Consider the following statements about the Guidelines for Charging Infrastructure for the Electric Vehicles:
The Ministry of Heavy Industries is the nodal agency for the roll-out of the EV public charging infrastructure.
  • All public charging stations can obtain electricity from any generation company through open access.
  • At least one charging station should be available in a grid of 3 km X 3 km.
    Which of the statements given above is/are correct?
    • a)
      1 only
    • b)
      2 and 3 only
    • c)
      1 and 3 only
    • d)
      1, 2 and 3
    Correct answer is option 'B'. Can you explain this answer?
    Most Upvoted Answer
    Consider the following statements about the Guidelines for Charging I...
    • Guidelines for Charging Infrastructure for the Electric Vehicles: The Ministry of Power has released the Guidelines for Charging Infrastructure for the Electric Vehicles.
    • Salient Features:
      • The owners may charge their EVs at their residences/offices using their existing electricity connections.
      • Any individual is free to establish public charging stations, which should meet the laid down technical, safety and performance metrics by the Bureau of Energy Efficiency, the Ministry of Power and the Central Electricity Authority.
      • The public charging station to get electricity connection by the distribution license company as per the Electricity (Rights of Consumers) Rules, 2020. (Less than 7 days in the metro cities, 15 days in other municipal areas, 30 days in the rural areas).
      • Any public charging station/chain of charging stations may obtain electricity from any generation company though opens access.
      • Requirements of the Public Charging Stations: Safety, adequate space for vehicles, tie up with network service providers to enable online booking of slots.
      • The public charging stations may also be installed by the housing societies, malls, office complexes, restaurants, hotels, etc.
      • Public Charging Infrastructure for Long Range EVs/Heavy Duty FVs:
        (a) They will have at least two chargers of minimum 100 kW (200-750 V or higher) each of different specification (CCS/CHAdeMO chargers for above capacity or BIS Standards for eBus Charging Station (250-500 kw)).
        (b) Appropriate liquid cooled cables for high-speed charging facility for onboarding charging of Fluid Cooled Batteries.
      • Location of the Public Charging Stations:
        (a) At least one charging station to be available in a grid of 3 km X 3 km.
        (b) One charging station shall be set up at every 25 km on both sides of the highways/roads.
        (c) At least one fast charging station at every 100 kms, one on each side of the highways/road.
        (d) Priority to the existing retail outlets of the Oil Marketing Companies for the installation of public EV charging stations.
      • Nodal Agency: The Bureau of Energy Efficiency (BEE), under the Ministry of Power, to be the Central Nodal Agency for the establishment of public EV charging infrastructure. The BEE to create and maintain a national online database of all the public charging stations in consultation with the state nodal agencies.
      • Tariff: Tariff not to exceed the average cost of supply of electricity till 2025. Separate metering arrangement to the PCS (Public Charging Station), so that the consumption can be recorded.
    Explore Courses for UPSC exam

