Mechanical Engineering Exam  >  Mechanical Engineering Questions  >  In inventory planning, extra in ventory is un... Start Learning for Free
In inventory planning, extra in ventory is unnecessarily carried to the end of the planning period when using one of the following lot size decision policies:
[1998]
  • a)
    Lot for lot production
  • b)
    Economic Order Quantity (EOQ) lot size
  • c)
    Period Order Quantity (POQ) lot size
  • d)
    Part period total cost balancing
Correct answer is option 'B'. Can you explain this answer?
Most Upvoted Answer
In inventory planning, extra in ventory is unnecessarily carried to th...
Explanation:

Introduction:
Inventory planning involves determining the optimal quantity of inventory to be held in order to meet customer demand while minimizing costs. Various lot size decision policies are used in inventory planning to determine the quantity of inventory to be ordered or produced at a given time. These policies aim to strike a balance between carrying costs (the cost of holding inventory) and ordering costs (the cost of placing an order or setting up production).

Lot for Lot Production:
Lot for lot production is a lot size decision policy where the quantity produced or ordered is equal to the quantity demanded in each period. In other words, the lot size is set to match the demand exactly. This policy minimizes carrying costs as there is no extra inventory carried over to the next period. However, it can result in higher ordering costs if frequent orders or setups are required.

Economic Order Quantity (EOQ) Lot Size:
The Economic Order Quantity (EOQ) lot size is a lot size decision policy that calculates the optimal order quantity based on the tradeoff between carrying costs and ordering costs. It aims to minimize the total cost of inventory by finding the order quantity that minimizes the sum of carrying costs and ordering costs. The EOQ formula takes into account the annual demand, ordering cost, and carrying cost per unit.

Period Order Quantity (POQ) Lot Size:
The Period Order Quantity (POQ) lot size is a lot size decision policy where the quantity produced or ordered is fixed for a specific period, such as a month or a quarter. The lot size is determined based on the anticipated demand for that period. POQ can help in achieving economies of scale by producing or ordering in larger quantities, which can reduce per unit costs. However, it can lead to carrying extra inventory if the actual demand is lower than anticipated.

Part Period Total Cost Balancing:
Part Period Total Cost Balancing is a lot size decision policy that aims to balance the carrying costs and ordering costs by finding the lot size that minimizes the total cost over a specific planning period. It takes into account the inventory carrying costs and ordering costs for each period in the planning horizon. The lot size is determined by comparing the total costs associated with different lot sizes.

Explanation of Correct Answer:
The correct answer is option 'B' - Economic Order Quantity (EOQ) lot size. EOQ lot size policy is considered the optimal lot size decision policy as it takes into account the tradeoff between carrying costs and ordering costs. It aims to minimize the total cost of inventory by finding the order quantity that balances these costs. By calculating the optimal order quantity, EOQ avoids the carrying of unnecessary extra inventory to the end of the planning period, reducing carrying costs. EOQ lot size policy is widely used in inventory planning due to its cost-effectiveness and efficiency.

In Summary:
- Lot for lot production minimizes carrying costs but can result in higher ordering costs.
- EOQ lot size policy calculates the optimal order quantity to minimize total costs and avoids carrying unnecessary extra inventory.
- POQ lot size policy can lead to carrying extra inventory if the actual demand is lower than anticipated.
- Part period total cost balancing aims to balance carrying costs and ordering costs by finding the lot size that minimizes the total cost over a specific planning period.
Free Test
Community Answer
In inventory planning, extra in ventory is unnecessarily carried to th...
  • A decision about how much to order has great significance in inventory management.
  • The quantity to be purchased should neither be small nor big because the costs of buying and carrying materials are very high.
  • Economic order quantity is the size of the lot to be purchased which is economically viable.
  • This is the number of materials that can be purchased at minimum costs.
  • Generally, economic order quantity is the point at which inventory carrying costs are equal to order costs.
  • First, EOQ policy is not optimal in MRP system because the assumptions of constant demand are not met.
  • As compared with a lot-for-lot policy, the setup costs for an EOQ policy will generally be lower and holding costs will be higher.
  • Second, in an EOQ policy, extra inventory is unnecessarily carried to the end of the planning horizon.
At EOQ:
Ordering cost = Holding cost
Attention Mechanical Engineering Students!
To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

In inventory planning, extra in ventory is unnecessarily carried to the end of the planning period when using one of the following lot size decision policies:[1998]a)Lot for lot productionb)Economic Order Quantity (EOQ) lot sizec)Period Order Quantity (POQ) lot sized)Part period total cost balancingCorrect answer is option 'B'. Can you explain this answer?
Question Description
In inventory planning, extra in ventory is unnecessarily carried to the end of the planning period when using one of the following lot size decision policies:[1998]a)Lot for lot productionb)Economic Order Quantity (EOQ) lot sizec)Period Order Quantity (POQ) lot sized)Part period total cost balancingCorrect answer is option 'B'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about In inventory planning, extra in ventory is unnecessarily carried to the end of the planning period when using one of the following lot size decision policies:[1998]a)Lot for lot productionb)Economic Order Quantity (EOQ) lot sizec)Period Order Quantity (POQ) lot sized)Part period total cost balancingCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for In inventory planning, extra in ventory is unnecessarily carried to the end of the planning period when using one of the following lot size decision policies:[1998]a)Lot for lot productionb)Economic Order Quantity (EOQ) lot sizec)Period Order Quantity (POQ) lot sized)Part period total cost balancingCorrect answer is option 'B'. Can you explain this answer?.
Solutions for In inventory planning, extra in ventory is unnecessarily carried to the end of the planning period when using one of the following lot size decision policies:[1998]a)Lot for lot productionb)Economic Order Quantity (EOQ) lot sizec)Period Order Quantity (POQ) lot sized)Part period total cost balancingCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of In inventory planning, extra in ventory is unnecessarily carried to the end of the planning period when using one of the following lot size decision policies:[1998]a)Lot for lot productionb)Economic Order Quantity (EOQ) lot sizec)Period Order Quantity (POQ) lot sized)Part period total cost balancingCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of In inventory planning, extra in ventory is unnecessarily carried to the end of the planning period when using one of the following lot size decision policies:[1998]a)Lot for lot productionb)Economic Order Quantity (EOQ) lot sizec)Period Order Quantity (POQ) lot sized)Part period total cost balancingCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for In inventory planning, extra in ventory is unnecessarily carried to the end of the planning period when using one of the following lot size decision policies:[1998]a)Lot for lot productionb)Economic Order Quantity (EOQ) lot sizec)Period Order Quantity (POQ) lot sized)Part period total cost balancingCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of In inventory planning, extra in ventory is unnecessarily carried to the end of the planning period when using one of the following lot size decision policies:[1998]a)Lot for lot productionb)Economic Order Quantity (EOQ) lot sizec)Period Order Quantity (POQ) lot sized)Part period total cost balancingCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice In inventory planning, extra in ventory is unnecessarily carried to the end of the planning period when using one of the following lot size decision policies:[1998]a)Lot for lot productionb)Economic Order Quantity (EOQ) lot sizec)Period Order Quantity (POQ) lot sized)Part period total cost balancingCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev