), such that on first turn P worked for one day, on second turn Q worked for 2 days and on third turn P worked for 3 days and so on. Find the time taken by R alone to complete the work which is sum of thrice the work done by P in 10 turns and six times of work done by Q in his 10 turns, if R is 20% more efficient than combined efficiency of P and Q together?a)225 daysb)175 daysc)185 daysd)205 dayse)None of theseCorrect answer is option 'E'. Can you explain this answer? for Banking Exams 2025 is part of Banking Exams preparation. The Question and answers have been prepared
according to
the Banking Exams exam syllabus. Information about P can do a work in 24 days, while Q do it in 36 days. P and Q worked for alternate turns (started with P), such that on first turn P worked for one day, on second turn Q worked for 2 days and on third turn P worked for 3 days and so on. Find the time taken by R alone to complete the work which is sum of thrice the work done by P in 10 turns and six times of work done by Q in his 10 turns, if R is 20% more efficient than combined efficiency of P and Q together?a)225 daysb)175 daysc)185 daysd)205 dayse)None of theseCorrect answer is option 'E'. Can you explain this answer? covers all topics & solutions for Banking Exams 2025 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for P can do a work in 24 days, while Q do it in 36 days. P and Q worked for alternate turns (started with P), such that on first turn P worked for one day, on second turn Q worked for 2 days and on third turn P worked for 3 days and so on. Find the time taken by R alone to complete the work which is sum of thrice the work done by P in 10 turns and six times of work done by Q in his 10 turns, if R is 20% more efficient than combined efficiency of P and Q together?a)225 daysb)175 daysc)185 daysd)205 dayse)None of theseCorrect answer is option 'E'. Can you explain this answer?.
Solutions for P can do a work in 24 days, while Q do it in 36 days. P and Q worked for alternate turns (started with P), such that on first turn P worked for one day, on second turn Q worked for 2 days and on third turn P worked for 3 days and so on. Find the time taken by R alone to complete the work which is sum of thrice the work done by P in 10 turns and six times of work done by Q in his 10 turns, if R is 20% more efficient than combined efficiency of P and Q together?a)225 daysb)175 daysc)185 daysd)205 dayse)None of theseCorrect answer is option 'E'. Can you explain this answer? in English & in Hindi are available as part of our courses for Banking Exams.
Download more important topics, notes, lectures and mock test series for Banking Exams Exam by signing up for free.
Here you can find the meaning of P can do a work in 24 days, while Q do it in 36 days. P and Q worked for alternate turns (started with P), such that on first turn P worked for one day, on second turn Q worked for 2 days and on third turn P worked for 3 days and so on. Find the time taken by R alone to complete the work which is sum of thrice the work done by P in 10 turns and six times of work done by Q in his 10 turns, if R is 20% more efficient than combined efficiency of P and Q together?a)225 daysb)175 daysc)185 daysd)205 dayse)None of theseCorrect answer is option 'E'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of
P can do a work in 24 days, while Q do it in 36 days. P and Q worked for alternate turns (started with P), such that on first turn P worked for one day, on second turn Q worked for 2 days and on third turn P worked for 3 days and so on. Find the time taken by R alone to complete the work which is sum of thrice the work done by P in 10 turns and six times of work done by Q in his 10 turns, if R is 20% more efficient than combined efficiency of P and Q together?a)225 daysb)175 daysc)185 daysd)205 dayse)None of theseCorrect answer is option 'E'. Can you explain this answer?, a detailed solution for P can do a work in 24 days, while Q do it in 36 days. P and Q worked for alternate turns (started with P), such that on first turn P worked for one day, on second turn Q worked for 2 days and on third turn P worked for 3 days and so on. Find the time taken by R alone to complete the work which is sum of thrice the work done by P in 10 turns and six times of work done by Q in his 10 turns, if R is 20% more efficient than combined efficiency of P and Q together?a)225 daysb)175 daysc)185 daysd)205 dayse)None of theseCorrect answer is option 'E'. Can you explain this answer? has been provided alongside types of P can do a work in 24 days, while Q do it in 36 days. P and Q worked for alternate turns (started with P), such that on first turn P worked for one day, on second turn Q worked for 2 days and on third turn P worked for 3 days and so on. Find the time taken by R alone to complete the work which is sum of thrice the work done by P in 10 turns and six times of work done by Q in his 10 turns, if R is 20% more efficient than combined efficiency of P and Q together?a)225 daysb)175 daysc)185 daysd)205 dayse)None of theseCorrect answer is option 'E'. Can you explain this answer? theory, EduRev gives you an
ample number of questions to practice P can do a work in 24 days, while Q do it in 36 days. P and Q worked for alternate turns (started with P), such that on first turn P worked for one day, on second turn Q worked for 2 days and on third turn P worked for 3 days and so on. Find the time taken by R alone to complete the work which is sum of thrice the work done by P in 10 turns and six times of work done by Q in his 10 turns, if R is 20% more efficient than combined efficiency of P and Q together?a)225 daysb)175 daysc)185 daysd)205 dayse)None of theseCorrect answer is option 'E'. Can you explain this answer? tests, examples and also practice Banking Exams tests.