    Top Courses for UPSC

    Consider the following statements about the Guidelines for Charging Infrastructure for the Electric Vehicles: The Ministry of Heavy Industries is the nodal agency for the roll-out of the EV public charging infrastructure. All public charging stations can obtain electricity from any generation company through open access. At least one charging station should be available in a grid of 3 km X 3 km. Which of the statements given above is/are correct?a)1 onlyb)2 and 3 onlyc)1 and 3 onlyd)1, 2 and 3Correct answer is option 'B'. Can you explain this answer?
    Question Description
    Consider the following statements about the Guidelines for Charging Infrastructure for the Electric Vehicles: The Ministry of Heavy Industries is the nodal agency for the roll-out of the EV public charging infrastructure. All public charging stations can obtain electricity from any generation company through open access. At least one charging station should be available in a grid of 3 km X 3 km. Which of the statements given above is/are correct?a)1 onlyb)2 and 3 onlyc)1 and 3 onlyd)1, 2 and 3Correct answer is option 'B'. Can you explain this answer? for UPSC 2024 is part of UPSC preparation. The Question and answers have been prepared according to the UPSC exam syllabus. Information about Consider the following statements about the Guidelines for Charging Infrastructure for the Electric Vehicles: The Ministry of Heavy Industries is the nodal agency for the roll-out of the EV public charging infrastructure. All public charging stations can obtain electricity from any generation company through open access. At least one charging station should be available in a grid of 3 km X 3 km. Which of the statements given above is/are correct?a)1 onlyb)2 and 3 onlyc)1 and 3 onlyd)1, 2 and 3Correct answer is option 'B'. Can you explain this answer? covers all topics & solutions for UPSC 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Consider the following statements about the Guidelines for Charging Infrastructure for the Electric Vehicles: The Ministry of Heavy Industries is the nodal agency for the roll-out of the EV public charging infrastructure. All public charging stations can obtain electricity from any generation company through open access. At least one charging station should be available in a grid of 3 km X 3 km. Which of the statements given above is/are correct?a)1 onlyb)2 and 3 onlyc)1 and 3 onlyd)1, 2 and 3Correct answer is option 'B'. Can you explain this answer?.
    Solutions for Consider the following statements about the Guidelines for Charging Infrastructure for the Electric Vehicles: The Ministry of Heavy Industries is the nodal agency for the roll-out of the EV public charging infrastructure. All public charging stations can obtain electricity from any generation company through open access. At least one charging station should be available in a grid of 3 km X 3 km. Which of the statements given above is/are correct?a)1 onlyb)2 and 3 onlyc)1 and 3 onlyd)1, 2 and 3Correct answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for UPSC. Download more important topics, notes, lectures and mock test series for UPSC Exam by signing up for free.
    Here you can find the meaning of Consider the following statements about the Guidelines for Charging Infrastructure for the Electric Vehicles: The Ministry of Heavy Industries is the nodal agency for the roll-out of the EV public charging infrastructure. All public charging stations can obtain electricity from any generation company through open access. At least one charging station should be available in a grid of 3 km X 3 km. Which of the statements given above is/are correct?a)1 onlyb)2 and 3 onlyc)1 and 3 onlyd)1, 2 and 3Correct answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Consider the following statements about the Guidelines for Charging Infrastructure for the Electric Vehicles: The Ministry of Heavy Industries is the nodal agency for the roll-out of the EV public charging infrastructure. All public charging stations can obtain electricity from any generation company through open access. At least one charging station should be available in a grid of 3 km X 3 km. Which of the statements given above is/are correct?a)1 onlyb)2 and 3 onlyc)1 and 3 onlyd)1, 2 and 3Correct answer is option 'B'. Can you explain this answer?, a detailed solution for Consider the following statements about the Guidelines for Charging Infrastructure for the Electric Vehicles: The Ministry of Heavy Industries is the nodal agency for the roll-out of the EV public charging infrastructure. All public charging stations can obtain electricity from any generation company through open access. At least one charging station should be available in a grid of 3 km X 3 km. Which of the statements given above is/are correct?a)1 onlyb)2 and 3 onlyc)1 and 3 onlyd)1, 2 and 3Correct answer is option 'B'. Can you explain this answer? has been provided alongside types of Consider the following statements about the Guidelines for Charging Infrastructure for the Electric Vehicles: The Ministry of Heavy Industries is the nodal agency for the roll-out of the EV public charging infrastructure. All public charging stations can obtain electricity from any generation company through open access. At least one charging station should be available in a grid of 3 km X 3 km. Which of the statements given above is/are correct?a)1 onlyb)2 and 3 onlyc)1 and 3 onlyd)1, 2 and 3Correct answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Consider the following statements about the Guidelines for Charging Infrastructure for the Electric Vehicles: The Ministry of Heavy Industries is the nodal agency for the roll-out of the EV public charging infrastructure. All public charging stations can obtain electricity from any generation company through open access. At least one charging station should be available in a grid of 3 km X 3 km. Which of the statements given above is/are correct?a)1 onlyb)2 and 3 onlyc)1 and 3 onlyd)1, 2 and 3Correct answer is option 'B'. Can you explain this answer? tests, examples and also practice UPSC tests.
    Explore Courses for UPSC exam

    Top Courses for UPSC

    Explore Courses
    Signup for Free!
    Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
    10M+ students study on EduRev